337:
350:
280:
451:. Construction had to withstand the pressure exerted by the Walchensee on the embankment, so that the road did not slide away. If the water level in winter falls due to outflow through the Walchensee power station, use of the road by trucks is limited by weight restrictions. In spring plant operators are obligated to increase the water level again in such a way that traffic restrictions — primarily affecting tourism — can be lifted or penalties are imposed. During winter operators must monitor the snow accumulated in the catchment area to calculate the amount of melt water expected and to comply with water level requirements. As of 2010, the Walchensee, along with other Bavarian power stations in the region, produce 1.3
471:
were in doubt. In 1915, von Miller suggested integrating the proposed power station into the region's power grid and the state-owned power supply company
Bayernwerk. The Bavarian parliament agreed to the construction of the power plant in 1918. Construction began in December 1918 and in 1924 the plant began producing electrical power. The problem of transporting that power over long distances was solved with the introduction of overhead power lines. From the outset, demand for power was so great that hydroelectricity could only provide a third of the required output, with the balance being supplied by
329:
42:
384:
water turbines with three-phase generators, and then exits into the
Kochelsee. Because the water level constantly changes, neither lake fully freezes in the winter; what does freeze on the lakes is potentially hazardous thin ice. The natural outflow of the Walchensee at Niedernach — over the Jachen
434:
The Rißbach comes from the northern part of the
Karwendel mountains, where it gathers the water of smaller streams in the Ahornboden area. After crossing the border between Tirol and Bavaria, and immediately after the inlet of the Fermersbach, a 6960 m lug carries water to the hydro-electric power
470:
was the developer and designer of the
Walchensee power station. It was initially intended to support the electrification of the Bavarian railways, but the project was suspended by the Bavarian parliament in 1912. It was believed too much electric power would be generated and the economic benefits
321:. The installed capacity is 124 MW with an annual production of 300 GWh. The power plant is south of Kochelsee, about 14 km (8.7 mi) from the village of Walchensee. It is one of the largest of its kind in Germany and has been owned by
417:
by a weir to form the Krüner Isar reservoir (870 m/2,850 ft) and is then diverted to the
Walchensee. This water flows past the Krün hydroelectric plant in an open channel, through a culvert, under the B 11 road at
369:(599 m/1,965 ft a.s.l.) to generate electricity. Through six, 450 m (1,480 ft) ducts connecting the two natural lakes, the water flows to the hydro-electric plant's four
76:
781:
684:
393:, but the natural inflow to the lake is still insufficient to provide enough water to the reservoir for the operation of the power station, so the waters of the
723:
426:
begins. At the end the water enters the hydro-electric power plant at (795 m/2,608 ft), propels the turbines, and finally flows into the lake.
791:
786:
336:
595:
349:
279:
624:
569:
17:
680:
516:
796:
658:
503:, a new Mach 10 wind tunnel was planned at the power station. The new power plant was to use the 202 meter difference from
754:
717:
707:
563:
310:
435:
plant at
Niedernach at the southeast end of the Walchensee. The power station has been in operation since 1951.
255:
298:
591:
508:
422:
and then via a tunnel to the
Sachensee lake (867 m/2,844 ft). Here a 3.9 kilometer long
747:
Secret Agenda: The United States
Government, Nazi Scientists, and Project Paperclip, 1945 to 1990
377:
617:
553:
444:
8:
527:
504:
500:
213:
507:
to generate 120 megawatts. However, instead of a new wind tunnel and power plant, the
479:(Bavarian Works Company). Bayernwerk was later denationalised and taken over by VIAG (
750:
713:
559:
365:(acting as the upper reservoir, at 802 m/2,631 ft above sea level) and the
654:
526:, and the new powerplant was completed after the war. The wind tunnel was moved to
467:
456:
472:
381:
226:
459:
electricity annually, i.e. the supply of close to 400,000 Bavarian households.
358:
236:
177:
775:
373:
187:
91:
78:
523:
328:
496:
370:
405:
The Isar, which flows as a whitewater river from the
Austrian part of the
448:
592:"Oberland.de - das Online-Magazin - OBERLAND - Hier find ich's obergut!"
