Knowledge

Walchensee Hydroelectric Power Station

Source 📝

337: 350: 280: 451:. Construction had to withstand the pressure exerted by the Walchensee on the embankment, so that the road did not slide away. If the water level in winter falls due to outflow through the Walchensee power station, use of the road by trucks is limited by weight restrictions. In spring plant operators are obligated to increase the water level again in such a way that traffic restrictions — primarily affecting tourism — can be lifted or penalties are imposed. During winter operators must monitor the snow accumulated in the catchment area to calculate the amount of melt water expected and to comply with water level requirements. As of 2010, the Walchensee, along with other Bavarian power stations in the region, produce 1.3 471:
were in doubt. In 1915, von Miller suggested integrating the proposed power station into the region's power grid and the state-owned power supply company Bayernwerk. The Bavarian parliament agreed to the construction of the power plant in 1918. Construction began in December 1918 and in 1924 the plant began producing electrical power. The problem of transporting that power over long distances was solved with the introduction of overhead power lines. From the outset, demand for power was so great that hydroelectricity could only provide a third of the required output, with the balance being supplied by
329: 42: 384:
water turbines with three-phase generators, and then exits into the Kochelsee. Because the water level constantly changes, neither lake fully freezes in the winter; what does freeze on the lakes is potentially hazardous thin ice. The natural outflow of the Walchensee at Niedernach — over the Jachen
434:
The Rißbach comes from the northern part of the Karwendel mountains, where it gathers the water of smaller streams in the Ahornboden area. After crossing the border between Tirol and Bavaria, and immediately after the inlet of the Fermersbach, a 6960 m lug carries water to the hydro-electric power
470:
was the developer and designer of the Walchensee power station. It was initially intended to support the electrification of the Bavarian railways, but the project was suspended by the Bavarian parliament in 1912. It was believed too much electric power would be generated and the economic benefits
321:. The installed capacity is 124 MW with an annual production of 300 GWh. The power plant is south of Kochelsee, about 14 km (8.7 mi) from the village of Walchensee. It is one of the largest of its kind in Germany and has been owned by 417:
by a weir to form the Krüner Isar reservoir (870 m/2,850 ft) and is then diverted to the Walchensee. This water flows past the Krün hydroelectric plant in an open channel, through a culvert, under the B 11 road at
369:(599 m/1,965 ft a.s.l.) to generate electricity. Through six, 450 m (1,480 ft) ducts connecting the two natural lakes, the water flows to the hydro-electric plant's four 76: 781: 684: 393:, but the natural inflow to the lake is still insufficient to provide enough water to the reservoir for the operation of the power station, so the waters of the 723: 426:
begins. At the end the water enters the hydro-electric power plant at (795 m/2,608 ft), propels the turbines, and finally flows into the lake.
791: 786: 336: 595: 349: 279: 624: 569: 17: 680: 516: 796: 658: 503:, a new Mach 10 wind tunnel was planned at the power station. The new power plant was to use the 202 meter difference from 754: 717: 707: 563: 310: 435:
plant at Niedernach at the southeast end of the Walchensee. The power station has been in operation since 1951.
255: 298: 591: 508: 422:
and then via a tunnel to the Sachensee lake (867 m/2,844 ft). Here a 3.9 kilometer long
747:
Secret Agenda: The United States Government, Nazi Scientists, and Project Paperclip, 1945 to 1990
