2151:. Various direct and indirect methods were used. Aerial and satellite images as well as investigations during the construction of the Autobahn (1930s) were evaluated. The mountains to be driven through were tested by, among other things, core drilling (mean distance: 500 metres, other source: 170 metres) extensively around the planned route and a directional borehole radar (range: around 20 to 30 metres around the boreholes), a 557 metres long exploratory tunnel was also driven into the mountain at the Irlahüll tunnel. The selective explorations showed a heterogeneous karst formation. A complete karst mapping was not carried out due to the mostly high overburden, with a necessary distance between boreholes of 20 to 30 metres. During the drive, anomalies were documented and explored with grid drilling. Depending on the degree of karstification, various measures were then taken, such as injection drilling up to 15 metres around the tube, cavity filling and piling; the inner shell was reinforced in places and the tunnel floor was structurally modified. According to DB information, karstification of this magnitude was not expected.
2456:
dissolving the loans as soon as possible and transferring them to the federal budget. The
Ministry of Transport stated that the federal government intends to follow this proposal as soon as sufficient budgetary funds were available. Since these were not initially available, the private pre-financing approved by the Bundestag was chosen in order to ensure that the economically desirable route was completed as quickly as possible. The Court of Auditors emphasised that with continuous private pre-financing, the amounts to be included in the federal budget after the commissioning of the railway for refinancing over a period of at least 15 years would be about as high as the average applications for household financing for construction during the construction phase of six to seven years. According to the Federal Railway Authority, between 1998 and April 2001 pre-financing amounts of €790 million were raised, which were taken over in 2000 and 2001 through financing from the federal budget. The total pre-financing costs amounted to around €30 million.
2460:
the existing network that arose as a result of the additional expenditure for major projects at
Deutsche Bahn. The repayment amounts saved by switching from loans to construction cost subsidies from DB AG were also not fully invested in the existing network. The resulting additional burden on the federal government led to the delay of other construction projects. Due to the fact that no upgrades were carried out, additional costs were incurred due to the necessary replacement investments. Overall more than €600 million was added to the federal budget, so the core target of the agreed maximum amount of financing was missed. The auditors also criticised the fact that the budget legislature had not been included in the measures taken by the Ministry of Transport and that it was not possible to precisely determine the additional burden "due to the lack of transparency in the financing commitments".
2843:
Ingolstadt Nord. In principle, there is a ban on passenger and freight trains meeting in tunnels at speeds over 250 km/h in
Germany. This regulation was specified in 1998 in an agreement between Deutsche Bahn, the Ministry of Transport and the Federal Railway Authority. Accordingly, such encounters are technically (not only in terms of the timetable) ruled out. Such a technical solution was not yet available at the time of commissioning. In 1999, the operating program provided for a total of 80 freight trains per day. The line is to be equipped with ETCS, which would enable safe separation of passenger and freight traffic, after 2017. A feasibility study on the widespread introduction of ETCS presented in September 2018 recommended equipping the route with ETCS by 2025. According to information from the end of 2019, the ETCS equipment of the new and upgraded line is now planned by 2023.
2171:(Munich) and the southern lot to a medium-sized bidding consortium led by Berger Bau (Passau) and Reiners Bau (Munich). Medium-sized companies accounted for DM 920 million, around 65 percent of the contracted work by value. A construction period of 53 months was planned for the new line to be completed, including around 15 months for the technical equipment. Commissioning was planned for the 2003 summer timetable. According to DB information, the short construction period forced construction to start quickly, which would have adversely affected preparation for the work. There was no time for cost optimisation, synergy effects would hardly have been achieved due to the many necessarily parallel work. This led to a shortage of experienced permanent staff at the construction companies.
2064:
Treuchtlingen and between
Treuchtlingen and Donauwörth for 200 km/h. In this solution, Augsburg was to be bypassed to the south, the Mering–Olching line was to be supplemented by two tracks and a long-distance railway replacement line was to be built in the Nuremberg area. Depending on the option, the Augsburg route would have been between 27 and 39 km longer than the Ingolstadt route. The results were presented to the Bavarian government on 29 June 1987. The government forwarded the report to its subordinate authorities, chambers of industry and commerce and the Bund Naturschutz for comments. On 2 and 3 May 1988, the Bavarian Ministry of Economics and Transport organised a discussion between these groups and Deutsche Bundesbahn.