512:
410:
362:
314:
135:
60:
394:
406:
366:
318:
150:
423:
219:
419:
306:
302:
414:
242:
618:"The Walchensee Power Plant. A Technological Jewel in the Alps"
322:
119:
64:
41:
484:
390:
386:
452:
483:) and as a result the power station is now operated by
515:
development was moved to the site following the 1943
475:. The plant was originally owned by the state-owned
782:
Buildings and structures in Bad Tölz-Wolfratshausen
773:
443:The main road from the village of Walchensee to
551:
361:of about 200 m (660 ft) between the
552:Hollister-Short, Graham (30 September 2016).
749:. New York: St.Martin's Press. p. 31.
490:
40:
681:"Walchensee Hydroelectric Power Station"
649:
647:
645:
348:
335:
327:
278:
792:Hydroelectric power stations in Germany
787:Energy infrastructure completed in 1924
705:
438:
14:
774:
699:
687:from the original on 24 September 2015
630:from the original on 22 September 2013
558:. Bloomsbury Publishing. p. 113.
344:
726:from the original on 29 November 2021
709:The Peenemunde Wind Tunnels: A Memoir
661:from the original on 12 November 2021
642:
572:from the original on 29 November 2021
744:
547:
545:
543:
505:the Walchensee down to the Kochelsee
738:
447:runs below the steep slopes of the
429:
24:
598:from the original on 14 March 2016
481:Vereinigte Industrieunternehmungen
25:
808:
767:
540:
400:
317:which is then released into the
712:. Yale University. p. 32.
797:1924 establishments in Germany
673:
610:
584:
13:
1:
332:Changing of the Pelton wheels
7:
357:The power station uses the
313:that is fed water from the
299:hydroelectric power station
10:
813:
462:
706:Wegener, Peter P (1996).
248:
235:
225:
212:
204:
196:
186:
176:
161:
156:
146:
141:
131:
126:
115:
107:
70:
56:
48:
39:
34:
29:Dam in Walchensee, Kochel
657:(in German). Uniper SE.
533:
491:World War II wind tunnel
283:Overview of the turbines
35:Walchensee power station
18:Lake Walchen Power Plant
378:single-phase generators
214:Installed capacity
354:
341:
333:
323:Uniper Kraftwerke GmbH
292:
289:Walchensee Power Plant
284:
237:Annual generation
655:"Walchenseekraftwerk"
555:History of Technology
397:river are also used.
352:
339:
331:
311:storage power station
282:
92:47.63000°N 11.33750°E
745:Hunt, Linda (1991).
623:. e.on Wesserkraft.
509:Mach 4.4 wind tunnel
439:Distinctive features
409:, is dammed between
227:Capacity factor
162:Commission date
683:. 4 December 2014.
528:White Oak, Maryland
407:Karwendel mountains
345:Technical operation
294:Walchenseekraftwerk
88: /
487:Wasserkraft GmbH.
389:— is blocked by a
355:
342:
334:
285:
97:47.63000; 11.33750
530:, after the war.
353:The six penstocks
340:The six penstocks
277:
276:
266:/unsere-standorte
16:(Redirected from
804:
761:
760:
742:
736:
735:
733:
731:
703:
697:
696:
694:
692:
677:
671:
670:
668:
666:
651:
640:
639:
637:
635:
629:
622:
614:
608:
607:
605:
603:
588:
582:
581:
579:
577:
549:
473:traction engines
468:Oskar von Miller
430:Rißbach transfer
273:
272:
269:
267:
265:
264:/unser-geschaeft
263:
261:
259:
257:
172:
170:
103:
102:
100:
99:
98:
93:
89:
86:
85:
84:
81:
44:
32:
31:
21:
812:
811:
807:
806:
805:
803:
802:
801:
772:
771:
770:
765:
764:
757:
743:
739:
729:
727:
720:
704:
700:
690:
688:
679:
678:
674:
664:
662:
653:
652:
643:
633:
631:
627:
620:
616:
