Knowledge

Shaft sinking

Source 📝

659:. The activities of the sinking cycle (excavation, installation of temporary ground support, placement of the shaft lining and extending shaft services) all take place in this phase of construction. In a shaft where there are to be multiple working levels, shaft stations and station stubs (short lengths of a horizontal tunnel leading away from the station) will be developed by the sinkers on the way down. As the equipment to excavate these stations must be small enough to fit through the openings in the Galloway, the rate of advance in developing the station stubs is typically low, compared to what can be achieved with full-size mining equipment, so station stubs are typically kept as short as possible. 229: 615:. The pre-sink is the excavation and support of the first 60 – 100 metres of the shaft barrel, often completed with smaller equipment such as handheld, pneumatic drilling equipment to drill holes for basting and ground support and mini-excavators for mucking. During the pre-sink, hoisting of muck and equipment is usually performed by a mobile crane on the surface. It is necessary to sink this part of the shaft first so that the Galloway, a multi-level working platform may be installed with enough vertical distance to the shaft bottom that it will not be damaged by 38: 365: 49: 319: 451: 647:
means of winches, which move slowly and are rated for significant loads, while the sinking buckets (or kibbles) are moved in the shaft by the sinking hoist, which moves quickly and is rated for less load than the winches. To protect the hoist(s) and winches and the sensitive electronics which are used to control their operation they are normally installed inside a build called a hoist (or winder) house.
600:
down to bedrock, inside which the shaft collar will be constructed. Having the loads imposed by the collar, headframe and hoisting plant transferred into solid rock is necessary to prevent unplanned subsidence. Where the depth of bedrock is too great to for a box cut to be economically viable, or the
570:
as the project team repeats the same series of activities over and over in what is called "the sinking cycle", eventually approaching the theoretical maximum rate for that sinking set up over time. The use of experienced shaft sinkers is necessary to reduce the length of this learning curve and thus
665:
Once the shaft reaches the final design depth, the shaft is stripped of any temporary services, the Galloway cut up or modified to suit the installation of the permanent shaft set-up, the shaft sets (if required) installed and the headframe / winders modified to allow for permanent hoisting. Any
646:
With the collar constructed and the Galloway installed the headframe and hoist (or winder) houses may be constructed and the hoist and winch ropes installed. Headframes may be either steel or concrete and their design will determine how they are constructed. The Galloway is moved in the shaft by
421:
The shaft liner does not reach right to the bottom of the shaft during sinking, but lags behind by a fixed distance. This distance is determined by the methodology of excavation and the design thickness of the permanent liner. To ensure the safety of persons working on the shaft bottom temporary
687:
Traditionally, sinking contractors would build a temporary headframe for the sinking set-up, which would then be dismantled to make way for a permanent headframe. With the growth in complexity and duration of shaft sinking projects over time it has become more common to incorporate more of the
437:
For this reason, and to minimise the number of persons on the shaft bottom a number of projects have successfully switched to shotcrete for this temporary lining. Research and development in this area is focusing on the robotic application of shotcrete and the commercialisation of thin sprayed
639:
located on the surface. The Galloway allows sinkers to efficiently work on different levels as required by the various tasks of the sinking cycle. It is typical for the Galloway to be constructed off to one side of the shaft and lowered into the pre-sink with a crane in as complete a state as
258:
At ground level beneath and around the headframe is the Shaft Collar (also called the Bank or Deck), which provides the foundation necessary to support the weight of the headframe and provides a means for workers, materials and services to enter and exit the shaft. Collars are usually massive
691:
With the advancements made in raise boring technology, raise borers have been used to create a pilot hole for shaft sinking, where access exists at the bottom of the new shaft, in this case the sinking phase is dedicated to enlarging this pilot hole to full diameter (a process usually called
520:
to the surface. Smaller mining operations use a skip mounted underneath the cage, rather than a separate device, while some large mines have separate shafts for the cage and skips. The third compartment is used for an emergency exit; it may house an auxiliary cage or a system of ladders. An
383:
Final choice of shaft lining is dependent on the geology of the rock which the shaft passes through, some shafts have several liners sections as required Where shafts are sunk in very competent rock there may be no requirement for lining at all, or just the installation of welded mesh and
380:. The shaft lining performs several functions; it is first and foremost a safety feature preventing loose or unstable rock from falling into the shaft, then a place for shaft sets to bolt into, and lastly a smooth surface to minimise resistance to airflow for ventilation. 128:), dimensions and depth of mine shafts vary greatly in response to the specific needs of the mine they are part of and the geology they are sunk through. For example, in North and South America, smaller shafts are designed to be rectangular in plan view with 478:
and top hat sections. Top hat sections offer a number of advantages over hollow structural sections including simpler installation, improved corrosion resistance and increased stiffness. Mine conveyances run on the guides in a similar way to how a
78:
Shaft sinking is one of the most difficult of all mining development methods: restricted space, gravity, groundwater and specialized procedures make the task quite formidable. Shafts may be sunk by conventional drill and blast or mechanised means.
