589:
Booterstown. However, in 1993 Derek Verso carried out a major rebuild. The organ was taken out of the chamber and placed in the south transept of the church. New casework was carefully constructed, modeled on the original front paneling. Old dummy pipes (stored away after the moving of the old organ to the chamber) were added to make a new side-facade. A great number of new stops were added (mostly to the Pedal, which is now very developed) and a new console was built retaining the original keyboards. It features a combination system, rare for a parish organ and very useful for repertoire and liturgy. The finished instrument is a powerful, free-standing organ, unique and one of the finest two-manuals in Dublin, at least. In 2017/18 the organ went under major refurbishment carried out by the Wells Kennedy Partnership.
493:
project would take some six months and cost €1,280,000. When safe access was put in place at the commencement of the contract, an inspection of the listed risk items revealed the need for several significant additional tasks, including woodworm treatment of the attic timbers and the removal of three further stained glass windows. These items necessitated four Section 5 Planning Applications being submitted to the Local Authority, as the church is a Protected Structure.
410:"The church of St Paul is of the gothic style of architecture and although not large, is extremely tasteful and imposing. The building measures 101 ft. 6 in. internally by 35 ft. 6 inches wide and 55 ft. 6 inches high to the ridge. It comprises a Nave and Chancel measuring 18 ft. 6 inches by 21 ft. It is in the Decorative style and has at the south west corner a tower and spire raising to a height of 120 ft. to the top of the iron Finial. 22: 503:
treatment and reinforcement, following which many of these broken natural slates had to be replaced; repaired cracks to the chimneys and added cowls; repaired extensive flashings in valleys and at parapet level; replaced and repaired guttering, hoppers and downpipes; removed, repaired and replaced crenulations on the east side.
472:
proceeds added to the restoration fund. In the present economic climate the select vestry decided on a low-key approach to fund raising. An appeal was launched and to date this has raised just over €60,000. It was decided that it was important to ask parishioners to make a contribution if they were in a position to do so.
530:
Heating works: Replaced all existing pipework and radiators with energy efficient three leaf radiators; installed extra boiler in Parish Centre dedicated to the church heating, with new 24 hour/7 day control, including thermostatic control in the church; provided independent hot water heaters for all
518:
Internal Stone Works: Removed old coating and conducted extensive repairs to stone traceries surrounding the glazing; removed efflorescence; sanded down all internal window surrounds; major repair to second door surrounds in the main foyer due to rusting hinges and cracks in stonework; plastered over
488:
As with all maintenance work, it is difficult to prepare documentation that defines all necessary works, especially when the scope of works cannot be evaluated until areas of the building have been opened up for inspection. However, based on the reports from our consultants, and detailed inspections,
437:
The existing church building form expresses clearly the several alterations and extensions to the original, resulting in several volumes that are interconnected, but with each retaining their own identity. The original building was designed in an architectural style that was popular at that time, and
522:
Glazing: Removed eight full stained-glass windows for repair in the studio; repaired 13 other stained and plain glass windows in situ; repaired glazing bars and repaired window openings; provided fully ventilated external secondary glazing to all windows – this was a preferred choice to the proposed
502:
Roof: Extensive repairs to slates and ridge tiles, including the replacement of the entire roof slates over the side transept; end gable steel straps had to be replaced. The lower 11 rows of slates were removed from both sides of the main roof to allow access to the lower rafter timbers for woodworm
458:
The sod was turned to begin construction work on a new parish centre within the grounds of the church on Sunday 19 March 2006. Obtaining planning permission was a torturous process which involved eight planning applications beginning in 2000. The new Parish Centre was officially opened by President
454:
The site for the parochial hall on Adelaide Road was obtained in 1910, with the building being opened in February 1912. The building remained in its original form until 1968 when an extension to its west side, to provide for a caretaker's apartment as well as additional meeting rooms and facilities,
445:
The organ was relocated to its present position in the side chapel in 1993. A number of changes were also made to the chancel, which was extended and made into a more flexible space. A robing room and parish office was created in the space vacated by the organ and a toilet installed at the back of
433:
In 1872 the first bells were installed in the tower with the peal being completed some five years later. Construction of the transept and organ enclosure of the eastern side of the building was completed in 1898. Construction of the chancel apse was completed in 1913, resulting in the building form
475:
The church was closed for 41 weeks while the work was being carried out. During that time the congregation worshipped in the parish centre and over Christmas and New Year had a number of joint services with their neighbours in Christ Church, Dun Laoghaire. They returned to St Paul's on Mothering
