Knowledge

King Street Bridge (Melbourne)

Source 📝

485:
to be the lack of, or insufficient, preheat around the weld area to limit the intensity of residual stresses in the heat affected zone. In these circumstances, brittle fracture was almost guaranteed. In fact, all the cracks occurred in the HAZ of the plate material. (On the other hand, it appears unlikely that preheating could be consistently applied, and that difficulties in application could have resulted in variations in the properties of the steel, including strength loss and stress inconsistencies over the affected or nearby areas – possibly causing similar or other types of failure, such as long-term fatigue).
33: 245: 253: 929: 264: 346:, consulting engineers for Utah Australia, on behalf of the Country Roads Board, and constructed over the next two years. The substructure of the main bridge was completed in November 1959, and the east and west lanes of the low-level bridge over the Yarra were completed except for handrailing and lighting. 524:
As each span consisted of four girders, it was decided to construct large heavily reinforced concrete blocks at the ends of each pair of girders. These were to house the anchor blocks of the post tensioning cables. These blocks were held between the girders by heavy high tensile rods passing through
502:
As J&W were responsible for all plate tests, for which they were not particularly convinced were necessary, there was a great deal of bickering between CRB inspectors and J&W shop staff. The Commissioners in their report made the statement that "We hardly know whom to blame the more, J&W
444:
The superstructure design by H&R incorporated standard design details for girders and cover plates as was common at the time for mild steel construction. CRB had allowed in the tender the use of high tensile steel to British Standard BS 968:1941. H&R chose to use this steel to reduce weight,
484:
H&R placed the transverse welded ends of cover plates of tension flanges in regions of low stress as permitted by the specifications. Had proper consideration been given during fabrication to weld preparation, the failure of the bridge may not have occurred. The greatest oversight appeared
448:
Included in the CRB tender documents were comprehensive specifications for fabrication in high tensile steel to be read in conjunction with and additional to those of BS 968 -1941. (It was suggested that the Standard may have had erroneous guidelines that were not supported by experience, and that
475:
Steel supplied by BHP was generally very close to the maximum tolerances regarding chemical composition. It was later revealed that the chemical composition of plates sometimes exceeded specification even when ladle analysis was within specification. BHP also did not appreciate the welding
224:
When it opened in 1961, the bridge had eight lanes across the Yarra River, two through lanes in each direction connecting King Street to Kings Way, in addition to two lanes on each side that connected to King Street to Yarra Bank Road. At the south end north facing on and off ramps connected to
476:
requirements for high tensile steel and even advised J&W on occasion that even when the chemical composition shown by ladle analysis exceeded specification, the steel was still weldable. Brittleness was of prime importance and under test, some samples did not even show a yield point.
532:
type with cast iron wedges fastening each cable into a mating block. Each cable was made up of a number of strands each containing seven high tensile wires. As an example, on span no. 11, 110 feet long, the total prestressing force employed amounted to about 11000 tonnes.
283:. Expectations were of world-wide tenders for the design and construction of a bridge 410 feet (120 m) long and 149 feet (45 m) wide and having a continued elevated structure 1,880 feet (570 m) long and 63 feet (19 m) wide over the 518:, chief structural engineer; Shandor Mokos and Tom Dobson, senior structural engineers; and Graham Ebbage, assistant structural engineer. All are deceased (2020) bar Ebbage who went on to design bridges in Melbourne, Brisbane and Hong Kong. 460:
J&W, when placing their order for steel from BHP, failed to require additional tests as per the CRB specifications. As a result, BHP only supplied ladle analyses. BHP even stated to J&W at some stage that
310:
Contractors from Utah Australia began their operations on the site on 25 November 1957, building a temporary bridge to give access to the eventual location of the bridge's piers over the river. The passing of the
295:, Whiteman Street, Queensbridge Street, City Road and Hanna Street, and returning to the present level of Hanna Street (later Kings Way) near Grant Street, South Melbourne. Together with the construction of the 499:
During final inspection of girders, under significant pressure of time and very unsatisfactory circumstances, it was likely that the cracks which eventually caused the bridge to fail were missed.