688:
permanent shaft set-up into the sinking phase. This results in a reduced overall project duration, as for example, if the service piping used to sink the shaft does not need to be stripped out to make way for permanent piping.
189:
A shaft may be either vertical or inclined (between 80 and 90 degrees to the horizontal), although most modern mine shafts are vertical. If access exists at the bottom of the proposed shaft, and ground conditions allow, then
588:
Although significant emphasis is placed on the rate of progress of a project sinking cycle by shaft sinkers, sinking is only one of a number of phases in the conventional construction of a new shaft, as follows;
558:
The lowest point in a sinking shaft is known as the "shaft bottom". Shaft projects differ from some other forms of mine development in that all activities that take place on the shaft bottom become part of the
209:". Many other global mining jurisdictions have adopted this rule and shafts are therefore often found in pairs (although there are multiple alternative methods of providing a second means of egress). 205:
where the single shaft at the mine became blocked, the United Kingdom made single shaft mines illegal in 1862, establishing the practice that all underground mines must have a "
540:. One or more of the compartments discussed above may be used for air intake, while others may be used for exhaust. Where this is the case a steel or concrete wall called a 105:
The modern shaft sinking industry is gradually shifting further towards greater mechanisation. Recent innovations in the form of full-face shaft boring (akin to a vertical
751: 505:, a conveyance used for moving workers and supplies below the surface, which is suspended from the hoist on steel wire rope. It functions in a similar manner to an 255:
wheel (with the hoist motor mounted on the ground). The headframe will also typically contain bins for storing ore being transferred to the processing facility.
289:, sometimes for many kilometers. The lowest shaft station is most often the point where rock leaves the mine levels and is transferred to the shaft, if so a 139:
Mine shafts may be used for a variety of purposes, including as a means of escape in the event of an emergency underground and allowing for the movement of:
285:(or inset) which allows men, materials and services to enter and exit the shaft. From the station tunnels (drifts, galleries or levels) extend towards the 640:
possible. Once in place, the Galloway is "chaired" (suspended from the shaft collar) while the headframe is built above, often protected by a bulkhead.
676:
As with the depth and design of shafts, significant variations may exist in this sequence depending on local conditions. For example, shafts in the
566:
It is typical for progress (the "sinking rate") in the sinking phase (that is excavation, ground support and lining) of a shaft project to follow a
82:
Historically, mine shaft sinking has been among the most dangerous of all the mining occupations and the preserve of mining contractors called
304:
typically connects the bottom of the shaft with the rest of the mine, this ramp often contains the mine's water handling facility, called the
180:. Small shafts may be excavated upwards from within an existing mine as long as there is access at the bottom, in which case they are called 672:
The Permanent set-up must then be commissioned to ensure that all parts are operating as planned before being handed over to the new owner.
347: 1029: 352: 52:
A plan-view schematic of a mine shaft showing cage and skip compartments. Services may be housed in either of the four open compartments.
509:. Cages may be single-, double-, or rarely triple-deck, always having multiple redundant safety systems in case of unexpected failure. 546:
is installed between the two compartments to separate the air flow. At many mines there are one or more complete additional separate
746: 696:(waste rock) from sinking falls down the pilot hole and is handled using existing mine infrastructure off critical path. 635:
The Galloway (also known as a Sinking Stage or Scaffold) is a multi-level working platform, suspended in the shaft from
414:
and even squash balls have been required by specific circumstances. In extreme cases, particularly when sinking through
206: 956:
du Judeel, G; Keyter and Harte (April 2012). "Shaft Lining design for a potash shaft in rock salts at large depths".
