Knowledge

Tieback (geotechnical)

Source 📝

24: 104:
load-elongation curve according to gauge readings. This simple procedure is used to test each tieback for which a performance test is not conducted. Performance testing is a more reliable method of predicting the load-elongation behavior, and is conducted on a selected number of tiebacks in a project. For performance testing, a particular sequence of increasing and decreasing loads are applied, using equipment similar to those used in the proof test. Typically, the maximum load applied during the test will exceed the design load of the tieback system by approximately 20 to 30%. The creep behavior of the tieback system can also be studied according to the aforementioned procedure.
495: 348: 394: 307: 295: 406: 457: 382: 283: 430: 483: 471: 507: 418: 531: 447: 370: 271: 519: 319: 90:
The main purpose of an anchored wall system is to construct an internally stable mass of soil to resist external failure modes, while maintaining an acceptable level of serviceability. The constructed system should limit movement of the soil and the wall. The magnitude of total anchor force required
43:
is a structural element installed in soil or rock to transfer applied tensile load into the ground. Typically in the form of a horizontal wire or rod, or a helical anchor, a tieback is commonly used along with other retaining systems (e.g. soldier piles, sheet piles, secant and tangent walls) to
63:
Tiebacks are drilled into soil using a small diameter shaft, and usually installed at an angle of 15 to 45 degrees. They can be either drilled directly into a soldier pile, or through a wale installed between consecutive piles. Grouted tiebacks can be constructed as steel rods drilled through a
103:
Upon installation, tiebacks are tested and usually pre-loaded. In specific, a combination of proof tests and performance tests are performed on every job. Proof testing involves the application of successively larger loads on the tieback with a loading jack, allowing for the recording of a
94:
The bond length of the tieback must extend beyond the potential critical failure surface of the soil. Otherwise the tieback cannot provide resistance to the collapse of the ground mass enclosed within the failure surface.
82:
resistance, k is an empirical constant and T is the installation torque. These anchors are installed either for small loads in short sections or for larger loads and in long continuous lengths.
68:
is then pumped under pressure into the tieback anchor holes to increase soil resistance and thereby prevent tiebacks from pulling out, reducing the risk for wall destabilization.
298: 409: 385: 433: 219: 486: 71: 373: 91:
in the tieback can be determined by analyzing the soil and groundwater properties as well as sources of external loads applied to the system.
56:
with sufficient resistance. The tieback-deadman structure resists forces that would otherwise cause the wall to lean, as for example, when a
1184: 1350: 1229: 212: 23: 192: 639: 237: 205: 173: 78:
required during installation. This relationship is in accordance with the equation Qt = kT where Qt is the total