377: 617: 553: 444: 8: 527: 504: 500: 213: 507:
to generate 120 megawatts. However, instead of a new wind tunnel and power plant, the
479:(Bavarian Works Company). Bayernwerk was later denationalised and taken over by VIAG ( 750: 713: 559: 365:(acting as the upper reservoir, at 802 m/2,631 ft above sea level) and the 654: 526:, and the new powerplant was completed after the war. The wind tunnel was moved to 467: 456: 472: 381: 226: 459:
electricity annually, i.e. the supply of close to 400,000 Bavarian households.
358: 236: 177: 775: 373: 187: 91: 78: 523: 328: 496: 370: 405:
The Isar, which flows as a whitewater river from the Austrian part of the
448: 592:"Oberland.de - das Online-Magazin - OBERLAND - Hier find ich's obergut!" 512: 410: 362: 314: 135: 60: 394: 406: 366: 318: 150: 423: 219: 419: 306: 302: 414: 242: 618:"The Walchensee Power Plant. A Technological Jewel in the Alps" 322: 119: 64: 41: 484: 390: 386: 452: 483:) and as a result the power station is now operated by 515:
development was moved to the site following the 1943
475:. The plant was originally owned by the state-owned 782:
Buildings and structures in Bad Tölz-Wolfratshausen
773: 443:The main road from the village of Walchensee to 551: 361:of about 200 m (660 ft) between the 552:Hollister-Short, Graham (30 September 2016). 749:. New York: St.Martin's Press. p. 31. 490: 40: 681:"Walchensee Hydroelectric Power Station" 649: 647: 645: 348: 335: 327: 278: 792:Hydroelectric power stations in Germany 787:Energy infrastructure completed in 1924 705: 438: 14: 774: 699: 687:from the original on 24 September 2015 630:from the original on 22 September 2013 558:. Bloomsbury Publishing. p. 113. 344: 726:from the original on 29 November 2021 709:The Peenemunde Wind Tunnels: A Memoir 661:from the original on 12 November 2021 642: 572:from the original on 29 November 2021 744: 547: 545: 543: 505:the Walchensee down to the Kochelsee 738: 447:runs below the steep slopes of the 429: 24: 598:from the original on 14 March 2016 481:Vereinigte Industrieunternehmungen 25: 808: 767: 540: 400: 317:which is then released into the 712:. Yale University. p. 32. 797:1924 establishments in Germany 673: 610: 584: 13: 1: 332:Changing of the Pelton wheels 7: 357:The power station uses the 313:that is fed water from the 299:hydroelectric power station 10: 813: 462: 706:Wegener, Peter P (1996). 248: 235: 225: 212: 204: 196: 186: 176: 161: 156: 146: 141: 131: 126: 115: 107: 70: 56: 48: 39: 34: 29:Dam in Walchensee, Kochel 657:(in German). Uniper SE. 533: 491:World War II wind tunnel 283:Overview of the turbines 35:Walchensee power station 18:Lake Walchen Power Plant 378:single-phase generators 214:Installed capacity 354: 341: 333: 323:Uniper Kraftwerke GmbH 292: 289:Walchensee Power Plant 284: 237:Annual generation 655:"Walchenseekraftwerk" 555:History of Technology 397:river are also used. 352: 339: 331: 311:storage power station 282: 92:47.63000°N 11.33750°E 745:Hunt, Linda (1991). 623:. e.on Wesserkraft. 509:Mach 4.4 wind tunnel 439:Distinctive features 409:, is dammed between 227:Capacity factor 162:Commission date 683:. 4 December 2014. 528:White Oak, Maryland 407:Karwendel mountains 345:Technical operation 294:Walchenseekraftwerk 88: /  487:Wasserkraft GmbH. 389:— is blocked by a 355: 342: 334: 285: 97:47.63000; 11.33750 530:, after the war. 353:The six penstocks 340:The six penstocks 277: 276: 266:/unsere-standorte 16:(Redirected from 804: 761: 760: 742: 736: 735: 733: 731: 703: 697: 696: 694: 692: 677: 671: 670: 668: 666: 651: 640: 639: 637: 635: 629: 622: 614: 608: 607: 605: 603: 588: 582: 581: 579: 577: 549: 473:traction engines 468:Oskar von Miller 430:Rißbach transfer 273: 272: 269: 267: 265: 264:/unser-geschaeft 263: 261: 259: 257: 172: 170: 103: 102: 100: 99: 98: 93: 89: 86: 85: 84: 81: 44: 32: 31: 21: 812: 811: 807: 806: 805: 803: 802: 801: 