895: 800: 121:, which are "sunk" as a means of accessing an underground ore body, during the development of an underground mine. 629:. From the bottom of the box cut, the shaft collar is constructed bottom up in a planned series of concrete pours. 1022: 684:
is both strong and close to the surface. This reduces the amount of time required to establish the shaft collar.
220:, which has a depth of 2991 meters. Along with its twin ventilation shafts, it took ten years to sink and equip. 1113: 1108: 741: 736: 563:
for the project schedule. The infrastructure required to sink a shaft is referred to as "the sinking set-up".
63:
is the action of excavating a mine shaft from the top down, where there is initially no access to the bottom.
877: 430:) is among the most physically challenging parts of the shaft sinking cycle as bolts must be installed using 377: 997: 537: 296:
Beneath the lowest shaft station the shaft continues on for some distance, this area is referred to as the
1243: 1238: 1085: 1015: 31: 17: 475: 271:
or casing is incorporated into the collar to ensure the proper flow of air into and out of the mine.
202: 64: 912: 247:(or winding tower, poppet head or pit head) which stands above the shaft. Depending on the type of 1002: 293:
is excavated on one side of the shaft at this location to allow transfer facilities to be built.
228: 458:
Where the shaft is to be used for hoisting it is frequently split into multiple compartments by
376:
Many (although not all) shafts are lined following excavation and the installation of temporary
1167: 653:
The Sinking set-up must then be commissioned to ensure that all parts are operating as planned.
620: 816: 597: 578:
Getting the various components of the sinking set-up correct and installed at the right time.
106: 1065: 975:
Sanders, D. (April 2012). "New Waterproofing Technologies for Vertical Shaft Construction".
410:
segments have all been used at one time or another. Additionally, the use of materials like
560: 480: 212:
Currently, the deepest continuous single-lift mine shaft in the world is the main shaft at
8: 260: 217: 887: 274:
Beneath the collar the part of the shaft which continues into the ground is called the
149:
Mine services (such as compressed air, water, backfill, power, communications and fuel)
891: 796: 68: 37: 939:"Sinking Contractor's Close Out Presentation on the completion of South Deep Shafts" 1202: 1080: 692:"slashing"). This methodology can be considerably faster than full face sinking as 513: 407: 369: 264: 842: 596:. A box cut is a large square or rectangular excavation typically completed using 388:. The material of choice for shaft lining is mass concrete which is poured behind 71:
projects, differ greatly in execution method from deep shafts, typically sunk for
1207: 1172: 1149: 1055: 677: 364: 237: 213: 83: 251:(or winder) used, the top of the headframe will either house a hoist motor or a 109:) have shown promise but the use of this method is, as of 2019, not widespread. 48: 1197: 1177: 1047: 883: 606: 602: 567: 486:
Some shafts do not use guide beams but instead utilize steel wire rope (called
329: 248: 181: 1232: 1217: 1070: 731: 693: 194:
may be used to excavate the shaft from the bottom up; such shafts are called
166:
When the top of the excavation is the ground surface, it is referred to as a
42: 318: 1134: 1129: 711: 706: 581:
Having experienced people involved from as early in the project as possible
522: 268: 99: 27:
Process of excavating a vertical or near vertical tunnel from the top down
1212: 1075: 726: 530: 483:
runs on its rails, both having wheels which keep them securely in place.
281:
At locations where the shaft barrel meets horizontal workings there is a
191: 584:
Using the available time on the shaft bottom as efficiently as possible.
418:, composite liners consisting of two or more materials may be required. 721: 526: 236:, Katowice. Currently functioning as observation tower and part of the 716: 431: 423: 403: 395: 385: 334: 244: 125: 1007: 938: 243:
The most visible feature of a traditionally-built mine shaft is the
1144: 601:
bedrock is not strong enough, civil engineering techniques such as
542: 506: 450: 422:
ground support is installed, usually consisting of welded mesh and
133: 1159: 777: 681: 616: 498:
or wheel of cheese) as these are easier to maintain and replace.
495: 439: 411: 91: 943:
Proceedings of the Third South African Conference on Base Metals
680:
generally do not need a deep and complex shaft collar since the
310:, as water will naturally flow to the lowest point in the mine. 170:; when the top of the excavation is underground, it is called a 1060: 1038: 415: 342: 286: 252: 129: 118: 87: 72: 263:
structures with more than one level. If the shaft is used for
636: 463: 399: 172: 95: 490:) kept in tension by massive weights at shaft bottom called 426:. The installation of the temporary ground support (called 306: 955: 843:"Case Study - Blind Shaft Sinking for BHP Jansen Project" 633:
Galloway (Sinking Stage) Construction & Installation.