2102:
repeatedly emphasized that the costs of such a solution would be underestimated, but the benefits would be overestimated. Furthermore, with the necessary construction during ongoing operations, long-term deterioration in operational quality was to be expected. The capacity of an upgrade only option was also not sufficient, the route length via
Augsburg was at least 28 kilometres longer. The Federal Court of Auditors stated in the same year that Deutsche Bundesbahn had calculated the Ingolstadt option too cheaply, but had artificially made the Augsburg option more expensive. The authorities calculated DM 3.89 billion (€1.99 billion) for the Ingolstadt option and DM 2.2 billion (€1.1 billion) for the Augsburg option.
2122:(BN) repeatedly opposed the line as a whole, in particular with reference to the upgrade option via Augsburg and the ecological impact of the new line. The environmental association stated, among other things, that the line was not objectively necessary for the public good. Among other things, the Bavarian Administrative Court dismissed complaints brought by the BN in a joint judgment and order dated 29 March 1996 and 10 January 1997. Constitutional complaints from BN were finally determined on 8 June 1998 by the Federal Constitutional Court when they were not admitted for trial and a related motion for an injunction was dismissed.
1882:
2452:
to the safety concept), increased environmental regulations and general wage and price increases. Delays in planning approval procedures on the upgraded section also contributed to the cost increases. The additional costs of the slab track, the use of which was only decided in 2000 and also contributed to cost increases, compared to the originally planned ballasted track are given by
Deutsche Bahn as one third. Savings of around €300 million result from the omission of some line improvements and station upgrades between Petershausen and Ingolstadt, with a maximum speed of 160 or 190 instead of 200 km/h throughout.
2239:
costs. Due to unexpected hydrological problems, Offenbau tunnel had to be built using a compressed air process. Large parts of
Euerwang Tunnel also had to be made water tight. Denkendorf Tunnel was built after massive landslides tripled its length and was built in groundwater. Karst formations in the area of the Altmühlalb were particularly noteworthy, which could not be bypassed on a large scale due to the width to build the line parallel with the autobahn. In the Irlahüll, Geisberg and Stammham tunnels, karst caves had to be backfilled. By the autumn of 2004, the shells of all tunnels were completed.
1874:
2436:—"Railway Crossing Act"). In addition to the financing agreement, the federal government financed individual sub-projects, such as the traffic facilities at Allersberg and Kinding stations (€4.7 million) and measures to protect roads from train cdashes. The federal government reported expenditure of €3.268 billion for the period up to 31 December 2007, of which €1.978 billion were federal funds. While the figure of €3.573 billion includes implemented and outstanding measures, the figure of €3.268 billion includes all costs actually incurred up to the end of 2007.
2068:
Bundesbahn and handed over to the
Bavarian State Ministry for Regional Development and Environmental Issues on 25 July 1989 to clarify the spatial planning issues, spatial planning permission was applied for and the spatial planning procedure was initiated. Six options were examined in the Nuremberg–Ingolstadt corridor, including a route to the west of the realised variant, via Pfahldorf, with a connection to the Munich–Treuchtlingen railway line near Gaimersheim. The documents were made public in September 1989 in the affected communities.
2083:
Augsburg variant were to be implemented, according to Dürr, four-tracking of the line between Roth and
Treuchtlingen would have been necessary. In the same letter, the CEO requested that the planning process be shortened to separate the projects for the new and upgraded Nuremberg–Ingolstadt–Munich line and the Mering bypass and four-tracking in the Augsburg area. The four-tracking of the line between Augsburg and Nuremberg was not to be pursued further, the four-tracking of the Augsburg-Munich line had become necessary for both options.
1570:
been upgraded for this speed. At the end of May 1981, a total of 256.3 kilometres of track sections could be operated at 200 km/h. A further acceleration of train traffic on the lines, mostly laid out in the 19th century for lower speeds, was generally not possible without major rerouting. For example, numerous narrow curves on the track in the Donauwörth–Nuremberg section (96.3 kilometres) only allowed speeds of up to 160 km/h in places. In the 1980s, long-distance travel between
Nuremberg and Munich was around one hour and 40 minutes.
