Knowledge

Resource adequacy

Source 📝

159:
to avoid building its own spare generation capacity to satisfy the RA and instead purchase "ICAP credits" from some other company in the pool that already has such capacity (the probability of two companies falling below their RA targets simultaneously is considered to be negligible). The ICAP
179:, but complicated in case of hydropower and renewables, as the available energy from these sources tend to be highly correlated over a large geographical area. Incorporation of solar and wind generators into firm capacity frameworks presents challenges due to their intermittency (cf. 215:
does not immediately affect the consumption and becomes punitive. "Energy-only markets have the potential to result in an equilibrium point for the market that is not consistent with what users and regulators want to see", so every wholesale electricity market in the world relies on
243:(in the form of a lack of investment into generation facilities). Per Wolak, lower offer caps complicate the situation, as do the electrification of space heating, adoption of electric vehicles, and an increasing share of the 131:. These monopoly utilities had an incentive to overestimate the peak demand in order to build more capacity and justify an increase in their regulator-approved rates. Lack of capacity generally was not a problem. 79:, typically 1 day in 10 years. IRM is used to measure the adequacy of the generation capacity and serves as a guide to evaluate the needs for the capacity changes. When discussing the future capacity needs, the 207:
at market-determined prices. However, customers of electric utilities frequently do not have an ability to shift their consumption away from high-priced periods (consider, for example, the
175:
RA contracts for 110-120% of its annual peak power. As any capacity-based scheme, this approach relies on credible estimates of firm capacity. These estimates are easy for conventional
164:, which also requires the suppliers to offer all available resources on a day-ahead basis ("must-offer"). If a unit that received the ICAP payment is called upon, it must run. 96: 240: 212: 128: 139:
In a deregulated grid some sort of incentives are necessary for market participants to build and maintain generation and transmission resources that
622: 314: 143:
some day be called upon to maintain the grid balance, but most of the time are idled and do not produce revenue from the sale of electricity. An
84: 239:, while the rolling blackouts equally penalize the LSEs that did procure sufficient resources and the ones that did not. This results in a 203:
nature of electricity production is fairly typical among other industries that have no problems recovering production costs and generating
75:
Installed reserve margin (IRM) is the amount of the generating capacity in excess of the expected load, calculated to satisfy the
120: 522: 161: 611: 99:(ORM). The ORM calculations account for the current generation and transmission outages and assume that all the 646: 557: 64: 127:, done by the utility itself, additional expenses were negotiated with regulators that were representing the 124: 152: 40: 47:
at any time to accommodate major equipment failures (e.g., a disconnection of a nuclear power unit or a
538:
Long-Term Resource Adequacy in Wholesale Electricity Markets with Significant Intermittent Renewables
536: 244: 52: 306: 76: 60: 176: 48: 223:
Wolak points to the combination of offer caps and electricity shortage mitigation strategies (
577: 195:
Electricity markets are quite unique in their need for an RA mechanism, even though the high
217: 204: 8: 602: 232: 168: 104: 598: 56: 585: 545: 224: 180: 100: 44: 589: 578:"Model-Limited Choice and the Determination of the Need for Generation Capacity" 55:
sources (e.g, wind dying down). The adequacy standard should satisfy the chosen
236: 184: 43:. For example, sufficient unused generation capacity shall be available to the 28: 640: 208: 200: 172: 92: 88: 32: 35:
to satisfy the end-user power demand at any time (typically an issue at the
558:"Too Much Is Never Enough: Constructing Electricity Capacity Market Demand" 227:) leading to the need for an RA mechanism (Wolak calls this dependency a 36: 196: 156: 582:
Regulating Power: The Economics of Electricity in the Information Age
549: 108: 87:(NERC) by default uses the 15% reserve target for the mostly 155:
to maintain the RA requirements. ICAP allows a member of a
355: 343: 160:
obligation is called upon not by a purchaser, but by the