452:
Neither UTAH nor J&W ever really appreciated the differences that high tensile steel presented in its fabrication, particularly with regards to welding. Therein started the road to failure.
303:
3.5mil. Seven tenderers submitted a total of 14 tenders for the work when tenders closed on 29 January 1957, and after examination by the Board's officers, the government accepted the tender of
319:
on 18 December 1957, granted formal permission for the bridge to be built, gave the Country Roads Board powers to take ownership of relevant lands and not to inhibit the operations of the
521:
It had to be assumed that all girders contained cracks, whether presently detected or not. It was therefore decided to post tension all girders so as to leave no parts in tension.
1254: 536:
To protect the cables from corrosion, the cables were enclosed in fibre cement ducts and then high pressure grouted. These are what some people now see as pipes under the bridge.
236:
The south end of the bridge has been undergoing differential settlement between the approach ramps resting on fill, and the suspended section supported by bored piles.
1244: 514:
MMBW Highways Division carried out this work. The engineering staff were William (Bill) Burren, chief engineer, Highways Division; Stan Long, 2nd in charge,
356:. It is of a welded, steel girder concrete deck cantilever-suspended span construction with suspended spans up to approximately 100 feet (30 m) long. 488:
Izod tests for plate and welds were specified. Many Izod tests, particularly for welds, were repeated after an initial failure until a pass was achieved.
57: 364:
Soon after completion, on 10 July 1962, one span collapsed under the weight of a 47-ton semi-trailer, though the weight was within the bridge limits.
1259: 349:
Traffic commenced using the east and west lanes of the low-level bridge in November 1960, and on 12 April 1961, the main bridge was opened by the
970: 933: 327:
during construction, declared the road a "public highway" once completed, and apportioned the total cost of to be borne as follows: 65% by the
1249: 939: 620: 1229: 393: 491:
The Commission Report stated that "A more callous disregard of the value of acceptance tests it would be difficult to imagine."
1239: 380:
September 1956. Design and construct tenders called by the Country Roads Board of Victoria (CRB) as the Constructing Authority.
1224: 296: 511:
As authority in charge of the bridge at time of failure, MMBW was responsible for the design of the reconstruction method.
963: 1234: 564: 630: 590: 445:
so economising on the cost of the foundations. Design and construction of the foundations was undertaken by UTAH.
1112: 956: 1219: 1214: 915: 881: 1264: 979: 50: 1183: 1049: 320: 288: 1170: 683: 1132: 1064: 943: 328: 304: 279:), under instructions from the government, prepared specifications in 1956 for a bridge to cross the 145: 122: 658:"King Street Bridge – southern approach and down ramps: Report on possible rehabilitation solutions" 233:
closed Yarra Bank Road, and the bridge ramps were connected to the basement carpark of the complex.
657: 426: 343: 1079: 1029: 834: 813: 767: 733: 712: 336: 226: 1157: 1092: 316: 206: 92: 755: 32: 1152: 1069: 1014: 324: 292: 948: 814:"Country Roads Board Victoria. Forty-Seventh Annual Report: for the year ended 30 June 1960" 1019: 835:"Country Roads Board Victoria. Forty-Eighth Annual Report: for the year ended 30 June 1961" 734:"Country Roads Board Victoria. Forty-Fourth Annual Report: for the year ended 30 June 1957" 544: 515: 768:"Country Roads Board Victoria. Forty-Fifth Annual Report: for the year ended 30 June 1958" 713:"Country Roads Board Victoria. Forty-Third Annual Report: for the year ended 30 June 1956" 8: 1107: 1039: 1034: 350: 272: 1162: 1137: 1054: 895: 857: 540: 419: 861:. Vol. 35, no. 9, 878. Australian Capital Territory. 5 April 1961. p. 2 853:"In Victoria This Week: That King Street Bridge will be opened officially on April 12" 225:
Whiteman Street, and the running lanes from the viaduct descend to ground level, with
740:. Melbourne: Victorian Government Library Service. 21 November 1957. pp. 21, 48. 626: 332: 1193: 1188: 1175: 1147: 1142: 1059: 1009: 429:, consulting engineers, subcontractor to Utah for detailed design of superstructure 300: 1074: 1024: 472:
Not all tensile and Izod tests for different plate thicknesses were carried out.
