Knowledge

Dunlin oilfield

Source 📝

30: 563:. The decommissioning process, which requires regulatory approvals, is expected to cost about £400 million. Dunlin has been cited as an example of the impact a decommissioning decision has impacting surrounding infrastructure as per the 2014 Wood MER (Maximising Economic Recovery) Report - the "Domino Effect". Enquest will have to provide a pipeline "bypass" to allow continued export from the Thistle complex of fields to be exported via the 16" export line into the 24" line that runs from Dunlin to Cormorant Alpha. 503: 37: 535:
flowlines from Merlin comprise 8" water injection and production lines. These tie into the Osprey riser system at Dunlin. Merlin subsea controls tie in via a crossover manifold adjacent to Dunlin into the Osprey umbilical system. Flexible flowlines were installed for water injection service on Merlin and Osprey in 2002.
534:
The Merlin field was discovered in 1998 and was initially developed as a low cost CRINE field (Cost Reduction In the New Era) utilising the discovery well recompleted as a subsea producer. The Merlin drill centre was progressively expanded to 3 subsea production wells and a single water injector. The
466:
The topsides facilities included capability to drill, produce, meter and export oil. It also has capability to re-inject water to maintain reservoir pressure, (111,250 bls/day) predicted. Peak production was 115,000 barrels per day in 1979; and it was approximately in the region of 3500 - 4000 bpd in
546:
Fairfield installed a 4" fuel gas import line from the Thistle platform in 2012 to provide fuel for the platform power generation plant. The field had become gas deficient (insufficient associated gas being produced as a by product of oil production) under Shell. In an attempt to mitigate this Shell
530:
Osprey was developed by Shell in 1989/90 and employs two drill centres, one for production (with 8 subsea trees) and one for water injection (with 4 subsea trees). The drill centres are connected to the platform via two back to back flowline bundles containing 2 off 8" production flowlines and a 10"
550:
Dunlin acts as a pipeline node on the Brent system and provides connection point for the 16" export line from the Enquest operated Thistle and Don Fields and the 16" line from the Murchison field (the latter in the process of being decommissioned by Canadian Natural Resources International - CNRI -
547:
had installed a 33KVa power import cable between Dunlin and Brent C in 2002. The Brent sequence fields rely on water injection to maintain production and Dunlin had an installed water injection plant capable of delivering 250,000 bwpd supplied by 5 electrically powered water injection pumps.
203:
The Field was originally discovered in July 1973 in a water depth of 151 metres (495 ft) approximately 12 km from the UK-Norway median line. Estimated recovery is 363 million barrels of oil. The oil reservoir is located at a depth of 9,000 feet (2,740 metres).
463:(229,000 tonnes) and it is designed to carry a topsides weight of 15,635 long tons (15,886 tonnes). The storage system was decommissioned by Shell from 2005 to 2007 prior to the sale to Fairfield Energy. 566:
The decommissioning of the Murchison field and the Dunlin complex removes two "shippers" from the Brent system resulting in increase pipeline operating costs for the remaining users.
531:
water injection line. Subsea trees and the manifolds were supplied by Cameron Oil Tools (now OneSubsea). Subsea control system was supplied by Kvaerner FSSL (now Aker solutions).
459:
type (Anglo Dutch Offshore Concrete) and was installed in June 1977. It has four legs and storage capacity for 838,200 barrels of oil. The total sub-structure weight is 225,000
