Knowledge

MeyGen

Source 📝

1061: 1033: 1047: 300:, to construct up to 61 two or three-bladed turbines with a total installed capacity of 86 MW. This was subject to construction in a phased manner so that potential environmental impacts could be understood. Each turbine was limited to 16-20 m in rotor diameter, rated at 1.0-2.4 MW, and connected to the grid by 6.6 kV cable. 381:. These are all three-bladed horizontal-axis turbines with an 18 m rotor diameter, that reach the 1.5 MW rated power at a current speed of 3 m/s. They are mounted on three-legged gravity foundations that sit on the seabed, each weighing around 350 tonnes with six 200 tonne ballast blocks. 321:
Phase 1b was initially planned to add a further 4 MW comprising two AR2000 turbines, with another 73.5 MW in Phase 1c. Phase 1b was then revised to installing four turbines, bringing the total to eight. This required the Section 36 consent to be varied, to allow the additional two turbines
336:
Four further contracts totalling 21.94 MW were awarded in the CfD AR5 auction in September 2023. An application was then submitted to vary the license conditions, to permit a smaller number of larger turbines to be used. These would be up to 24 m in diameter, remove the limit on the rated
317:
Some elements of the project were constructed outwith the licensed area, however after statutory consultation Marine Scotland varied the license in September 2017 to extend the consented site area. It was considered there were no additional impacts and that asking for full removal may have had
340:
As of January 2024, the plan is to install the next 28 MW of turbines as Phase 2 to be commissioned by 2027, and a further 22 MW as Phase 3 by 2028. Phase 2 is planned to consist of a further 10 turbines.
313:
In December 2016 it was announced that the first turbine had begun full power operations, and all four turbines were installed by February 2017. Phase 1 (formerly called Phase 1a) began operations in April 2018.
306:
granted the project a license in January 2014. This initially only lasted until the end of 2020, but was extended in July 2016 to cover the period until 1 January 2041 or 25 years after completion of phase 1a.
539: 384:
The turbines in phase 1 are connected to the onshore power conversion centre at Ness of Quoys by an individual cable per turbine. These are laid on the seabed, with landfall by 550 m long
330: 310:
Construction work on the project started in January 2015, building an access road towards the sea where the onshore power conversion building would be located.
1004: 388:
conduits, installed in July 2015. The cables were installed by James Fisher Marine Services by November 2015, with a total length of 11 km. This used the
528: 347:
The site has the potential for a further 312 MW to be deployed beyond that, subject to expanding the consent. This would amount to 398 MW in total.
370: 690: 953: 350:
By 2018 the four turbines had produced 8 GWh. In 2019, they produced 13.8 GWh. Total cumulative production was 51 GWh by March 2023.
472: 500: 897: 639: 580: 46: 916: 333:(CfD) Allocation Round 4 (AR4), which will be used to support the construction of Phase 2 which is now due to be commissioned in 2027 1084: 846: 793: 767: 553: 934: 717: 344:
In September 2024, the MeyGen project was awarded a further 9 MW in the CfD AR6 auction, to be delivered in 2028/29.
640:"Marine Licence - MeyGen Tidal Energy Project - Inner Sound, Pentland Firth - 04577 | Marine Scotland Information" 385: 358: 979: 253:
The high speed of currents in the area, reaching up to 5 m/s (11 mph), made the chosen site in the
326: 246:. Meygen was claimed to be the "world’s largest tidal stream power project". There are plans for up to 400 742: 664: 917:"A tidal project in Scottish waters just generated enough electricity to power nearly 4,000 homes" 447: 227:
It is currently being constructed in a phased manner. The first phase of the project uses four 1.5
1066: 136: 125: 374: 239: 231:
MW turbines with 18 m (59 ft) rotor diameter which were installed submerged on the
94: 337:
power per turbine, and increase the maximum voltage of the underwater cables to 33 kV.
117: 325:
In July 2022, MeyGen plc was awarded a contract to supply 28 MW of electricity to the
297: 8: 389: 243: 557: 303: 270: 173: 221: 1038: 871: 534: 451: 378: 821: 421: 274: 254: 217: 183: 1078: 266: 61: 48: 1052: 477: 278: 195: 898:"SIMEC Atlantis partners with GE on world's largest tidal stream turbine" 322:
above the six permitted in Phase 1. However, this phase did not proceed.