887: 768: 310: 1200: 800: 245: 1103: 498: 1179: 1169: 1041: 1031: 861: 599: 397: 228: 124: 17: 1019: 994: 934: 614: 555: 32: 141: 1282: 1093: 743: 718: 569: 548: 440: 969: 778: 286: 1322: 1174: 1131: 1024: 949: 332: 8: 1098: 1088: 644: 629: 589: 562: 337: 327: 48:. With one end of the tieback secured to the wall, the other end is anchored to a stable 1049: 758: 541: 460: 1146: 892: 783: 753: 604: 169: 1196: 1083: 974: 939: 914: 773: 594: 421: 1312: 1136: 1054: 989: 984: 882: 748: 619: 474: 163: 1259: 1151: 1068: 872: 634: 624: 510: 45: 1189: 1344: 1287: 1126: 1004: 999: 954: 723: 494: 347: 60:
is pushed seaward by water trapped on the landward side after a heavy rain.
1307: 1302: 1292: 1272: 959: 902: 733: 450: 393: 306: 197: 53: 359: 294: 1317: 1014: 897: 836: 405: 28: 456: 381: 282: 1141: 1121: 1009: 821: 816: 738: 728: 609: 354: 274: 52:, such as a concrete deadman which has been driven into the ground or 1297: 1277: 1163: 979: 964: 580: 522: 322: 49: 1327: 1214: 944: 919: 846: 763: 429: 482: 470: 1267: 1239: 924: 851: 841: 831: 826: 534: 506: 79: 57: 417: 1249: 1244: 1234: 1224: 1156: 929: 877: 687: 530: 446: 369: 75: 74:
are screwed into place. Their capacity is proportional to the
270: 64:
concrete wall out into the soil or bedrock on the other side.
702: 65: 518: 318: 697: 692: 682: 677: 672: 657: 193:
California Department of Transportation tieback document
165:
Tiebacks in foundation engineering and construction
1342: 213: 44:provide additional stability to cantilevered 227: 220: 206: 161: 85: 22: 119: 117: 1343: 136: 134: 201: 142:"Ground Anchors and Anchored Systems" 114: 131: 13: 14: 1362: 238:Offshore geotechnical engineering 186: 529: 517: 505: 493: 481: 469: 455: 445: 428: 416: 404: 392: 380: 368: 346: 317: 305: 293: 281: 269: 1351:Geotechnical shoring structures 155: 1: 888:Mechanically stabilized earth 107: 640:Hydraulic conductivity tests 7: 1201:Stress distribution in soil 10: 1367: 351:Pore pressure measurement 98: 15: 1258: 1213: 1112: 1104:Preconsolidation pressure 1076: 1067: 1040: 860: 809: 796: 711: 665: 656: 579: 499:Standard penetration test 257: 244: 235: 600:California bearing ratio 398:Rotary-pressure sounding 229:Geotechnical engineering 162:Schnabel, Harry (1982). 27:Tiebacks to reinforce a 18:Tieback (disambiguation) 1020:Geosynthetic clay liner 995:Expanded clay aggregate 615:Proctor compaction test 556:Crosshole sonic logging 542:Nuclear densometer test 299:Geo-electrical sounding 1283:Earthquake engineering 1094:Lateral earth pressure 719:Hydraulic conductivity 570:Wave equation analysis 549:Exploration geophysics 441:Deformation monitoring 410:Rotary weight sounding 36: 461:Settlement recordings 386:Rock control drilling 287:Cone penetration test 86:Design considerations 26: 1323:Agricultural science 1025:Cellular confinement 16:For other uses, see 1215:Numerical analysis 1099:Overburden pressure 1089:Pore water pressure 869:Shoring structures 744:Reynolds' dilatancy 645:Water content tests 630:Triaxial shear test 590:Soil classification 563:Pile integrity test 54:anchored into earth 1190:Slab stabilisation 1170:Stability analysis 37: 1338: 1337: 1209: 1208: 1185:Sliding criterion 1147:Response spectrum 1063: 1062: 893:Pressure grouting 792: 791: 652: 651: 605:Direct shear test 311:Permeability test 1358: 1197:Bearing capacity 1084:Effective stress 1074: 1073: 975:Land reclamation 915:Land development 810:Natural features 807: 806: 774:Specific storage 663: 662: 595:Atterberg limits 533: 521: 509: 497: 485: 473: 459: 449: 434:Screw plate test 432: 420: 408: 396: 384: 372: 350: 321: 309: 297: 285: 273: 255: 254: 222: 215: 208: 199: 198: 180: 179: 159: 153: 152: 