1477:(at 300 km/h) of 100 millimetres. A longitudinal gradient of 2.0% is achieved in nine sections from 600 to 1,815 metres in length (in Geisberg tunnel). The railway embankments reach heights of up to 16 metres. 55 percent of the new line is on curves, with a minimum curve radius of 4,085 meters. The crossover to the opposite track branching off at the stations can be operated at 130 km/h, those on the platform tracks at 100 km/h. The establishment of a crossover in Lohen (line kilometre 42) was planned, but was later realised only as a
1319:
1366:
2384:
set at DM 7.0 billion, with the total amount including interest of DM 15.6 billion. The repayment was to be made in instalments of up to DM 622 million. The federal government would have taken over the construction and financing costs incurred by Deutsche Bahn at the latest from the time the system was commissioned. According to a media report from the end of 1995, the repayment was to be made in 25 annual installments from 2003. Payments amounting to a total of DM 15 billion would have been involved.
2479:
1307:
2444:
submitted a report to its supervisory board in which additional costs of at least DM 799 million were expected. Shortly thereafter, auditors determined a value of DM 1.6 billion. Of the expected unavoidable additional costs, DM 289 million was attributable to project development, DM 124 million for geological risks of the tunnel construction (which could only be assessed in 2000), and DM 119 million for control and safety technology as well as DM 112 million for fire and disaster protection.
2561:) of the locomotive were switched off for both record runs, which took place on the eastern track heading towards Nuremberg; encounters with trains could also be ruled out with certainty. Therefore, the entire line in front of the train (up to around 50 kilometres) had to be free of trains. Since there was only one ICE line running regularly on the high-speed route until the timetable change on 10 December 2006, these requirements could be met without any disruption to passenger traffic.
2212:
2315:
3006:
29:
722:
662:
485:
348:
2243:
1554:
5665:
2204:
1846:
through an open area towards the Altmühl valley. To the east of Kinding, the line would have crossed the Altmühl valley and the section running parallel with the autobahn would have been reached at Buch. From here the route would have been as in option 1. 59 kilometres of the total 174 kilometres of the route would have been designed for 250 km/h and 59 kilometres for 200 km/h. This option was affected by numerous constraints (particularly buildings).
1834:
high-voltage line. Weißenburg and Treuchtlingen would have been bypassed to the west. South of Treuchtlingen, from Möhren to north of Wörnitzstein, the existing line would have been affected, then line improvements in the Wörnitz valley. Longer sections of the existing route would have been abandoned after line improvements had been made. 203 kilometres total length, of which around 65 kilometres cleared for 250 km/h and 94 kilometres for 200 km/h.
2396:(€715.8/m), and the share of planning costs incurred after December 1996 was limited to ten percent of the total. These project costs did not include around €265 million contributed by third parties. This was used to finance the Allersberg, Kinding and Ingolstadt Nord stations, the removal of 14 level crossings between Ingolstadt and Munich, the expansion of park-and-ride facilities and the upgrade of the S-Bahn between Obermenzing and Dachau.
1853:. The new line was to run through the Sulz valley, touching on Mühlhausen and Berching. North of Beilngries, the new line would have turned west to leave the Sulz valley. The Altmühl valley would have been crossed east of Kinding (as in option 6) to then run parallel with the autobahn. The rest of the route would have been like option 1. 57 kilometres of the 180 kilometres would have been designed for 250 km/h and 59 kilometres for 200 km/h.
1382:
5510:
1137:
898:
884:
767:
753:
423:
409:
303:
2859:
1102:
1074:
1046:
1018:
990:
959:
856:
826:
798:
632:
604:
573:
545:
454:
1130:
385:
296:
2534:
1890:
1186:
378:
271:
891:
760:
416:
1161:
929:
693:
515:
325:
5675:
2420:
1462:
2404:
to the upgraded line. The commissioning of the new and upgraded line was planned for 2003; the expanded S-Bahn between Obermenzing and Dachau was to follow in 2004. The federal government's right to withdraw from private pre-financing was contractually stipulated in the financing agreement, which was invoked in 2000/2001. This avoided additional burdens on the federal budget of at least €5 billion.
2098:
long-distance passenger and 38 freight trains per day and direction in 2010 on the new line. In mid-1994, Deutsche Bahn calculated—now taking into account the segregation of fast and slow traffic—with 42 long-distance passenger trains and 20 freight trains. The route—via Ingolstadt—was included in the Federal Railways Expansion Act (BSchwAG) of 15 November 1993 in the version of 27 December 1993.