213: 265:
In October 2010, the newly named "MeyGen" tidal project from the nearby
529:"Wave goodbye to hope of tidal energy exports, Scots politicians told" 691:"Atlantis' first MeyGen tidal turbine starts operating at full power" 614: 290: 1060: 1005:"Subsea Cables Successfully Deployed in MeyGen Tidal Energy Project" 954:"Simec Atlantis Energy wins £1.5m Scot Gov grant for Meygen project" 473:"World's first large-scale tidal energy farm launches in Scotland" 369:
Phase 1 of the project comprises four 1.5 MW turbines, three
1046: 397: 361:
in 2020, to develop a sub-sea hub to connect multiple turbines.
581:"World's biggest 'wave farm' in crisis as RWE npower pulls out" 400:
window. The onshore power conversion equipment was supplied by
232: 216:
plant in the north of Scotland. The project is located in the
448:"Scotland unveils world's largest tidal stream power project" 847:"Contracts for Difference (CfD) Allocation Round 6: results" 794:"Contracts for Difference (CfD) Allocation Round 5: results" 768:"Contracts for Difference (CfD) Allocation Round 4: results" 501:"Atlantis installs fourth and final Meygen Phase 1A turbine" 242:, although previously by Tidal Power Scotland Limited and 935:"SAE Deploys Upgraded Turbine at MeyGen Tidal Power Site" 401: 269:
and "Gen" for generation was created by a consortium of
296:
A consent was granted in 2013, under Section 36 of the
1028: 977: 527: 1076: 257:well suited to this type of energy generation. 519: 743:"MeyGen Tidal Power Project, Pentland Firth" 612: 357:million Scottish Government grant from the 220:, specifically the Inner Sound between the 978:rebeccavandenberge (16 September 2015). 945: 914: 718:"Meygen Starts 25 year operations phase" 572: 277:and received operational lease from the 615:MeyGen Tidal Array EIA Screening Report 554:"Major Scottish tidal project unveiled" 1077: 980:"Atlantis Team Rocking MeyGen Project" 951: 864: 578: 525: 445: 364: 816: 814: 737: 735: 733: 731: 715: 377:AR1500 developed in conjunction with 895: 634: 632: 608: 606: 604: 602: 465: 915:Frangoul, Anmar (27 January 2020). 359:Saltire Tidal Energy Challenge Fund 13: 811: 728: 446:Dickie, Mure (12 September 2016). 396:, and was completed over a 2½ day 289:years. In 2011 Norwegian partners 250:MW to be installed at the site. 14: 1096: 665:"MeyGen construction work starts" 629: 613:Xodus Group (22 September 2023). 599: 542:from the original on 12 May 2022. 439: 1085:Tidal power stations in Scotland 1059: 1045: 1031: 716:White, Matthew (12 April 2008). 238:The project is owned and run by 997: 971: 952:McPhee, David (25 March 2020). 927: 908: 896:Hill, Joshua S (24 June 2019). 889: 839: 786: 760: 709: 683: 657: 579:Donald, Colin (24 July 2011). 546: 526:Connor, Steve (10 July 2013). 493: 414: 386:horizontal directional drilled 112:Tidal power station 1: 407: 293:pulled out of the project. 7: 224:and the Scottish mainland. 210:MeyGen tidal energy project 184:Annual net output 10: 1101: 939:Offshore Engineer Magazine 669:Offshore Engineer Magazine 260: 353:The project received £1.5 192: 182: 172: 160: 156: 151: 134: 116: 111: 103: 93: 85: 77: 40: 32: 28: 23: 371:Andritz Hydro Hammerfest 331:Contracts for difference 1067:Renewable energy portal 174:Nameplate capacity 86:Construction began 178:6 MW (4 × 1.5 MW) 165:Units operational 126:Tidal stream generator 876:SIMEC ATLANTIS ENERGY 240:SIMEC Atlantis Energy 152:Power generation 107:SIMEC Atlantis Energy 16:Tidal energy facility 235:in winter 2016/17. 