517: 156: 752:
Repurposing old mine shafts for energy storage purposes
666:
permanent conveyances will be installed at this stage.
86:. Today shaft sinking contractors are concentrated in 860:
Gleeson, D (September 2018). "That Sinking Feeling".
392:
in lifts of 6 m as the shaft advances (gets deeper).
521:
additional compartment houses mine services such as
474:. For steel shaft guides, the main two options are 501:The largest compartment is typically used for the 454:Typical mine cage, located in Harzbergbau, Germany 132:supports. Larger shafts are round in plan and are 571:the duration of the project as much as possible. 1230: 609:may be used to create a deep foundation instead. 30:"Mineshaft" redirects here. For other uses, see 574:Key to a successful shaft sinking project are: 512:The second compartment is used for one or more 817:"A Glossary of Mining Terms used in mid 1800s" 795:. John Wiley and Sons Inc. pp. 282, 284. 1023: 466:. Vertical members in a shaft set are called 874: 663:Shaft Equipping & Headframe Changeover. 536:A second reason to divide the shaft is for 1030: 1016: 117:Mine shafts are vertical or near-vertical 774:Underground Drilling and Loading Handbook 644:Headframe & Hoist House Construction. 840: 462:, these may be made of either timber or 449: 363: 317: 227: 223: 47: 36: 974: 936: 859: 790: 771: 14: 1231: 793:Introductory Mining Engineering 2nd ed 1037: 1011: 809: 553: 445: 890:: McIntosh Engineering. p. 92. 155:Broken rock (in the form of payable 998:Abandoned Mine Shafts & Tunnels 913:"Work: The Hartley Mining Disaster" 910: 747:Glossary of coal mining terminology 550:with separate head gear and cages. 494:(because of their resemblance to a 24: 875:De la Vergne, Jack (August 2003). 25: 1255: 991: 525:and pipes for transfer of water, 470:, horizontal members are called 968: 945:: 455 – via Academia.edu. 670:Commissioning Permanent Set Up. 313: 162:Or any combination of the above 949: 930: 904: 868: 853: 834: 784: 765: 742:Underground mining (soft rock) 737:Underground mining (hard rock) 112: 13: 1: 977:Shaft Design and Construction 958:Shaft Design and Construction 758: 651:Commissioning Sinking Set-Up. 780:: Tamrock Corp. p. 173. 772:Puhakka, Tuula, ed. (1997). 7: 791:Hartman, Howard L. (2002). 699: 10: 1260: 878:Hard Rock Miner's Handbook 476:hollow structural sections 216:in South Africa, owned by 32:Mineshaft (disambiguation) 29: 1190: 1158: 1122: 1101: 1094: 1046: 203:Hartley Colliery disaster 41:Abandoned mine shafts in 207:a second means of egress 159:, or non payable waste) 847:SDC 2019 - Proceedings 455: 373: 361: 240: 53: 45: 911:BBC (February 2004), 598:earthmoving equipment 453: 434:powered rock drills. 367: 321: 231: 224:Parts of a mine shaft 107:tunnel boring machine 67:, typically sunk for 51: 40: 862:International Mining 841:Rennkamp, P (2019). 481:steel roller coaster 300:. A tunnel called a 1086:Mountaintop removal 937:Douglas, A (2005). 