2523:
2115:(introduction to Ingolstadt). The new line was divided into 14 planning approval sections and two for the long-distance traction power lines. Up to 300 objections were raised by citizens in the individual procedures for the planning approval sections. Of a total of around 40 lawsuits and summary proceedings against the administrative acts, none led to success.
2094:
stations in Allersberg and Kinding, which were upgraded from overtaking to regional stations. The original planning (1991) envisaged a new line with a ballasted superstructure, with a maximum speed of 250 km/h and an extensive expansion of the Munich-Ingolstadt line for 200 km/h, with a section about ten kilometers long for 160 km/h.
1529:
scarce capital and limited technical choices. For the steam locomotives, which were comparatively slow by modern standards, a route that adapted to the mostly hilly terrain with numerous curves was sufficient. As early as 14 May 1863, Ludwig Joseph Freiherr von Brück, Director General of the Royal Bavarian Transport Authorities (
2565:
south portal of the Göggelsbuch tunnel. The locomotive accelerated from 285 km/h to 357.0 km/h from kilometre 45.2 onwards, the record being set at kilometre 36.6 at 4:03 p.m. The top speed was maintained for a few seconds before the engine driver braked the engine so that it could come to a stop in Allersberg station on time.
2617:
intermediate stops in Ingolstadt. The travel time between Munich and Frankfurt/Cologne was reduced by around half an hour (compared to the route via Stuttgart). The regular travel times in regional traffic between the two main stations were reduced from two and a half to three hours to around one and a quarter (in the
2111:
the plans were publicly displayed in the affected communities. In early 1992, the start of construction (in the Nuremberg/Feucht area) was planned for January/February 1993. After a total construction time of five to seven years, the line was to be put into operation at the end of 1998/beginning of 1999.
2388:
Federal Audit Office had been running for four years. Around DM 2 billion was spent on the new line and around DM 1 billion on the upgraded line. In mid-1996, DM 241 million had been spent on planning, acquiring land and preliminary investigations, most of which had been borne by the federal government.
4510:"Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Dr. Anton Hofreiter, Winfried Hermann, Dr. Valerie Wilms, weiterer Abgeordneter und der Fraktion BÜNDNIS 90/DIE GRÜNEN – Drucksache 17/3757 – Fulda-Runden der Deutschen Bahn AG und Finanzierungsvereinbarungen zu Bedarfsplanprojekten"
3081:
Both regional services were operated by Deutsche Bahn in December 2006 for an initial period of seven years and then put out to tender for a long-term period of ten years. The service covers 1.7 million kilometres annually. According to DB information, around 70 people are employed to handle regional
2593:
Three locations along the line were considered for a planned Nuremberg ICE plant. Only at these three locations along the high-speed line can all desired works operations be run both on the line and to Nuremberg Hauptbahnhof. This is not the case for various other locations considered on other lines.
2455:
The model of private pre-financing met with sharp criticism. The Federal Audit Office, in its comments on budget management in 1997, criticised this form of raising capital as uneconomical and complained that the financing costs were "grossly disproportionate to the investment costs". He recommended
2451:
Since the federal government's share was fixed at around €2 billion, Deutsche Bahn bore the majority of the additional costs incurred, in 2004 over €450 million. The main reasons for the cost increases include geological problems in tunnel construction, extensive plan changes (especially improvements
2383:
On 19 January 1992, the federal government decided to have the planned new and upgraded line privately pre-financed as a pilot project for the first time with loans from the railways. The Bundestag approved this project in the 1996 Budget Act. In Section 29 (2) of the act, the maximum loan amount was
2273:
The line's "gap closure" ceremony took place in Kinding station on 13 May 2005. An 11 metre-long piece of rail was cut out in the north-eastern area of the station that morning and brought into the adjacent Schellenberg tunnel by excavator. In the afternoon, in the presence of several hundred guests,
2043:
While the need for a faster connection was generally undisputed, the planned route in particular, as well its effects on the ecosystem and landscape, caused intensive discussions. The proposed new and upgraded line met with broad approval from numerous social groups, especially in the Nuremberg area,
1630:
presented the DB headquarters with an initial proposal for a new rail link between Nuremberg and Munich. At the request of the DB in 1984, the project—with an open route, open investment costs and "subject to sufficient proof of economic viability taking into account the network effects"—was included