95:Commission date 62:58.65833°N 3.12500°W 1009:Hydro International 481:. 12 September 2016 373:AH1000 MK1 and one 365:Project description 244:Scottish Enterprise 214:tidal stream energy 58: /  558:New Civil Engineer 507:. 20 February 2017 375:Atlantis Resources 318:adverse impacts. 271:Atlantis Resources 135:Type of  67:58.65833; -3.12500 1011:. 3 November 2015 697:. 7 December 2016 671:. 21 January 2015 560:. 28 October 2010 285:MW project for 25 203: 202: 1092: 1069: 1064: 1063: 1055: 1050: 1049: 1041: 1036: 1035: 1034: 1021: 1020: 1018: 1016: 1001: 995: 994: 992: 990: 975: 969: 968: 966: 964: 949: 943: 942: 931: 925: 924: 912: 906: 905: 893: 887: 886: 884: 882: 868: 862: 861: 859: 857: 843: 837: 836: 834: 832: 818: 809: 808: 806: 804: 790: 784: 783: 781: 779: 764: 758: 757: 755: 753: 739: 726: 725: 713: 707: 706: 704: 702: 695:Power Technology 687: 681: 680: 678: 676: 661: 655: 654: 652: 650: 636: 627: 626: 624: 622: 610: 597: 596: 594: 592: 576: 570: 569: 567: 565: 550: 544: 543: 531: 523: 517: 516: 514: 512: 497: 491: 490: 488: 486: 469: 463: 462: 460: 458: 443: 437: 436: 434: 432: 418: 356: 288: 284: 249: 230: 222:Island of Stroma 196:edit on Wikidata 73: 72: 70: 69: 68: 63: 59: 56: 55: 54: 51: 21: 20: 1100: 1099: 1095: 1094: 1093: 1091: 1090: 1089: 1075: 1074: 1073: 1072: 1065: 1058: 1051: 1044: 1039:Scotland portal 1037: 1032: 1030: 1025: 1024: 1014: 1012: 1003: 1002: 998: 988: 986: 976: 972: 962: 960: 950: 946: 933: 932: 928: 913: 909: 894: 890: 880: 878: 870: 869: 865: 855: 853: 845: 844: 840: 830: 828: 820: 819: 812: 802: 800: 792: 791: 787: 777: 775: 774:. UK Government 766: 765: 761: 751: 749: 741: 740: 729: 714: 710: 700: 698: 689: 688: 684: 674: 672: 663: 662: 658: 648: 646: 644:marine.gov.scot 638: 637: 630: 620: 618: 611: 600: 590: 588: 577: 573: 563: 561: 552: 551: 547: 535:The Independent 524: 520: 510: 508: 499: 498: 494: 484: 482: 471: 470: 466: 456: 454: 452:Financial Times 444: 440: 430: 428: 420: 419: 415: 410: 379:Lockheed Martin 367: 354: 304:Marine Scotland 298:Electricity Act 286: 282: 263: 247: 228: 199: 188:10.2 GWh (2023) 147: 144:Horizontal axis 130: 66: 64: 60: 57: 52: 49: 47: 45: 44: 17: 12: 11: 5: 1098: 1088: 1087: 1071: 1070: 1056: 1042: 1027: 1026: 1023: 1022: 996: 970: 944: 941:. 5 July 2023. 926: 907: 888: 863: 838: 826:SAE Renewables 810: 785: 759: 727: 708: 682: 656: 628: 598: 571: 545: 518: 492: 464: 438: 426:SAE Renewables 412: 411: 409: 406: 366: 363: 275:Morgan Stanley 262: 259: 255:Pentland Firth 218:Pentland Firth 201: 200: 193: 190: 189: 186: 180: 179: 176: 170: 169: 166: 162: 161: 158: 157: 154: 153: 149: 148: 146: 145: 141: 139: 132: 131: 129: 128: 122: 120: 114: 113: 109: 108: 105: 101: 100: 97: 91: 90: 87: 83: 82: 79: 75: 74: 42: 38: 37: 34: 30: 29: 26: 25: 15: 9: 6: 4: 3: 2: 1097: 1086: 1083: 1082: 1080: 1068: 1062: 1057: 1054: 1048: 1043: 1040: 1029: 1010: 1006: 1000: 985: 984:Offshore Wind 981: 974: 959: 955: 948: 940: 936: 930: 922: 918: 911: 903: 899: 892: 877: 873: 867: 852: 848: 842: 827: 823: 817: 815: 799: 795: 789: 773: 769: 763: 748: 744: 738: 736: 734: 732: 723: 719: 712: 696: 692: 686: 670: 666: 660: 645: 