627:Collar Construction 523:high voltage cables 372:in Wodzisław Śląski 261:reinforced concrete 218:Gold Fields Limited 1244:Mining engineering 1239:Underground mining 594:Box Cut Excavation 554:Shaft construction 456: 446:Shaft compartments 374: 362: 241: 54: 46: 1226: 1225: 1186: 1185: 69:civil engineering 16:(Redirected from 1251: 1099: 1098: 1081:Hydraulic mining 1032: 1025: 1018: 1009: 1008: 1003:Top Hat Sections 985: 984: 972: 966: 965: 953: 947: 946: 934: 928: 927: 926: 924: 908: 902: 901: 872: 866: 865: 857: 851: 850: 838: 832: 831: 829: 827: 813: 807: 806: 788: 782: 781: 769: 548:auxiliary shafts 516:, used to hoist 408:precast concrete 370:1 Maja Coal Mine 368:Sheave wheel of 265:mine ventilation 21: 1259: 1258: 1254: 1253: 1252: 1250: 1249: 1248: 1229: 1228: 1227: 1222: 1208:Deep sea mining 1182: 1168:Room and pillar 1154: 1118: 1090: 1042: 1036: 994: 989: 988: 973: 969: 954: 950: 935: 931: 922: 920: 917:Legacies – Tyne 909: 905: 898: 873: 869: 858: 854: 839: 835: 825: 823: 815: 814: 810: 803: 789: 785: 770: 766: 761: 756: 702: 678:Canadian Shield 603:diaphragm walls 556: 448: 360: 316: 238:Silesian Museum 232:Mine Headframe 226: 214:South Deep Mine 196:borehole shafts 152:Ventilation air 115: 35: 28: 23: 22: 15: 12: 11: 5: 1257: 1247: 1246: 1241: 1224: 1223: 1221: 1220: 1215: 1210: 1205: 1200: 1194: 1192: 1188: 1187: 1184: 1183: 1181: 1180: 1175: 1170: 1164: 1162: 1156: 1155: 1153: 1152: 1147: 1142: 1137: 1132: 1126: 1124: 1120: 1119: 1117: 1116: 1111: 1105: 1103: 1096: 1092: 1091: 1089: 1088: 1083: 1078: 1073: 1068: 1063: 1058: 1052: 1050: 1044: 1043: 1035: 1034: 1027: 1020: 1012: 1006: 1005: 1000: 993: 992:External links 990: 987: 986: 967: 948: 929: 903: 896: 867: 852: 833: 808: 801: 783: 763: 762: 760: 757: 755: 754: 749: 744: 739: 734: 729: 724: 719: 714: 709: 703: 701: 698: 674: 673: 667: 660: 654: 648: 641: 630: 624: 610: 607:concrete piles 586: 585: 582: 579: 568:learning curve 555: 552: 527:compressed air 492:cheese weights 447: 444: 398:, fibrecrete, 378:ground support 359: 358: 355: 350: 345: 340: 337: 332: 326: 315: 312: 291:loading pocket 225: 222: 201:Following the 164: 163: 160: 153: 150: 147: 144: 124:The shape (in 114: 111: 65:Shallow shafts 26: 9: 6: 4: 3: 2: 1256: 1245: 1242: 1240: 1237: 1236: 1234: 1219: 1218:Seabed mining 1216: 1214: 1211: 1209: 1206: 1204: 1201: 1199: 1196: 1195: 1193: 1189: 1179: 1176: 1174: 1171: 1169: 1166: 1165: 1163: 1161: 1157: 1151: 1148: 1146: 1143: 1141: 1138: 1136: 1133: 1131: 1128: 1127: 1125: 1121: 1115: 1112: 1110: 1107: 1106: 1104: 1100: 1097: 1093: 1087: 1084: 1082: 1079: 1077: 1074: 1072: 1069: 1067: 1064: 1062: 1059: 1057: 1054: 1053: 1051: 1049: 1045: 1040: 1033: 1028: 1026: 1021: 1019: 1014: 1013: 1010: 1004: 1001: 999: 996: 995: 982: 978: 971: 963: 959: 952: 944: 940: 933: 918: 914: 907: 899: 897:0-9687006-1-6 893: 889: 885: 881: 879: 871: 864:. p. 28. 863: 856: 848: 844: 837: 822: 818: 812: 804: 802:0-471-34851-1 798: 794: 787: 779: 775: 768: 764: 753: 750: 748: 745: 743: 740: 738: 735: 733: 732:Salt-concrete 730: 728: 725: 723: 720: 718: 715: 713: 710: 708: 705: 704: 697: 695: 689: 685: 683: 679: 671: 668: 664: 661: 658: 655: 652: 649: 645: 642: 638: 634: 631: 628: 625: 622: 618: 614: 611: 608: 604: 599: 595: 592: 591: 590: 583: 580: 577: 576: 575: 572: 569: 564: 562: 561:critical path 551: 549: 545: 544: 539: 534: 532: 528: 524: 519: 515: 510: 508: 504: 499: 497: 493: 489: 484: 482: 477: 473: 469: 465: 461: 452: 443: 441: 435: 433: 429: 425: 419: 417: 413: 409: 405: 401: 397: 393: 391: 387: 381: 