1597:
via Nuremberg-Fischbach and Feucht to Roth, where it would have connected to the existing Nuremberg–Augsburg line. The change of direction in Nuremberg would have been abolished and the capacity that would have become free on the tracks between Roth and Nuremberg was to be used for the planned line 2
1588:
test train was at an advanced stage of development. Considerations at that time envisaged the construction of a 31.8 km-long long-distance railway replacement line for long-distance passenger and freight traffic in the Nuremberg area. In the most likely option, the route would have run from Nuremberg
1338:
to cut through as little of the landscape as possible. This "bundling" meant that nine tunnels with a total length of 27 kilometres were required–almost a third of the new route. The 7.7 km long Euerwang tunnel and the 7.3 km long Irlahüll tunnel are among the longest tunnels in Germany. In addition,
2564:
In long tunnels and along a noise barrier at kilometre 45, the maximum permissible speed for the tests was limited to 250 km/h and 285 km/h respectively. A maximum speed of 350 km/h was only permitted on the approximately nine-kilometre section between the north portal of the Offenbau tunnel and the
2447:
On 13 March 2002, Deutsche Bahn told its supervisory board that the expected total costs for the project would be around €3.6 billion. Ground problems identified in the course of the construction work would have necessitated considerable additional work and new planning approval procedures. From the
2403:
had already calculated that costs would amount to more than DM 4 billion. By exhausting all possibilities when awarding the contract, the originally estimated costs of DM 4.05 billion were reduced to DM 3.87 billion (including price increases). Of this, DM 2.75 billion went to the new line, the rest
2174:
Three separate, smaller construction lots covered the connecting areas in Nuremberg (Reichswald junction) and Ingolstadt (Audi tunnel lots and Ingolstadt node). Completion was expected in 1998 in 2003. The equipment for rail power supply, signalling technology and telecommunications was awarded as a
2101:
According to a report by Vieregg-Rössler of July 1994, the journey time would have been 74 minutes if the route via Augsburg had been upgraded and active tilting technology had been used, and 69 minutes if the new line had been built between Donauwörth and Pleinfeld (2.8% grade). Deutsche Bundesbahn
1856:
option 8 (Nuremberg – Sengenthal – Ingolstadt – Munich) would have run like option 6, but via Neumarkt to Sengenthal. South of Sengenthal, the line was to run east of the Sulz valley to the south through open ground. North of Beilngries the line would have run to the west. Further on, the line would
1569:
In the 1980s, the options for expanding the existing routes had been exhausted in many places: Intercity services reached 200 km/h on upgraded lines. The Augsburg-Oberhausen – Bäumeheim – (Donauwörth) (32.8 kilometres) and Munich-Lochhausen – Augsburg-Hochzoll (42.7 kilometres) sections had already
1457:
The new line runs largely through an area dominated by agriculture and forestry. Areas of particular ecological value are cut through in the Lorenzer Reichswald (forest) in Nuremberg, when crossing the Altmühl and Anlauter valleys, and in the Kösching forest near Ingolstadt. The gradient of the line
1377:
to Nuremberg-Fischbach (9 kilometres). The route leaves Nuremberg Central Station in an easterly direction, crossing the railway line to Eger and running parallel to the S-Bahn lines 2 and 3 past the stadium to Nuremberg-Fischbach. At Reichswald junction, the Regensburg line is routed via high-speed
2986:
Between December 2006 and June 2007, there was a 22 percent increase in passengers in long-distance traffic between Munich and Nuremberg. In 2007, the first year with a full operating program, passenger numbers between Nuremberg and Munich increased by around 30%, with around six million passengers
2802:
The Allgäu-Franken-Express regional express line was established to replace the ICE trains that were no longer used between Nuremberg and Augsburg. Until 2020, the trains ran between Nuremberg and Augsburg in a travel time similar to that of the ICE (around 70 minutes), sometimes with extensions to
2573:
made a test run at the end of the record run to check the condition of the overhead line and the superstructure of the new line. According to DB Netz and Siemens, neither the line nor the locomotive had been specially prepared from a technical point of view. Minor adjustments included reduced brake
2568:
About 1,500 people followed the journey along the line and at Kinding station. Around 4:30 p.m. the locomotive arrived where a celebration and a vehicle show were taking place; the two French record locomotives could also be viewed. In order to rule out that damage had occurred to the NBS, the test