550:
Main Robing Room: Added new tea station to replace that in now demolished ladies robing room; outside of contract, Roy Watchorn kindly installed comprehensive new cupboards for storage of electric piano, choir music, robes and archive material over two floors; provided new storage space for other
543:
Fire Compliance: Removed all combustible cupboards and stored materials in critical areas; removed former ladies robing room; installed new fire extinguishers and new fire notices and signage; Installed new smoke detection and fire alarm system, together with emergency lighting system in case of
506:
Attic: Strengthened roof structure against cracking using bracing as cross ties; added splice plates to cracked rafters; cleaned out the ceiling rafters and applied woodworm treatment to the entire attic space in the main roof; insulated the main roof right down to the eaves level of the rafters;
554:
Decoration: Painted all surfaces except exposed stone and the organ, including ceilings, timber arches, pews, cupboards, sanctuary timber panels, new plastered areas; painted external louvres in tower and dormer vents and all ironware, including downpipes and main gates; laid new carpets only in
514:
External Stoneworks: Extensive repairs to the window traceries, including replacement and numerous patch repairs of the mullions, including older repairs to the stone around the windows; the Rose window needed special extra attention; repaired cracks in pinnacles, with many instances of pointing
471:
The cost of this major restoration work had amounted to €1.5 million. The bulk of this money came from reserves. There was money left following the sale of the old Parish Hall and the construction of the new parish centre. A house left to the parish by the late Odette Gatenby was sold and the
492:
With the appointment of Dave Stanley (who formerly assisted St Paul's in Kisiizi Hospital) as our Project Manager, work started in July 2012. We agreed the scope of the building contract and made some assessments on contingencies required to cover unforeseeable works. It was estimated that the
526:
Electrical works: Rewired all electrical cables and installed a new main circuit board; Installed new lighting throughout, including new pendant lights centred on the two aisles – lights are movement sensitive in ancillary rooms; installed new intruder alarms on all external doors and PIRs in
484:
In 2010, the Vestry, in consultation with its advisors, reduced the list of works to be carried out at the church to essential items – works necessary to protect and preserve the building fabric as well as the renewal of the heating and electrical installations, and ensuring compliance of the
588:
This organ was originally a Forster & Andrews built onto the back wall of the church. However, when the present sanctuary was added, the instrument was moved into a newly built chamber. At that stage was almost identical in specification to the organ of St Philip & St James' Church,
544:
fire; provided new fire doors at entrances and to robing room ; provided fire proof cupboard in northern entrance and for sound system in robing room; fire-proofed balcony and upper robing room stairs; installed fire control panel in Vestry; reversed hinges on some firedoors .
489:
our Design Team, led by fellow parishioner and conservation architect, Bryan Roe of Scott Tallon Walker, Architects, proceeded to obtain planning permission for the works and to prepare tender documentation which was then issued to several suitable building contractors for pricing.
510:
Spire: Replaced top stone and repaired/repainted the cross; removed the levelling shims and applied repair mortar in the damaged joint around the entire perimeter; undertook spot repairs to spire stone work, including pointing; replaced the lightning conductor.
441:
Dry rot was discovered in the church in 1980/81 over the organ, which was then located in the chancel. At this time the plaster was removed from the walls in the nave and the previous lighting and heating system installed.
383:
The Church of St Paul Glenageary is one of seven churches that were built in the old Parish of Monkstown in County Dublin. The cost of its erection was provided out of a bequest by a Miss Shannon, a wealthy lady of
571:
choir with around 16 members. They sing Choral Eucharist twice a month, and are regularly invited to sing in neighbouring parishes and diocesan cathedrals. In 2015, 2016 and 2017 the choir undertook a tour to the
374:
style. The church has had a distinguished history of both rectors and curates, with many of them going on to senior posts in the Church of Ireland and further afield. The current rector is The Rev Gary Dowd.
438:
reflects good design practice of the day. The steep pitched roofs, and the clear detailing and rough cut stonework tied together by strong horizontal banding creates a strong identity for the church.
683: 499:
The schedule of works below will give an idea of the extent of the works and enable us all to appreciate the width of the scope, as much of the works carried out are not readily visible.
673: 496:
Despite the time needed for these additional planning applications and extensive additional work, the project was completed in February 2013, with a final account of just over €1.5m.
388:, left by her to build a number of churches in or near Dublin. To this bequest are due Zion Church Rathgar, St Barnabas's, North Lotts Dublin and St Kevin's South Circular Road. 527:
selected locations; installed a new sound system, including speakers and a main control panel; Installed security lights at each external door and emergency lights throughout.