402:
September 1962 to August 1963. Royal Commission into the Failure of Kings Bridge.
257: 230: 218: 38: 820:. Melbourne: Victorian Government Library Service. 21 November 1960. p. 45. 774:. Melbourne: Victorian Government Library Service. 19 November 1958. p. 27. 719:. Melbourne: Victorian Government Library Service. 23 November 1956. p. 22. 1127: 1117: 1004: 841:. Melbourne: Victorian Government Library Service. 1 December 1961. p. 42. 244: 852: 785: 422:– Subcontractor to Utah for fabrication, erection and painting of girders 229:
emerging from City Road to the median strip. In the 1990s, the development of
1208: 1122: 1087: 1044: 911: 72: 59: 42: 1097: 994: 568: 412:
CRB (Country Roads Board) – Constructing authority and contract principal
353: 284: 280: 217:, Australia. The bridge continues south as an elevated viaduct, with the 210: 102: 999: 529: 983: 616: 466: 462: 214: 794:. No. 31, 070. Victoria, Australia. 1 December 1954. p. 8 276: 112: 790: 786:"Traffic Relief Project: £870,000 Bridge for King Street Favored" 252: 525:
each block from girder to girder, averaging about 19 rods each.
928: 978: 912:"Report of Royal Commission into the Failure of Kings Bridge" 371:" section, is taken from the report of the Royal Commission. 615: 267:
Looking south to the end of the elevated section of Kingsway
287:
at King Street, together with a viaduct crossing above the
263: 503:
for its cavalier attitude or CRB for putting up with it."
432: 165: 1255:
Buildings and structures in the City of Melbourne (LGA)
655: 622:
Fluid City: Transforming Melbourne's Urban Waterfront
256:Elevated section of Kingsway headed north through 1206: 406: 342:The King Street Bridge was designed in 1959 by 940:Transporting of girder through South Melbourne 435:Broken Hill Propriety Ltd. for supply of steel 964: 1245:Bridge disasters caused by engineering error 469:as per the CRB specifications were useless. 684:"Melbourne city's Kings Bridge cracking up" 479: 971: 957: 869:– via National Library of Australia. 829: 827: 802:– via National Library of Australia. 656:Kellog Brown and Root (13 November 2006). 299:, the whole project was estimated to cost 728: 726: 707: 705: 547:was MMBW site engineer for the contract. 494: 394:Melbourne and Metropolitan Board of Works 1260:Transport in the City of Melbourne (LGA) 751: 749: 747: 681: 262: 251: 243: 824: 806: 1207: 760: 723: 702: 567:. custommaps.net. 1966. Archived from 539:The reconstruction was carried out by 952: 744: 651: 649: 672:(accessed via FoI by Channel 7 news) 597:. archmedia.com.au. July–August 1997 415:UTAH Aust Ltd – Principal contractor 392:October 1961. Bridge handed over to 879:Transport Benefits from New Bridge 449:were relied upon for this design). 368: 13: 1250:Victoria (state) royal commissions 905: 646: 455: 14: 1276: 921: 682:Gardiner, Ashley (17 June 2008). 506: 396:(MMBW) as a metropolitan highway. 