605: 293:
The field was developed by a single integrated drilling, production, storage and accommodation platform. The principal design data of the Dunlin platform was as follows:
644: 196:
Under Fairfield initially the platform was operated using the duty holder model. Amec (now Worley) were the duty holder contractor and
674: 609: 90: 455:
Production started in August 1978 from the Dunlin Alpha platform. This platform is a concrete gravity base (GBS) structure of the
29: 494:
The oil production profile for Dunlin (in 1000s barrels per year) in the early operating period is shown in the graph:
222:
at a depth of 8,700 to 9,700 feet (2,652 to 2,957 m). The reservoir and its fluids had the following characteristics:
456: 669: 664: 467:
2015 prior to the shut in announcement (Production ceased on 15 June 2015) Oil production is by pipeline to
630: 515: 559:
In May 2015, Fairfield Energy has announced plans to decommission its Dunlin Alpha platform in the
200:
was the engineering and upgrade project contract. Fairfield became the duty holder in April 2014.
484: 207:
Dunlin acts as the host platform for production from the Osprey and Merlin subsea fields.
8: 538:
Osprey and Merlin produce from the same Brent sequence geology as the main Dunlin Field.
468: 190: 511: 606:"Access to Fairfield Energy's Oil and Gas Infrastructure | Fairfield Energy" 197: 193:
but was sold in 2008 and is now operated by Fairfield Energy and partners MCX.
658: 105: 92: 472: 476: 510:
Graphs are unavailable due to technical issues. There is more info on
560: 488: 219: 189:, in block number 211/23a and 211/24a. It was originally operated by 480: 460: 216: 186: 182: 645:"Low Oil Price Domino Effect to Shut More North Sea Fields Early" 178: 589: 594:. Ledbury: Oilfield Publications Limited. pp. 158–62. 631:"Fairfield Energy in move to decommission oil platform" 656: 345:Drilling, production, storage, accommodation 541: 525: 329:Ewbank & Partners / Halcrow Offshore 282:310 million barrels, 52.2 million tonnes 441:Cormorant A 35 km 24-inch pipeline 36: 657: 590:Oilfield Publications Limited (1985). 398:Throughput oil, barrels per day (bpd) 177:is situated 195 km northeast of 585: 583: 581: 579: 496: 13: 554: 14: 686: 576: 215:The reservoir comprises a middle 675:Oil and gas industry in Shetland 501: 35: 28: 266:250 standard cubic feet/barrel 637: 623: 598: 1: 569: 288: 592:The North Sea Platform Guide 297:Dunlin platform design data 210: 44:Location of Dunlin oil field 7: 10: 691: 449:Used on board as fuel gas 382:Storage capacity, barrels 318:Fabrication substructure 163: 158: 150: 142: 137: 129: 121: 84: 76: 68: 60: 52: 23: 18: 633:. BBC News. 11 May 2015. 483:. Associated gas powers 226:Dunlin reservoir fluids 542:Pipeline Infrastructure 526:Subsea Satellite Fields 334:Topside weight, tonnes 321:Maasvlakte Netherlands 670:Oil fields of Scotland 430:Water injection start 305:61°16’30”N 01°35’51”E 485:electrical generation 406:Water injection, bpd 350:Accommodation (crew) 279:Recoverable reserves 665:North Sea oil fields 310:Water depth, metres 164:Producing formations 106:61.27500°N 1.59750°E 414:Platform installed 298: 227: 151:Start of production 102: /  446:Gas production to 438:Oil production to 296: 225: 64:northern North Sea 523: 522: 453: 452: 422:Production start 361:Concrete gravity 286: 285: 171: 170: 111:61.27500; 1.59750 682: 649: 648: 641: 635: 634: 627: 621: 620: 618: 617: 608:. Archived from 602: 596: 595: 587: 505: 504: 497: 326:Topsides design 299: 295: 228: 224: 117: 116: 114: 113: 112: 107: 103: 100: 99: 98: 95: 77:Offshore/onshore 39: 38: 32: 19:Dunlin oil field 16: 15: 