534:
Bells: Replaced and repaired bolts, bushings, clappers and straps due to rust; applied anti-rust and intumescent paint to steel support beams; Treated end of timber supports.
145: 688: 678: 658: 39: 555:
essential areas – back and front of church, side chapel, Vestry, stairs to balcony, main corridor on balcony; laid new floor covering in toilets.
86: 58: 65: 663: 607:"1868 - St. Paul's Church of Ireland, Glenageary, Co. Dublin - Architecture of Dun Laoghaire Rathdown - Archiseek - Irish Architecture" 531:
hand basins, including new basins in the vestry and rear of church toilets; provided new ventilation to toilet at rear of church.
72: 485:
building with Safety and Building Regulations. Other works, which had been considered desirable but not essential, were omitted.
422:
In 1869, the organ was installed, located at an unorthodox location at the eastern side of the rectangular chancel under the
54: 668: 577: 363: 303: 105: 606: 419:
The consecration of the church was postponed until Sunday 8 July 1868 as the building had yet to be completed.
43: 79: 405:"The new church at St Paul’s, Glenageary, was opened for public worship for the first time yesterday morning. 563:
There has probably been a choir at St Paul's since it was consecrated in 1868. The current choir under the
573: 371: 273: 580:. There is an esteemed history of Directors of Music, with the current one being Caroline Barnes. 415:"The structure was erected by Mr. John Nolan of Dublin from the design of Mr. A Jones, Architect." 325: 32: 397: 198: 515:
repairs; treated all mould, moss and algae growth; fixed three known leaks into the church.
253: 8: 268: 191: 564: 367: 507:
provided a new hatch access to the attic and access walkway for later inspections.
547:
Vestry: Installed new shelves and cupboards and new wash hand basin and fittings.
652: 460: 359: 160: 147: 537:
Entrances: Provided two automatic universal access doors at ramp entrance.
233: 423: 203: 644: 637: 213: 540:
Balcony: Strengthened floor joists and provided safety rails at edges.
355: 181: 132: 395:, along with the spire, was completed in 1868. On 3 January 1868, the 248: 519:
areas in side chapel and re-fixed several of the memorial plaques .
21: 340: 466: 392: 385: 298: 310: 684:
Church of Ireland church buildings in the Republic of Ireland
446:
the church. A universal access ramp was constructed in 2009.
391:
Construction of the main body of the church and rectangular
568: 427: 674:
Gothic Revival church buildings in the Republic of Ireland
426:(which has since been removed after the addition of the 46:. Unsourced material may be challenged and removed. 689:19th-century churches in the Republic of Ireland 650: 467:Restoration work to church completed 2012-2013 370:. The building itself is a large one in the 679:Religious organizations established in 1821 479: 120:Church in Glenageary, Republic of Ireland 106:Learn how and when to remove this message 651: 44:adding citations to reliable sources 15: 13: 659:Churches in Dún Laoghaire–Rathdown 14: 700: 664:Diocese of Dublin and Glendalough 629: 449: 364:Diocese of Dublin and Glendalough 20: 31:needs additional citations for 611:Archiseek - Irish Architecture 599: 578:St Patrick's Cathedral, Dublin 401:issued the following account: 214:glenageary.dublin.anglican.org 55:"St Paul's Church, Glenageary" 1: 592: 523:grills and was cost neutral. 7: 574:Diocese of Derry and Raphoe 362:, is a large parish of the 10: 705: 669:Churches completed in 1868 378: 341:Organist/Director of music 576:and sing every summer in 463:on Sunday 23 April 2007. 339: 334: 324: 319: 309: 297: 292: 284: 279: 267: 259: 247: 242: 232: 224: 219: 209: 197: 187: 176: 142: 138: 130: 125: 583: 558: 480:The Restoration Project 476:Sunday, 10 March 2013. 434:that currently exists. 