1230:1961 establishments in Australia 1070:Gardiners Creek Trail Footbridge 927: 374: 221:built around it in later years. 31: 888: 873: 845: 839:Country Roads Board of Victoria 818:Country Roads Board of Victoria 778: 772:Country Roads Board of Victoria 738:Country Roads Board of Victoria 717:Country Roads Board of Victoria 367:The following, except for the " 1167:Swan Street/Wallen Road Bridge 1138:Ruffey Trail Suspension Bridge 1040:Diamond Creek Trail Footbridge 1035:Darebin Creek Trail Footbridge 882:Truck & Bus Transportation 675: 609: 583: 557: 1: 1240:Bridge disasters in Australia 934:King Street Bridge, Melbourne 916:National Library of Australia 550: 407:Participants for construction 386:September 1957. Work started. 1225:Bridges over the Yarra River 980:Crossings of the Yarra River 619:, Leonie Sandercock (2004). 399:July 1962. Bridge collapsed. 389:April 1961. Open to traffic. 7: 1194:Westerfolds Park Footbridge 756:King-street Bridge Act 1957 359: 313:King-street Bridge Act 1957 10: 1281: 541:John Holland Constructions 383:May 1957. Tenders awarded. 239: 1235:Bridges completed in 1961 990: 944:State Library of Victoria 439: 427:Hardcastle & Richards 344:Hardcastle & Richards 191: 186: 171: 161: 157:Utah Construction Company 151: 146:Utah Construction Company 141: 136: 128: 118: 108: 98: 88: 49: 30: 23: 1176:Walmer Street Footbridge 1010:Chandler Highway Bridges 480:Cover plates and welding 297:Flinders Street overpass 73:37.822083°S 144.958056°E 1080:Hawthorn Railway Bridge 1050:Eastern Freeway Bridges 1030:Cremorne Railway Bridge 528:The cables were of the 337:City of South Melbourne 175:12 April 1961 132:Clarendon Street Bridge 37:King Street Bridge and 1158:Spotswood sewer tunnel 1113:Manningham Road Bridge 1093:Johnston Street Bridge 1065:Fitzsimons Lane Bridge 595:Architecture Australia 495:Fabrication inspection 325:St Kilda railway lines 317:Parliament of Victoria 293:St Kilda railway lines 268: 260: 249: 78:-37.822083; 144.958056 1153:Spencer Street Bridge 1084:Heyington Rail Bridge 1060:Fairfield Pipe Bridge 1015:Charles Grimes Bridge 894:Verbal briefing from 266: 255: 247: 1220:Plate girder bridges 1215:Bridges in Melbourne 1020:Church Street Bridge 936:at Wikimedia Commons 329:Victorian government 248:Viewed from the west 1265:Southbank, Victoria 1108:MacRobertson Bridge 896:Johns & Waygood 571:on 5 September 2007 420:Johns & Waygood 351:Premier of Victoria 273:Country Roads Board 199:King Street Bridge, 69: /  1163:Swan Street Bridge 1103:King Street Bridge 1055:Evan Walker Bridge 858:The Canberra Times 591:"Melbourne Casino" 565:"Melway Edition 1" 269: 261: 250: 25:King Street Bridge 1202: 1201: 1180:Warrandyte Bridge 1000:Burke Road Bridge 932:Media related to 885:May 1961 page 103 333:City of Melbourne 195: 194: 1272: 1189:West Gate Bridge 1148:Seafarers Bridge 1143:Sandridge Bridge 973: 966: 959: 950: 949: 931: 899: 892: 886: 877: 871: 870: 868: 866: 849: 843: 842: 831: 822: 821: 810: 804: 803: 801: 799: 782: 776: 775: 764: 758: 