149:www.fhwa.dot.gov 146: 138: 129: 128: 121: 1366: 1365: 1361: 1360: 1359: 1357: 1356: 1355: 1341: 1340: 1339: 1334: 1313:Earth materials 1254: 1216: 1205: 1114: 1108: 1059: 1036: 990:Earth structure 985:Erosion control 883:Ground freezing 873:Retaining walls 856: 798: 788: 749:Angle of repose 707: 648: 582: 575: 574: 535:Visible bedrock 487:Simple sounding 475:Shear vane test 251:instrumentation 250: 248: 240: 231: 226: 189: 184: 183: 176: 160: 156: 144: 140: 139: 132: 123: 122: 115: 110: 101: 88: 72:Helical anchors 46:retaining walls 21: 12: 11: 5: 1364: 1354: 1353: 1336: 1335: 1333: 1332: 1331: 1330: 1320: 1315: 1310: 1305: 1300: 1295: 1290: 1285: 1280: 1275: 1270: 1264: 1262: 1260:Related fields 1256: 1255: 1253: 1252: 1247: 1242: 1237: 1232: 1227: 1221: 1219: 1211: 1210: 1207: 1206: 1204: 1203: 1194: 1193: 1192: 1187: 1182: 1180:Classification 1177: 1172: 1161: 1160: 1159: 1154: 1152:Seismic hazard 1149: 1139: 1134: 1129: 1124: 1118: 1116: 1110: 1109: 1107: 1106: 1101: 1096: 1091: 1086: 1080: 1078: 1071: 1065: 1064: 1061: 1060: 1058: 1057: 1052: 1046: 1044: 1038: 1037: 1035: 1034: 1029: 1028: 1027: 1022: 1017: 1012: 1002: 997: 992: 987: 982: 977: 972: 967: 962: 957: 952: 947: 942: 937: 932: 927: 922: 917: 912: 911: 910: 905: 900: 895: 890: 885: 880: 875: 866: 864: 858: 857: 855: 854: 849: 844: 839: 834: 829: 824: 819: 813: 811: 804: 794: 793: 790: 789: 787: 786: 781: 779:Shear strength 776: 771: 766: 761: 756: 754:Friction angle 751: 746: 741: 736: 731: 726: 721: 715: 713: 709: 708: 706: 705: 700: 695: 690: 685: 680: 675: 669: 667: 660: 654: 653: 650: 649: 647: 642: 637: 635:Oedometer test 632: 627: 625:Sieve analysis 622: 617: 612: 607: 602: 597: 592: 587: 585: 577: 576: 573: 572: 566: 565: 559: 558: 552: 551: 545: 544: 538: 537: 526: 525: 514: 513: 511:Total sounding 502: 501: 490: 489: 478: 477: 466: 465: 464: 463: 453: 437: 436: 425: 424: 413: 412: 401: 400: 389: 388: 377: 376: 365: 364: 363: 362: 357: 343: 342: 341: 340: 335: 330: 314: 313: 302: 301: 290: 289: 278: 277: 266: 265: 263: 252: 242: 241: 236: 233: 232: 225: 224: 217: 210: 202: 196: 195: 188: 187:External links 185: 182: 181: 174: 154: 130: 112: 111: 109: 106: 100: 97: 87: 84: 9: 6: 4: 3: 2: 1363: 1352: 1349: 1348: 1346: 1329: 1326: 1325: 1324: 1321: 1319: 1316: 1314: 1311: 1309: 1306: 1304: 1301: 1299: 1296: 1294: 1291: 1289: 1288:Geomorphology 1286: 1284: 1281: 1279: 1276: 1274: 1271: 1269: 1266: 1265: 1263: 1261: 1257: 1251: 1248: 1246: 1243: 1241: 1238: 1236: 1233: 1231: 1228: 1226: 1223: 1222: 1220: 1218: 1212: 1202: 1198: 1195: 1191: 1188: 1186: 1183: 1181: 1178: 1176: 1173: 1171: 1168: 1167: 1165: 1162: 1158: 1155: 1153: 1150: 1148: 1145: 1144: 1143: 1140: 1138: 1135: 1133: 1132:Consolidation 1130: 1128: 1127:Frost heaving 1125: 1123: 1120: 1119: 1117: 1111: 1105: 1102: 1100: 1097: 1095: 1092: 1090: 1087: 1085: 1082: 1081: 1079: 1075: 1072: 1070: 1066: 1056: 1053: 1051: 1048: 1047: 1045: 1043: 1039: 1033: 1030: 1026: 1023: 1021: 1018: 1016: 1013: 1011: 1008: 1007: 1006: 1005:Geosynthetics 1003: 1001: 1000:Crushed stone 998: 996: 993: 991: 988: 986: 983: 981: 978: 976: 973: 971: 968: 966: 963: 961: 958: 956: 955:Cut-and-cover 953: 951: 948: 946: 943: 941: 938: 936: 933: 931: 928: 926: 923: 921: 918: 916: 913: 909: 906: 904: 901: 899: 896: 894: 891: 889: 886: 884: 881: 879: 876: 874: 871: 870: 868: 867: 865: 863: 859: 853: 850: 848: 845: 843: 840: 838: 835: 833: 830: 