379: 371: 366: 356: 354: 351: 349: 346: 344: 341: 338: 336: 333: 331: 328: 327: 325: 322:Schematic of 320: 311: 309: 308: 303: 299: 294: 292: 288: 284: 283:shaft station 279: 277: 272: 270: 266: 262: 256: 254: 250: 246: 239: 235: 230: 221: 219: 215: 210: 208: 204: 199: 197: 193: 187: 186: 184: 179: 175: 174: 169: 161: 158: 154: 151: 148: 145: 142: 141: 140: 137: 135: 131: 127: 122: 120: 110: 108: 103: 101: 97: 93: 89: 85: 80: 76: 74: 70: 66: 62: 61:shaft sinking 58: 50: 44: 43:Marl, Germany 39: 33: 19: 1139: 980: 976: 970: 961: 957: 951: 942: 932: 921:, retrieved 916: 906: 876: 870: 861: 855: 846: 836: 824:. Retrieved 820: 811: 792: 786: 773: 767: 712:Engine shaft 707:Drift mining 690: 686: 675: 669: 662: 656: 650: 643: 632: 626: 612: 593: 587: 573: 565: 557: 547: 541: 535: 511: 502: 500: 491: 487: 485: 471: 467: 459: 457: 436: 427: 420: 406:tubing, and 394: 389: 382: 375: 323: 314:Shaft lining 305: 301: 298:shaft bottom 297: 295: 290: 282: 280: 276:shaft barrel 275: 273: 269:plenum space 257: 242: 233: 211: 200: 195: 192:raise boring 188: 182: 177: 171: 167: 165: 138: 123: 116: 104: 100:South Africa 81: 77: 60: 57:Shaft mining 56: 55: 1213:Prospecting 1095:Sub-surface 983:(1): 90–92. 964:(1): 51–54. 880:, Edition 3 776:. Tampere, 727:Raise borer 538:ventilation 531:diesel fuel 390:shaft forms 113:Mine shafts 1233:Categories 1123:Directions 1041:techniques 759:References 722:Man engine 488:guide rope 460:shaft sets 424:rock bolts 386:rock bolts 348:false edge 75:projects. 18:Mine shaft 1203:Automated 1198:Abandoned 1114:Soft rock 1109:Hard rock 1061:Quarrying 923:3 October 888:North Bay 717:Headframe 657:Full Sink 503:mine cage 432:pneumatic 404:cast iron 396:Shotcrete 357:mineshaft 353:hoistroom 324:headframe 245:headframe 178:sub-shaft 146:Materials 126:plan view 1173:Longwall 1150:Borehole 1145:Bell pit 1076:Dredging 1056:Open-pit 826:10 April 700:See also 621:blasting 617:fly rock 613:Pre-Sink 543:brattice 507:elevator 442:liners. 287:ore body 234:Warszawa 134:concrete 1178:Retreat 1160:Stoping 1102:Classes 1048:Surface 778:Finland 682:bedrock 637:winches 619:during 496:truckle 472:buntons 440:polymer 428:bolting 412:bitumen 136:lined. 119:tunnels 92:Germany 84:sinkers 1071:Placer 1039:Mining 894:  821:GENUKI 799:  468:guides 416:halite 253:sheave 183:raises 143:People 130:timber 88:Canada 73:mining 1191:Other 1140:Shaft 1135:Slope 1130:Drift 1066:Strip 919:, BBC 884:Tempe 849:: 42. 514:skips 464:steel 400:brick 343:sheer 339:wheel 335:cable 330:hoist 249:hoist 176:or a 173:winze 168:shaft 96:China 925:2013 892:ISBN 828:2017 797:ISBN 694:muck 307:sump 302:ramp 267:, a 98:and 605:or 529:or 518:ore 157:ore 59:or 1235:: 979:. 960:. 941:. 915:, 882:. 845:. 819:. 533:. 402:, 278:. 198:. 102:. 94:, 90:, 1031:e 1024:t 1017:v 981:1 962:1 900:. 886:/ 830:. 805:. 623:. 185:. 34:. 20:)

Index

Mine shaft
Mineshaft (disambiguation)

Marl, Germany

Shallow shafts
civil engineering
mining
sinkers
Canada
Germany
China
South Africa
tunnel boring machine
tunnels
plan view
timber
concrete
ore
winze
raises.
raise boring
Hartley Colliery disaster
a second means of egress
South Deep Mine
Gold Fields Limited

Silesian Museum
headframe
hoist

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.