753: 742: 741: 730: 721: 720: 709: 700: 699: 697: 695: 679: 673: 671: 669: 667: 662: 653: 644: 643: 641: 639: 613: 607: 606: 604: 602: 587: 581: 580: 578: 576: 561: 335:, and 5% by the 182: 180: 154: 84: 83: 81: 80: 79: 74: 70: 67: 66: 65: 62: 35: 21: 20: 1280: 1279: 1275: 1274: 1273: 1271: 1270: 1269: 1205: 1204: 1203: 1198: 1171:Victoria Bridge 1075:Hawthorn Bridge 986: 977: 924: 908: 906:Further reading 903: 902: 893: 889: 878: 874: 864: 862: 851: 850: 846: 833: 832: 825: 812: 811: 807: 797: 795: 784: 783: 779: 766: 765: 761: 754: 745: 732: 731: 724: 711: 710: 703: 693: 691: 680: 676: 665: 663: 660: 654: 647: 637: 635: 633: 614: 610: 600: 598: 589: 588: 584: 574: 572: 563: 562: 558: 553: 509: 497: 482: 458: 456:Material supply 442: 409: 377: 362: 242: 178: 176: 152: 77: 75: 71: 68: 63: 60: 58: 56: 55: 45: 26: 19: 12: 11: 5: 1278: 1268: 1267: 1262: 1257: 1252: 1247: 1242: 1237: 1232: 1227: 1222: 1217: 1200: 1199: 1197: 1196: 1191: 1186: 1181: 1178: 1173: 1168: 1165: 1160: 1155: 1150: 1145: 1140: 1135: 1130: 1128:Princes Bridge 1125: 1120: 1118:Monash Freeway 1115: 1110: 1105: 1100: 1095: 1090: 1085: 1082: 1077: 1072: 1067: 1062: 1057: 1052: 1047: 1042: 1037: 1032: 1027: 1025:Collins Bridge 1022: 1017: 1012: 1007: 1005:Burnley Tunnel 1002: 997: 991: 988: 987: 976: 975: 968: 961: 953: 947: 946: 937: 923: 922:External links 920: 919: 918: 907: 904: 901: 900: 887: 872: 844: 823: 805: 777: 759: 743: 722: 701: 674: 645: 631: 625:. UNSW Press. 608: 582: 555: 554: 552: 549: 508: 507:Reconstruction 505: 496: 493: 481: 478: 457: 454: 441: 438: 437: 436: 430: 423: 416: 413: 408: 405: 404: 403: 400: 397: 390: 387: 384: 381: 376: 373: 369:Reconstruction 361: 358: 321:Port Melbourne 305:Utah Australia 289:Port Melbourne 241: 238: 201:also known as 193: 192: 189: 188: 184: 183: 173: 169: 168: 163: 162:Fabrication by 159: 158: 155: 153:Constructed by 149: 148: 143: 139: 138: 134: 133: 130: 126: 125: 120: 116: 115: 110: 106: 105: 100: 96: 95: 90: 86: 85: 53: 47: 46: 36: 28: 27: 24: 17: 9: 6: 4: 3: 2: 1277: 1266: 1263: 1261: 1258: 1256: 1253: 1251: 1248: 1246: 1243: 1241: 1238: 1236: 1233: 1231: 1228: 1226: 1223: 1221: 1218: 1216: 1213: 1212: 1210: 1195: 1192: 1190: 1187: 1185: 1182: 1179: 1177: 1174: 1172: 1169: 1166: 1164: 1161: 1159: 1156: 1154: 1151: 1149: 1146: 1144: 1141: 1139: 1136: 1134: 1133:Queens Bridge 1131: 1129: 1126: 1124: 1123:Morell Bridge 1121: 1119: 1116: 1114: 1111: 1109: 1106: 1104: 1101: 1099: 1096: 1094: 1091: 1089: 1088:Hoddle Bridge 1086: 1083: 1081: 1078: 1076: 1073: 1071: 1068: 1066: 1063: 1061: 1058: 1056: 1053: 1051: 1048: 1046: 1045:Domain Tunnel 1043: 1041: 1038: 1036: 1033: 1031: 1028: 1026: 1023: 1021: 1018: 1016: 1013: 1011: 1008: 1006: 1003: 1001: 998: 996: 993: 992: 989: 985: 981: 974: 969: 967: 962: 960: 955: 954: 951: 945: 941: 938: 935: 930: 926: 925: 917: 913: 910: 909: 897: 891: 884: 883: 876: 860: 859: 854: 848: 840: 836: 830: 828: 819: 815: 809: 793: 792: 787: 781: 773: 769: 