Knowledge

Project planning

Source 📝

82:. Project planning is inherently uncertain as it must be done before the project is actually started. Therefore, the duration of the tasks is often estimated through a weighted average of optimistic, normal, and pessimistic cases. The critical chain method adds "buffers" in the planning to anticipate potential delays in project execution. 106:
and project duration to comply with the project objectives. Once established and agreed, the project schedule becomes what is known as the baseline schedule. Progress will be measured against the baseline schedule throughout the life of the project. Analyzing progress compared to the baseline
55: 255: 118:
and the concept proposal. The outputs of the project planning phase include the project requirements, the project schedule, and the
34:
to plan and subsequently report progress within the project environment. Project planning can be done manually or by the use of
362: 310: 285: 217: 71: 99: 87: 51: 27: 326: 161: 141: 50:
is defined and the appropriate methods for completing the project are determined. Following this step, the
136: 35: 98:
for each activity can be allocated to each resource, giving the total project cost. At this stage, the
83: 47: 86:
or slack time in the schedule can be calculated using project management software. Then the necessary
75: 59: 119: 108: 206: 176: 79: 8: 151: 103: 23: 234: 367: 306: 281: 213: 62:. Project planning is often used to organize different areas of a project, including 171: 115: 208:
Project Management: A Systems Approach to Planning, Scheduling, and Controlling
201: 356: 16:
Aspect of project management which uses schedules to plan and report progress
166: 131: 63: 181: 146: 31: 67: 91: 275: 156: 58:
necessary to complete the work are listed and grouped into a
256:"Definition of project planning methodologies with examples" 102:
may be optimized to achieve the appropriate balance between
95: 347: 342: 70:
and the management of teams and individuals. The logical
114:
The inputs of the project planning phase 2 include the
280:(2nd ed.). Wiley-IEEE Computer Society Press. 205: 354: 305:(Third ed.). Project Management Institute. 200: 343:International Project Management Association 276:Richard H. Thayer, Edward Yourdon (2000). 329:, PM Hut (Last accessed 8 November 2009). 348:Association for Project Management (UK) 300: 278:Software Engineering Project Management 355: 232: 78:that enables identification of the 74:between tasks are defined using an 13: 14: 379: 336: 235:"PROJECT MANAGEMENT DEMYSTIFIED" 303:Earned Value Project Management 319: 294: 269: 248: 226: 194: 41: 26:, which relates to the use of 1: 363:Schedule (project management) 187: 162:Project Management Institute 142:Enterprise resource planning 7: 233:Heße, Robert (2023-04-08). 137:Dependency structure matrix 125: 36:project management software 10: 384: 327:Project Planning Overview 301:Fleming, Quentin (2005). 76:activity network diagram 60:work breakdown structure 212:(8th ed.). Wiley. 120:project management plan 109:earned value management 107:schedule is known as 177:Project stakeholders 152:Operations research 24:project management 325:Filicetti, John, 375: 330: 323: 317: 316: 298: 292: 291: 273: 267: 266: 264: 262: 252: 246: 245: 243: 242: 230: 224: 223: 211: 198: 172:Project slippage 100:project schedule 54:for the various 20:Project planning 383: 382: 378: 377: 376: 374: 373: 372: 353: 352: 339: 334: 333: 324: 320: 313: 299: 295: 288: 274: 270: 260: 258: 254: 253: 249: 240: 238: 231: 227: 220: 199: 195: 190: 128: 116:project charter 46:Initially, the 44: 17: 12: 11: 5: 381: 371: 370: 365: 351: 350: 345: 338: 337:External links 335: 332: 331: 318: 311: 293: 286: 268: 247: 225: 218: 202:Harold Kerzner 192: 191: 189: 186: 185: 184: 179: 174: 169: 164: 159: 154: 149: 144: 139: 134: 127: 124: 104:resource usage 43: 40: 15: 9: 6: 4: 3: 2: 380: 369: 366: 364: 361: 360: 358: 349: 346: 344: 341: 340: 328: 322: 314: 312:1-930699-89-1 308: 304: 297: 289: 287:0-8186-8000-8 283: 279: 272: 257: 251: 236: 229: 221: 219:0-471-22577-0 215: 210: 209: 203: 197: 193: 183: 180: 178: 175: 173: 170: 168: 165: 163: 160: 158: 155: 153: 150: 148: 145: 143: 140: 138: 135: 133: 130: 129: 123: 121: 117: 112: 110: 105: 101: 97: 93: 89: 85: 81: 80:critical path 77: 73: 69: 65: 64:project plans 61: 57: 53: 49: 48:project scope 39: 37: 33: 29: 25: 21: 321: 302: 296: 277: 271: 259:. Retrieved 250: 239:. Retrieved 228: 207: 196: 167:Project plan 132:Cost overrun 113: 72:dependencies 45: 32:Gantt charts 19: 18: 237:(in German) 182:Scope creep 147:Megaproject 42:Description 22:is part of 357:Categories 241:2023-06-11 188:References 92:estimated 88:resources 68:workloads 52:durations 28:schedules 368:Planning 261:24 April 204:(2003). 126:See also 30:such as 157:PRINCE2 90:can be 309:  284:  216:  96:costs 84:Float 56:tasks 307:ISBN 282:ISBN 263:2014 214:ISBN 94:and 359:: 122:. 111:. 66:, 38:. 315:. 290:. 265:. 244:. 222:.

Index

project management
schedules
Gantt charts
project management software
project scope
durations
tasks
work breakdown structure
project plans
workloads
dependencies
activity network diagram
critical path
Float
resources
estimated
costs
project schedule
resource usage
earned value management
project charter
project management plan
Cost overrun
Dependency structure matrix
Enterprise resource planning
Megaproject
Operations research
PRINCE2
Project Management Institute
Project plan

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.