828: 825: 823: 820: 818: 815: 814: 812: 808: 805: 802: 795: 785: 782: 780: 777: 775: 772: 770: 767: 765: 762: 760: 757: 755: 752: 750: 747: 745: 742: 740: 737: 735: 732: 730: 727: 725: 724:Water content 722: 720: 717: 716: 714: 710: 704: 701: 699: 696: 694: 691: 689: 686: 684: 681: 679: 676: 674: 671: 670: 668: 664: 661: 659: 655: 646: 643: 641: 638: 636: 633: 631: 628: 626: 623: 621: 618: 616: 613: 611: 608: 606: 603: 601: 598: 596: 593: 591: 588: 586: 584: 578: 571: 568: 567: 564: 561: 560: 557: 554: 553: 550: 547: 546: 543: 540: 539: 536: 532: 528: 527: 524: 520: 516: 515: 512: 508: 504: 503: 500: 496: 492: 491: 488: 484: 480: 479: 476: 472: 468: 467: 462: 458: 454: 452: 448: 444: 443: 442: 439: 438: 435: 431: 427: 426: 423: 422:Sample series 419: 415: 414: 411: 407: 403: 402: 399: 395: 391: 390: 387: 383: 379: 378: 375: 371: 367: 366: 361: 358: 356: 353: 352: 349: 345: 344: 339: 336: 334: 331: 329: 326: 325: 324: 320: 316: 315: 312: 308: 304: 303: 300: 296: 292: 291: 288: 284: 280: 279: 276: 272: 268: 267: 264: 261: 256: 253: 247: 246:Investigation 243: 239: 234: 230: 223: 218: 216: 211: 209: 204: 203: 200: 194: 191: 190: 177: 175:9780070555167 171: 167: 166: 158: 150: 143: 137: 135: 126: 120: 118: 113: 105: 96: 92: 83: 81: 77: 73: 69: 67: 61: 59: 55: 51: 47: 42: 34: 30: 25: 19: 1308:Biogeography 1303:Hydrogeology 1293:Soil science 1273:Geochemistry 1032:Infiltration 960:Cut and fill 907: 903:Soil nailing 769:Permeability 734:Bulk density 451:Inclinometer 374:Ram sounding 259: 164: 157: 148: 102: 93: 89: 70: 62: 40: 38: 1318:Archaeology 1042:Foundations 1015:Geomembrane 898:Slurry wall 837:Water table 801:Interaction 797:Structures 784:Sensitivity 581:Laboratory 125:"Tie-backs" 33:Ground Zero 29:slurry wall 1175:Mitigation 1157:Shear wave 1142:Earthquake 1137:Compaction 1122:Permafrost 1113:Phenomena/ 1010:Geotextile 935:Embankment 925:Excavation 862:Earthworks 822:Vegetation 817:Topography 739:Thixotropy 729:Void ratio 712:Properties 610:Hydrometer 355:Piezometer 275:Core drill 108:References 35:, New York 1298:Hydrology 1278:Petrology 1166:analysis 1164:Landslide 1069:Mechanics 980:Track bed 965:Fill dirt 950:Terracing 523:Trial pit 338:Statnamic 323:Load test 50:structure 1345:Category 1328:Agrology 1217:software 1115:problems 945:Causeway 920:Landfill 847:Subgrade 764:Porosity 759:Cohesion 1268:Geology 1240:SVSlope 1050:Shallow 970:Grading 908:Tieback 852:Subsoil 842:Bedrock 832:Topsoil 827:Terrain 620:R-value 583:testing 333:Dynamic 260:in situ 258:Field ( 99:Testing 80:tensile 58:seawall 41:tieback 1250:Plaxis 1245:UTEXAS 1235:SVFlux 1225:SEEP2D 1077:Forces 930:Trench 878:Gabion 688:Gravel 328:Static 172:  76:torque 1230:STABL 703:Loess 666:Types 145:(PDF) 66:Grout 1055:Deep 698:Loam 693:Peat 683:Sand 678:Silt 673:Clay 658:Soil 360:Well 170:ISBN 940:Cut 249:and 31:at 1347:: 1199:* 168:. 147:. 133:^ 116:^ 39:A 803:) 799:( 262:) 221:e 214:t 207:v 178:. 151:. 127:. 20:.

Index

Tieback (disambiguation)

slurry wall
Ground Zero
retaining walls
structure
anchored into earth
seawall
Grout
Helical anchors
torque
tensile


"Tie-backs"


"Ground Anchors and Anchored Systems"
Tiebacks in foundation engineering and construction
ISBN
9780070555167
California Department of Transportation tieback document
v
t
e
Geotechnical engineering
Offshore geotechnical engineering
Investigation

Core drill

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.