763: 757: 752: 750: 748: 739: 735: 729: 727: 718: 714: 708: 706: 690:. news.com.au 689: 685: 678: 659: 652: 650: 634: 632:9780868406695 628: 624: 623: 618: 612: 596: 592: 586: 570: 566: 560: 556: 548: 546: 542: 537: 534: 531: 526: 522: 519: 517: 512: 504: 500: 492: 489: 486: 477: 473: 470: 468: 464: 453: 450: 446: 434: 431: 428: 424: 421: 417: 414: 411: 410: 401: 398: 395: 391: 388: 385: 382: 379: 378: 375:Short history 372: 370: 365: 357: 355: 352: 347: 345: 340: 338: 334: 331:, 30% by the 330: 326: 322: 318: 314: 308: 306: 302: 298: 294: 290: 286: 282: 278: 274: 265: 259: 254: 246: 237: 234: 232: 228: 227:tram route 58 222: 220: 216: 212: 208: 204: 200: 190: 185: 174: 170: 167: 164: 160: 156: 150: 147: 144: 140: 135: 131: 127: 124: 123:Queens Bridge 121: 117: 114: 111: 109:Maintained by 107: 104: 101: 97: 94: 91: 87: 82: 64:144°57′29.0″E 54: 52: 48: 44: 43:Rialto Towers 40: 34: 29: 22: 16: 1102: 1098:Kanes Bridge 995:Bolte Bridge 890: 880: 875: 863:. Retrieved 856: 847: 838: 817: 808: 796:. Retrieved 789: 780: 771: 762: 737: 716: 692:. Retrieved 687: 677: 664:. Retrieved 636:. Retrieved 621: 611: 599:. Retrieved 594: 585: 573:. Retrieved 569:the original 559: 538: 535: 527: 523: 520: 513: 510: 501: 498: 490: 487: 483: 474: 471: 459: 451: 447: 443: 366: 363: 348: 341: 315:through the 312: 309: 270: 258:Crown Casino 235: 231:Crown Casino 223: 219:Crown Casino 203:Kings Bridge 202: 198: 196: 61:37°49′19.5″S 39:Crown Casino 15: 1184:Webb Bridge 354:Henry Bolte 285:Yarra River 281:Yarra River 211:Yarra River 207:King Street 129:Followed by 119:Preceded by 103:Yarra River 93:King Street 76: / 51:Coordinates 1209:Categories 898:circa 1967 688:Herald Sun 551:References 530:Freyssinet 463:Izod tests 179:1961-04-12 984:Melbourne 617:Kim Dovey 545:Bruce Day 516:Bruce Day 467:ductility 215:Melbourne 209:over the 41:from the 865:23 April 798:23 April 425:H&R 418:J&W 360:Collapse 277:VicRoads 205:carries 187:Location 142:Designer 113:VicRoads 791:The Age 694:17 June 666:17 June 638:17 June 601:17 June 575:17 June 275:(later 240:History 177: ( 137:History 99:Crosses 89:Carries 629:  440:Design 172:Opened 18:Bridge 661:(PDF) 867:2017 800:2017 696:2008 668:2008 640:2008 627:ISBN 603:2008 577:2008 465:for 323:and 291:and 271:The 197:The 982:in 433:BHP 213:in 166:BHP 1211:: 942:, 914:, 855:. 837:. 826:^ 816:. 788:. 770:. 746:^ 736:. 725:^ 715:. 704:^ 686:. 648:^ 593:. 543:. 339:. 307:. 301:A£ 972:e 965:t 958:v 698:. 670:. 642:. 605:. 579:. 181:)

Index


Crown Casino
Rialto Towers
Coordinates
37°49′19.5″S 144°57′29.0″E / 37.822083°S 144.958056°E / -37.822083; 144.958056
King Street
Yarra River
VicRoads
Queens Bridge
Utah Construction Company
BHP
King Street
Yarra River
Melbourne
Crown Casino
tram route 58
Crown Casino


Crown Casino

Country Roads Board
VicRoads
Yarra River
Yarra River
Port Melbourne
St Kilda railway lines
Flinders Street overpass

Utah Australia

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.