304:Dublin and Glendalough 161:53.28188°N 6.12587°W 40:improve this article 192:Republic of Ireland 157: /  131:St. Paul's Church, 260:Architectural type 166:53.28188; -6.12587 565:Director of Music 551:church material. 368:Church of Ireland 349: 348: 330:The Rev Gary Dowd 180:Silchester Road, 126:St. Paul's Church 116: 115: 108: 90: 696: 641: 640: 638:Official website 623: 622: 620: 618: 603: 352:St Paul's Church 172: 171: 169: 168: 167: 162: 158: 155: 154: 153: 150: 123: 122: 111: 104: 100: 97: 91: 89: 48: 24: 16: 704: 703: 699: 698: 697: 695: 694: 693: 649: 648: 636: 635: 632: 627: 626: 616: 614: 613:. 11 March 2014 605: 604: 600: 595: 586: 561: 482: 469: 452: 381: 345:Caroline Barnes 165: 163: 159: 156: 151: 148: 146: 144: 143: 121: 112: 101: 95: 92: 49: 47: 37: 25: 12: 11: 5: 702: 692: 691: 686: 681: 676: 671: 666: 661: 647: 646: 642: 631: 630:External links 628: 625: 624: 597: 596: 594: 591: 585: 582: 560: 557: 481: 478: 468: 465: 451: 450:Parochial hall 448: 417: 416: 412: 411: 407: 406: 380: 377: 372:Gothic Revival 347: 346: 343: 337: 336: 332: 331: 328: 322: 321: 317: 316: 313: 307: 306: 301: 295: 294: 293:Administration 290: 289: 286: 282: 281: 280:Specifications 277: 276: 274:Gothic Revival 271: 265: 264: 261: 257: 256: 251: 245: 244: 240: 239: 236: 230: 229: 226: 222: 221: 217: 216: 211: 207: 206: 201: 195: 194: 189: 185: 184: 178: 174: 173: 140: 139: 136: 135: 128: 127: 119: 114: 113: 28: 26: 19: 9: 6: 4: 3: 2: 701: 690: 687: 685: 682: 680: 677: 675: 672: 670: 667: 665: 662: 660: 657: 656: 654: 645: 643: 639: 634: 633: 612: 608: 602: 598: 590: 581: 579: 575: 570: 566: 556: 552: 548: 545: 541: 538: 535: 532: 528: 524: 520: 516: 512: 508: 504: 500: 497: 494: 490: 486: 477: 473: 464: 462: 461:Mary McAleese 456: 447: 443: 439: 435: 431: 429: 425: 420: 414: 413: 409: 408: 404: 403: 402: 400: 399: 398:Daily Express 394: 389: 387: 376: 373: 369: 365: 361: 360:County Dublin 357: 353: 344: 342: 338: 333: 329: 327: 323: 318: 314: 312: 308: 305: 302: 300: 296: 291: 287: 283: 278: 275: 272: 270: 266: 262: 258: 255: 252: 250: 246: 241: 237: 235: 231: 227: 223: 218: 215: 212: 208: 205: 202: 200: 196: 193: 190: 186: 183: 179: 175: 170: 141: 137: 134: 129: 124: 118: 110: 107: 99: 88: 85: 81: 78: 74: 71: 67: 64: 60: 57: –  56: 52: 51:Find sources: 45: 41: 35: 34: 29:This article 27: 23: 18: 17: 615:. Retrieved 610: 601: 587: 562: 553: 549: 546: 542: 539: 536: 533: 529: 525: 521: 517: 513: 509: 505: 501: 498: 495: 491: 487: 483: 474: 470: 457: 453: 444: 440: 436: 432: 421: 418: 396: 390: 382: 351: 350: 249:Architect(s) 243:Architecture 199:Denomination 117: 102: 93: 83: 76: 69: 62: 50: 38:Please help 33:verification 30: 455:was added. 424:rose window 238:8 July 1868 234:Consecrated 204:Anglicanism 164: / 653:Categories 593:References 356:Glenageary 182:Glenageary 149:53°16′55″N 133:Glenageary 66:newspapers 567:, are an 315:St Paul's 254:A.G Jones 152:6°07′33″W 96:June 2018 285:Capacity 177:Location 393:chancel 386:Belfast 379:History 366:of the 299:Diocese 225:Founded 220:History 210:Website 188:Country 80:scholar 326:Rector 320:Clergy 311:Parish 263:Church 82:  75:  68:  61:  53:  617:5 May 584:Organ 559:Music 335:Laity 269:Style 87:JSTOR 73:books 619:2018 569:SATB 428:apse 228:1821 59:news 430:). 354:in 288:500 42:by 655:: 609:. 358:, 621:. 109:) 103:( 98:) 94:( 84:· 77:· 70:· 63:· 36:.

Index


verification
improve this article
adding citations to reliable sources
"St Paul's Church, Glenageary"
news
newspapers
books
scholar
JSTOR
Learn how and when to remove this message
Glenageary
53°16′55″N 6°07′33″W / 53.28188°N 6.12587°W / 53.28188; -6.12587
Glenageary
Republic of Ireland
Denomination
Anglicanism
glenageary.dublin.anglican.org
Consecrated
Architect(s)
A.G Jones
Style
Gothic Revival
Diocese
Dublin and Glendalough
Parish
Rector
Organist/Director of music
Glenageary
County Dublin

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.