615:
611:
601:
599:
590:
589:
585:
575:
573:
566:
550:
541:
536:
493:
465:
441:
432:
403:
347:
254:
253:
252:
197:Pump-generators
168:
166:
142:Lower reservoir
127:Upper reservoir
122:Kraftwerke GmbH
96:
94:
90:
87:
82:
79:
77:
75:
74:
30:
23:
22:
15:
12:
11:
5:
810:
800:
799:
794:
789:
784:
769:
768:External links
766:
763:
762:
755:
737:
718:
698:
672:
641:
609:
583:
564:
538:
537:
535:
532:
492:
489:
464:
461:
440:
437:
431:
428:
402:
399:
374:water turbines
359:hydraulic head
346:
343:
275:
274:
246:
245:
239:
233:
232:
229:
223:
222:
216:
210:
209:
206:
202:
201:
198:
194:
193:
190:
184:
183:
182:ca. 200 m
180:
178:Hydraulic head
174:
173:
163:
159:
158:
154:
153:
148:
144:
143:
139:
138:
133:
129:
128:
124:
123:
117:
113:
112:
109:
105:
104:
72:
68:
67:
58:
54:
53:
50:
46:
45:
37:
36:
28:
9:
6:
4:
3:
2:
809:
798:
795:
793:
790:
788:
785:
783:
780:
779:
777:
758:
756:0-312-05510-2
752:
748:
741:
725:
721:
719:0-300-06367-9
715:
711:
710:
702:
686:
682:
676:
660:
656:
650:
648:
646:
626:
619:
613:
597:
593:
587:
571:
567:
565:9781350018907
561:
557:
556:
548:
546:
544:
539:
531:
529:
525:
521:
520:
514:
510:
506:
502:
498:
488:
486:
482:
478:
477:Bayernwerk AG
474:
469:
460:
458:
454:
450:
446:
436:
427:
425:
421:
416:
412:
408:
401:Isar transfer
398:
396:
392:
388:
385:to the River
383:
379:
375:
372:
368:
364:
360:
351:
338:
330:
326:
324:
320:
316:
312:
308:
304:
300:
296:
295:
290:
281:
271:
251:
247:
244:
240:
238:
234:
230:
228:
224:
221:
217:
215:
211:
207:
203:
199:
195:
191:
189:
185:
181:
179:
175:
164:
160:
157:Power Station
155:
152:
149:
145:
140:
137:
134:
130:
125:
121:
118:
114:
110:
106:
101:
73:
69:
66:
62:
59:
55:
51:
47:
43:
38:
33:
27:
19:
746:
740:
728:. Retrieved
708:
701:
689:. Retrieved
675:
663:. Retrieved
634:21 September
632:. Retrieved
612:
600:. Retrieved
586:
574:. Retrieved
554:
518:
497:Nazi Germany
494:
480:
476:
466:
442:
433:
404:
356:
325:since 2016.
293:
288:
286:
249:
26:
665:12 November
522:bombing of
499:'s planned
495:To develop
449:Herzogstand
380:, and four
268:/walchensee
111:Operational
95: /
71:Coordinates
776:Categories
576:14 October
524:Peenemünde
517:Operation
513:V-2 rocket
501:A10 rocket
411:Mittenwald
363:Walchensee
315:Walchensee
309:. It is a
136:Walchensee
83:11°20′15″E
80:47°37′48″N
61:Walchensee
511:used for
457:renewable
367:Kochelsee
319:Kochelsee
291:(German:
151:Kochelsee
724:Archived
691:11 March
685:Archived
659:Archived
625:Archived
602:11 March
596:Archived
570:Archived
424:penstock
188:Turbines
116:Owner(s)
57:Location
730:21 July
463:History
420:Wallgau
395:Rißbach
382:Francis
307:Germany
303:Bavaria
297:) is a
260:.energy
258:.uniper
250:Website
167: (
147:Creates
132:Creates
52:Germany
49:Country
753:
716:
562:
445:Urfeld
371:Pelton
120:Uniper
108:Status
65:Kochel
628:(PDF)
621:(PDF)
534:Notes
519:Hydra
376:with
270:.html
231:27.6%
205:Pumps
751:ISBN
732:2021
714:ISBN
693:2015
667:2021
636:2013
604:2015
578:2019
560:ISBN
485:E.ON
415:Krün
413:and
391:weir
387:Isar
287:The
243:GW·h
241:300
218:124
169:1924
165:1924
455:of
453:TWh
301:in
262:/de
256:www
778::
722:.
644:^
594:.
568:.
542:^
305:,
220:MW
63:,
759:.
734:.
695:.
669:.
638:.
606:.
580:.
208:0
200:0
192:8
171:)
20:)
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.