690: 689: 685: 684: 683: 681: 680: 679: 655: 654: 653: 652: 643: 642: 638: 629: 628: 624: 615: 613: 604: 603: 599: 588: 577: 572: 557: 555:Decommissioning 544: 528: 519: 506: 502: 487:. Some gas was 469:Cormorant Alpha 291: 271:Sulfur content 213: 175:Dunlin oilfield 167:Middle Jurassic 110: 108: 104: 101: 96: 93: 91: 89: 88: 72:211/23a 211/24a 69:Location/blocks 48: 47: 46: 45: 42: 41: 40: 12: 11: 5: 688: 678: 677: 672: 667: 651: 650: 636: 622: 597: 574: 573: 571: 568: 556: 553: 543: 540: 527: 524: 521: 520: 509: 507: 500: 451: 450: 447: 443: 442: 439: 435: 434: 431: 427: 426: 423: 419: 418: 415: 411: 410: 407: 403: 402: 399: 395: 394: 391: 387: 386: 383: 379: 378: 375: 371: 370: 367: 363: 362: 359: 355: 354: 351: 347: 346: 343: 339: 338: 335: 331: 330: 327: 323: 322: 319: 315: 314: 311: 307: 306: 303: 290: 287: 284: 283: 280: 276: 275: 272: 268: 267: 264: 263:Gas Oil Ratio 260: 259: 256: 252: 251: 248: 244: 243: 240: 236: 235: 232: 212: 209: 198:Aker Solutions 169: 168: 165: 161: 160: 156: 155: 152: 148: 147: 144: 140: 139: 135: 134: 131: 127: 126: 123: 119: 118: 86: 82: 81: 78: 74: 73: 70: 66: 65: 62: 58: 57: 56:United Kingdom 54: 50: 49: 43: 34: 33: 27: 26: 25: 24: 21: 20: 9: 6: 4: 3: 2: 687: 676: 673: 671: 668: 666: 663: 662: 660: 646: 640: 632: 626: 612:on 2015-07-17 611: 607: 601: 593: 586: 584: 582: 580: 575: 567: 564: 562: 552: 548: 539: 536: 532: 517: 516:MediaWiki.org 513: 508: 499: 498: 495: 492: 490: 486: 482: 478: 474: 470: 464: 462: 458: 448: 445: 444: 440: 437: 436: 432: 429: 428: 424: 421: 420: 416: 413: 412: 408: 405: 404: 400: 397: 396: 392: 389: 388: 384: 381: 380: 376: 373: 372: 368: 365: 364: 360: 357: 356: 352: 349: 348: 344: 341: 340: 336: 333: 332: 328: 325: 324: 320: 317: 316: 312: 309: 308: 304: 301: 300: 294: 281: 278: 277: 273: 270: 269: 265: 262: 261: 257: 254: 253: 250:100-1,500 md 249: 247:Permeability 246: 245: 241: 238: 237: 233: 230: 229: 223: 221: 218: 208: 205: 201: 199: 194: 192: 188: 184: 180: 176: 166: 162: 157: 153: 149: 145: 141: 138:Field history 136: 132: 128: 124: 120: 115: 87: 83: 79: 75: 71: 67: 63: 59: 55: 51: 31: 22: 17: 639: 625: 614:. Retrieved 610:the original 600: 591: 565: 558: 549: 545: 537: 533: 529: 493: 475:pipeline to 473:Brent System 471:and then by 465: 454: 425:August 1978 302:Coordinates 292: 255:API gravity 214: 206: 202: 195: 174: 172: 551:June 2015) 512:Phabricator 390:Well slots 274:0.4 % 109: / 85:Coordinates 659:Categories 616:2015-07-16 570:References 477:Sullom Voe 417:June 1977 289:Production 242:24 % 231:Parameter 159:Production 94:61°16′30″N 561:North Sea 461:long tons 433:May 1979 342:Function 239:Porosity 220:sandstone 211:The field 143:Discovery 122:Operators 97:1°35′51″E 481:Shetland 409:111,250 401:150,000 385:800,000 217:Jurassic 187:Scotland 183:Shetland 133:see text 125:see text 80:Offshore 514:and on 337:17,450 258:36°API 179:Lerwick 53:Country 489:flared 374:Cells 234:Value 61:Region 457:ANDOC 366:Legs 358:Type 191:Shell 130:Owner 353:183 313:151 173:The 154:1978 146:1973 393:48 377:81 661:: 578:^ 491:. 479:, 369:4 185:, 181:, 647:. 619:. 518:.

Index

Dunlin oilfield is located in North Sea
61°16′30″N 1°35′51″E / 61.27500°N 1.59750°E / 61.27500; 1.59750
Lerwick
Shetland
Scotland
Shell
Aker Solutions
Jurassic
sandstone
ANDOC
long tons
Cormorant Alpha
Brent System
Sullom Voe
Shetland
electrical generation
flared
Phabricator
MediaWiki.org
North Sea




"Access to Fairfield Energy's Oil and Gas Infrastructure | Fairfield Energy"
the original
"Fairfield Energy in move to decommission oil platform"
"Low Oil Price Domino Effect to Shut More North Sea Fields Early"
Categories
North Sea oil fields

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.