641: 635: 633: 616: 609: 607: 605: 603: 586: 585:Sunday Herald 582: 575: 559: 555: 549: 541: 537: 536: 530: 522: 506: 502: 496: 480: 479: 474: 468: 453: 449: 442: 427: 423: 417: 413: 405: 403: 399: 395: 391: 387: 382: 380: 376: 372: 362: 360: 351: 348: 345: 342: 338: 334: 332: 328: 323: 319: 315: 311: 308: 305: 301: 299: 294: 292: 280: 276: 272: 268: 267:Castle of Mey 258: 256: 251: 245: 241: 236: 234: 225: 223: 219: 215: 211: 207: 197: 191: 187: 185: 181: 177: 175: 171: 167: 164: 163: 159: 155: 150: 143: 142: 140: 138: 133: 127: 124: 123: 121: 119: 115: 110: 106: 102: 98: 96: 92: 88: 84: 80: 76: 71: 43: 39: 35: 31: 27: 22: 19: 1053:Water portal 1013:. Retrieved 1008: 999: 987:. Retrieved 983: 973: 961:. Retrieved 958:Energy Voice 957: 947: 938: 929: 920: 910: 902:RenewEconomy 901: 891: 879:. Retrieved 875: 866: 854:. Retrieved 850: 841: 829:. Retrieved 825: 801:. Retrieved 797: 788: 776:. Retrieved 771: 762: 750:. Retrieved 746: 721: 711: 699:. Retrieved 694: 685: 673:. Retrieved 668: 659: 647:. Retrieved 643: 619:. Retrieved 589:. Retrieved 584: 574: 562:. Retrieved 548: 533: 521: 509:. Retrieved 504: 495: 483:. Retrieved 478:The Guardian 476: 467: 455:. Retrieved 441: 429:. Retrieved 425: 416: 393: 383: 368: 352: 349: 346: 343: 339: 335: 324: 320: 316: 312: 309: 302: 295: 279:Crown Estate 264: 252: 237: 226: 209: 205: 204: 18: 856:3 September 803:25 November 722:4c Offshore 591:17 February 511:26 February 505:4c Offshore 431:18 December 394:Siem Daya 1 208:(full name 81:Operational 65: / 41:Coordinates 1015:27 January 989:27 January 881:13 January 831:27 January 778:13 January 752:27 January 701:9 December 675:27 January 649:27 January 621:27 January 564:9 December 485:9 December 457:9 December 408:References 50:58°39′30″N 747:NS Energy 587:. Glasgow 398:neap tide 291:Statkraft 273:Limited, 1079:Category 872:"MeyGen" 822:"MeyGen" 617:(Report) 540:Archived 422:"MeyGen" 281:to a 400 104:Owner(s) 53:3°7′30″W 36:Scotland 963:20 July 392:vessel 329:in the 327:GB grid 261:History 212:) is a 33:Country 851:GOV.UK 798:GOV.UK 772:GOV.UK 355:  287:  283:  248:  233:seabed 229:  206:MeyGen 78:Status 24:MeyGen 194:[ 1017:2024 991:2024 965:2020 921:CNBC 883:2023 858:2024 833:2024 805:2023 780:2023 754:2024 703:2016 677:2024 651:2024 623:2024 593:2024 566:2016 513:2017 487:2016 459:2016 433:2023 118:Type 99:2016 89:2014 402:ABB 137:TSG 1081:: 1007:. 982:. 956:. 937:. 919:. 900:. 874:. 849:. 824:. 813:^ 796:. 770:. 745:. 730:^ 720:. 693:. 667:. 642:. 631:^ 601:^ 583:. 556:. 538:. 532:. 503:. 475:. 450:. 424:. 404:. 390:DP 1019:. 993:. 967:. 923:. 904:. 885:. 860:. 835:. 807:. 782:. 756:. 724:. 705:. 679:. 653:. 625:. 595:. 568:. 515:. 489:. 461:. 435:. 198:] 168:4

Index

58°39′30″N 3°7′30″W / 58.65833°N 3.12500°W / 58.65833; -3.12500
Commission date
Type
Tidal stream generator
TSG
Nameplate capacity
Annual net output
edit on Wikidata
tidal stream energy
Pentland Firth
Island of Stroma
seabed
SIMEC Atlantis Energy
Scottish Enterprise
Pentland Firth
Castle of Mey
Atlantis Resources
Morgan Stanley
Crown Estate
Statkraft
Electricity Act
Marine Scotland
GB grid
Contracts for difference
Saltire Tidal Energy Challenge Fund
Andritz Hydro Hammerfest
Atlantis Resources
Lockheed Martin
horizontal directional drilled
DP

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.