772: 771: 770: 765: 764: 757: 743: 739: 729: 727: 720: 704: 700: 690: 688: 679: 678: 674: 664: 662: 653: 652: 643: 633: 631: 627: 620: 616: 615: 611: 601: 599: 590: 589: 585: 575: 573: 566: 550: 541: 536: 493: 465: 441: 432: 403: 347: 254: 253: 252: 197:Pump-generators 168: 166: 142:Lower reservoir 127:Upper reservoir 122:Kraftwerke GmbH 96: 94: 90: 87: 82: 79: 77: 75: 74: 30: 23: 22: 15: 12: 11: 5: 810: 800: 799: 794: 789: 784: 769: 768:External links 766: 763: 762: 755: 737: 718: 698: 672: 641: 609: 583: 564: 538: 537: 535: 532: 492: 489: 464: 461: 440: 437: 431: 428: 402: 399: 374:water turbines 359:hydraulic head 346: 343: 275: 274: 246: 245: 239: 233: 232: 229: 223: 222: 216: 210: 209: 206: 202: 201: 198: 194: 193: 190: 184: 183: 182:ca. 200 m 180: 178:Hydraulic head 174: 173: 163: 159: 158: 154: 153: 148: 144: 143: 139: 138: 133: 129: 128: 124: 123: 117: 113: 112: 109: 105: 104: 72: 68: 67: 58: 54: 53: 50: 46: 45: 37: 36: 28: 9: 6: 4: 3: 2: 809: 798: 795: 793: 790: 788: 785: 783: 780: 779: 777: 758: 756:0-312-05510-2 752: 748: 741: 725: 721: 719:0-300-06367-9 715: 711: 710: 702: 686: 682: 676: 660: 656: 650: 648: 646: 626: 619: 613: 597: 593: 587: 571: 567: 565:9781350018907 561: 557: 556: 548: 546: 544: 539: 531: 529: 525: 521: 520: 514: 510: 506: 502: 498: 488: 486: 482: 478: 477:Bayernwerk AG 474: 469: 460: 458: 454: 450: 446: 436: 427: 425: 421: 416: 412: 408: 401:Isar transfer 398: 396: 392: 388: 385:to the River 383: 379: 375: 372: 368: 364: 360: 351: 338: 330: 326: 324: 320: 316: 312: 308: 304: 300: 296: 295: 290: 281: 271: 251: 247: 244: 240: 238: 234: 230: 228: 224: 221: 217: 215: 211: 207: 203: 199: 195: 191: 189: 185: 181: 179: 175: 164: 160: 157:Power Station 155: 152: 149: 145: 140: 137: 134: 130: 125: 121: 118: 114: 110: 106: 101: 73: 69: 66: 62: 59: 55: 51: 47: 43: 38: 33: 27: 19: 746: 740: 728:. Retrieved 708: 701: 689:. Retrieved 675: 663:. Retrieved 634:21 September 632:. Retrieved 612: 600:. Retrieved 586: 574:. Retrieved 554: 518: 497:Nazi Germany 494: 480: 476: 466: 442: 433: 404: 356: 325:since 2016. 293: 288: 286: 249: 26: 665:12 November 522:bombing of 499:'s planned 495:To develop 449:Herzogstand 380:, and four 268:/walchensee 111:Operational 95: / 71:Coordinates 776:Categories 576:14 October 524:Peenemünde 517:Operation 513:V-2 rocket 501:A10 rocket 411:Mittenwald 363:Walchensee 315:Walchensee 309:. It is a 136:Walchensee 83:11°20′15″E 80:47°37′48″N 61:Walchensee 511:used for 457:renewable 367:Kochelsee 319:Kochelsee 291:(German: 151:Kochelsee 724:Archived 691:11 March 685:Archived 659:Archived 625:Archived 602:11 March 596:Archived 570:Archived 424:penstock 188:Turbines 116:Owner(s) 57:Location 730:21 July 463:History 420:Wallgau 395:Rißbach 382:Francis 307:Germany 303:Bavaria 297:) is a 260:.energy 258:.uniper 250:Website 167: ( 147:Creates 132:Creates 52:Germany 49:Country 753:  716:  562:  445:Urfeld 371:Pelton 120:Uniper 108:Status 65:Kochel 628:(PDF) 621:(PDF) 534:Notes 519:Hydra 376:with 270:.html 231:27.6% 205:Pumps 751:ISBN 732:2021 714:ISBN 693:2015 667:2021 636:2013 604:2015 578:2019 560:ISBN 485:E.ON 415:Krün 413:and 391:weir 387:Isar 287:The 243:GW·h 241:300 218:124 169:1924 165:1924 455:of 453:TWh 301:in 262:/de 256:www 778:: 722:. 644:^ 594:. 568:. 542:^ 305:, 220:MW 63:, 759:. 734:. 695:. 669:. 638:. 606:. 580:. 208:0 200:0 192:8 171:) 20:)

Index

Lake Walchen Power Plant

Walchensee
Kochel
47°37′48″N 11°20′15″E / 47.63000°N 11.33750°E / 47.63000; 11.33750
Uniper
Walchensee
Kochelsee
Hydraulic head
Turbines
Installed capacity
MW
Capacity factor
Annual generation
GW·h
www.uniper.energy/de/unser-geschaeft/unsere-standorte/walchensee.html

hydroelectric power station
Bavaria
Germany
storage power station
Walchensee
Kochelsee
Uniper Kraftwerke GmbH



hydraulic head
Walchensee
Kochelsee

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.