476: 474: 437: 435: 486: 386: 384: 382: 286: 264: 262: 260: 420: 367: 333: 331: 498: 471: 459: 447: 432: 408: 396: 379: 257: 107:loads are connected. ORM is thus lower than IRM ( 638: 328: 274: 114: 623:North American Electric Reliability Corporation 599:"PJM Manual 20: PJM Resource Adequacy Analysis" 315:North American Electric Reliability Corporation 85:North American Electric Reliability Corporation 235:(LSEs) to underpay for the electricity on the 555: 361: 349: 70: 231:): the price cap creates an incentive for 556:Aagaard, Todd; Kleit, Andrew N. (2022). 544:, National Bureau of Economic Research, 575: 292: 639: 211:needs). Under these circumstances the 121:vertically integrated electric utility 534: 530:. Stanford Washington Research Group. 520: 504: 492: 480: 465: 453: 441: 426: 414: 402: 390: 373: 268: 612:"2013 Summer Reliability Assessment" 609: 337: 95:ones. The IRM is different from the 596: 280: 190: 134: 13: 524:Resource Adequacy - Alphabet Soup! 521:Tezak, Christine (June 24, 2005). 162:regional transmission organization 14: 658: 183:) and might require the usage of 304: 584:. Springer US. pp. 77–97. 298: 145:installed capacity requirement 1: 535:Wolak, Frank A. (July 2021), 250: 167:Typical regulator requires a 115:Vertically integrated utility 83:term is used for the metric. 125:integrated resource planning 39:). RA is a component of the 7: 605:Resource Adequacy Planning. 590:10.1007/978-1-4615-3258-3_5 153:independent system operator 41:electrical grid reliability 10: 663: 514: 111:allows ORM as low as 3%). 245:variable renewable energy 53:variable renewable energy 571:(1). Washington: 79–124. 362:Aagaard & Kleit 2022 350:Aagaard & Kleit 2022 97:operating reserve margin 77:loss of load expectation 71:Installed reserve margin 61:loss of load expectation 597:PJM (August 25, 2021). 229:reliability externality 81:planning reserve margin 67:(so called "1-in-10"). 49:high-voltage power line 576:Pechman, Carl (1993). 31:is the ability of the 647:Electricity economics 241:missing money problem 233:load-serving entities 91:systems, 10% for the 307:"M-1 Reserve Margin" 205:return on investment 177:dispatchable sources 169:load serving entity 123:RA was part of the 105:interruptible power 565:Energy Law Journal 151:) is used by some 27:) in the field of 610:NERC (May 2013). 225:rolling blackouts 129:captive customers 119:In the case of a 65:1 day in 10 years 57:reliability index 17:Resource adequacy 654: 633: 631: 629: 616: 606: 593: 572: 562: 552: 543: 531: 529: 508: 502: 496: 490: 484: 478: 469: 463: 457: 451: 445: 439: 430: 424: 418: 412: 406: 400: 394: 388: 377: 371: 365: 359: 353: 347: 341: 335: 326: 325: 323: 321: 302: 296: 290: 284: 278: 272: 266: 213:scarcity pricing 191:Price cap and RA 135:Deregulated grid 59:, typically the 662: 661: 657: 656: 655: 653: 652: 651: 637: 636: 627: 625: 614: 560: 541: 527: 517: 512: 511: 503: 499: 495:, pp. 5–6. 491: 487: 479: 472: 464: 460: 452: 448: 440: 433: 425: 421: 413: 409: 401: 397: 389: 380: 376:, pp. 2–3. 372: 368: 360: 356: 348: 344: 336: 329: 319: 317: 303: 299: 291: 287: 279: 275: 267: 258: 253: 193: 181:Capacity credit 137: 117: 101:demand response 73: 51:) and drops in 45:electrical grid 25:supply adequacy 12: 11: 5: 660: 650: 649: 635: 634: 607: 594: 573: 553: 550:10.3386/w29033 532: 516: 513: 510: 509: 497: 485: 470: 458: 446: 431: 419: 407: 395: 378: 366: 354: 342: 327: 297: 285: 273: 255: 254: 252: 249: 237:forward market 220:in some form. 192: 189: 185:energy storage 136: 133: 116: 113: 72: 69: 29:electric power 9: 6: 4: 3: 2: 659: 648: 645: 644: 642: 624: 620: 613: 608: 604: 600: 595: 591: 587: 583: 579: 574: 570: 566: 559: 554: 551: 547: 540: 539: 533: 526: 525: 519: 518: 506: 501: 494: 489: 482: 477: 475: 467: 462: 455: 450: 443: 438: 436: 429:, p. 10. 428: 423: 416: 411: 404: 399: 392: 387: 385: 383: 375: 370: 364:, p. 86. 363: 358: 352:, p. 89. 351: 346: 339: 334: 332: 316: 312: 308: 301: 295:, p. 77. 294: 289: 283:, p. 13. 282: 277: 270: 265: 263: 261: 256: 248: 246: 242: 238: 234: 230: 226: 221: 219: 214: 210: 209:space heating 206: 202: 201:marginal cost 198: 188: 186: 182: 178: 174: 173:firm capacity 170: 165: 163: 158: 154: 150: 146: 142: 132: 130: 126: 122: 112: 110: 106: 102: 98: 94: 93:hydroelectric 90: 89:thermal power 86: 82: 78: 68: 66: 62: 58: 54: 50: 46: 42: 38: 34: 33:electric grid 30: 26: 22: 18: 626:. Retrieved 618: 581: 568: 564: 537: 523: 507:, p. 5. 500: 488: 483:, p. 6. 468:, p. 3. 461: 456:, p. 4. 449: 444:, p. 2. 422: 417:, p. 9. 410: 405:, p. 8. 398: 393:, p. 7. 369: 357: 345: 340:, p. 3. 318:. Retrieved 310: 300: 293:Pechman 1993 288: 276: 271:, p. 2. 228: 222: 194: 171:to purchase 166: 148: 144: 140: 138: 118: 80: 74: 24: 20: 16: 15: 37:peak demand 505:Wolak 2021 493:Wolak 2021 481:Wolak 2021 466:Tezak 2005 454:Wolak 2021 442:Wolak 2021 427:Wolak 2021 415:Wolak 2021 403:Wolak 2021 391:Wolak 2021 374:Tezak 2005 269:Tezak 2005 251:References 218:offer caps 197:fixed cost 157:power pool 63:(LOLE) of 338:NERC 2013 247:sources. 641:Category 628:10 April 619:nerc.com 320:10 April 311:nerc.com 281:PJM 2021 515:Sources 23:, also 305:NERC. 615:(PDF) 561:(PDF) 542:(PDF) 528:(PDF) 199:/low 109:CAISO 630:2023 322:2023 149:ICAP 103:and 603:PJM 586:doi 546:doi 141:may 643:: 621:. 617:. 601:. 580:. 569:43 567:. 563:. 473:^ 434:^ 381:^ 330:^ 313:. 309:. 259:^ 187:. 21:RA 632:. 592:. 588:: 548:: 324:. 147:( 19:(

Index

electric power
electric grid
peak demand
electrical grid reliability
electrical grid
high-voltage power line
variable renewable energy
reliability index
loss of load expectation
1 day in 10 years
loss of load expectation
North American Electric Reliability Corporation
thermal power
hydroelectric
operating reserve margin
demand response
interruptible power
CAISO
vertically integrated electric utility
integrated resource planning
captive customers
independent system operator
power pool
regional transmission organization
load serving entity
firm capacity
dispatchable sources
Capacity credit
energy storage
fixed cost

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.