2459:
In its 2003 annual report, the Federal Court of Auditors also criticised the fact that the federal government had granted additional grants and interest-free loans in excess of the fixed amount. There are also additional expenses, e.g. incurred due to the federal government covering funding gaps in
2391:
The private pre-financing was included in the financing agreement that was concluded on 19 December 1996 between the Ministry of Transport and Finance and Deutsche Bahn for a fixed price of DM 3870 million (€1978.7 million). All cost increases beyond the agreed financing framework were therefore to
2326:
occurred repeatedly at the portals of the Irlahüll and Euerwang tunnels. This necessitated the installation of sound absorbers in March and April 2006 and delayed preparations for the line's commissioning. In April 2006, the staff training trips began, during which the train drivers undertook route
2234:
The access route in Nuremberg was rebuilt over a length of five kilometres and the Reichswald junction was built from 1997 to 1999. Large-scale construction work in the new section began after the contract was placed at the end of 1998, and by March 1999 clearing work and archaeological preliminary
2067:
In a decision of 19 July 1988, the Bavarian government gave preference to the route via Ingolstadt. Due to imponderables in the field of nature conservation, Deutsche Bundesbahn were asked to draw up spatial planning documents for both major options. The required documents were prepared by Deutsche
1833:
option 3: Like option 2, but with a new line between Roth and Donauwörth. This NBS would have exited the Fischbach–Roth S-Bahn replacement route north of Roth and would have bypassed Roth to the west. From Georgensgmünd, this route would have run east of the existing line to Pleinfeld parallel to a
1829:
valley, it merges with the existing Nuremberg line near Büchenbach–Treuchtlingen. Large-scale rerouting of the existing line was planned north of Georgensgmünd and north and south of Pleinfeld; minor extensions were planned for the Treuchtlingen–Donauwörth line; larger route shifts would take place
1816:
option 1 (via Ingolstadt): new line between Nuremberg and Ingolstadt, 75 kilometres with a maximum speed of 250 km/h, 59 kilometres at 200 km/h, addition of an additional track to the line between Munich-Obermenzing and Petershausen, location of the new line parallel to the autobahn to the south of
2846:
In August 2011, Deutsche Bahn AG announced that it would stipulate that leading vehicles should be equipped with a train control system as a network access criterion for the new line. After the Federal Network Agency had rejected this in January 2012, DB Netz AG raised an objection against which a
2545:
class set a new world speed record for conventional electric locomotives. The 6,400 kilowatt multi-system locomotive reached the new record of 357.0 km/h on the second attempt at 4:03 p.m. near Hilpoltstein (Allersberg–Kinding section). It beat the record set by a French SNCF BB 9004 locomotive at
2238:
With the start of work on the Göggelsbuch tunnel on 18 May 1999, the excavation of the nine tunnels began, which was completed in May 2001. Numerous problems arose during the construction of the tubnnels, which required extensive design changes and had a significant impact on construction time and
2110:
The design planning began after the conclusion of the spatial planning process on 19 May 1991. On 29 May 1992, the first planning approval process was initiated on the basis of the documents created by the Main Department for New Lines of the Federal Railway Directorate in Nuremberg. In July 1992,
2093:
The procedure ended on 19 June 1991 with a state planning assessment in which the current route of the new line was identified as the most balanced solution. The authority issued conditions, particularly in the area of landscape and nature conservation, the long-distance stop in Ingolstadt and the
2842:
The line is suitable for freight trains weighing around 900 t and around 600 m-long, but is not used by freight trains (as of 2015). Freight traffic can in principle be handled on the line if there is no passenger traffic on the it at the same time. However, it is forbidden between Allersberg and
2486:
Between the start of operation on 28 May 2006 and the timetable change on 10 December 2006, a preliminary service ran. The shortest scheduled travel time between Nuremberg and Munich fell by 27 to 78 minutes. Only long-distance passenger trains ran at regular two-hour intervals, in particular the
2407:
The upgrade of the S-Bahn and the elimination of level crossings in the area of the upgraded line were not part of the financing agreement for the entire line. On 28 December 1998, a separate financing agreement for the construction of the S-Bahn followed between the state of Bavaria and Deutsche
2158:
The new line was divided into seven construction lots. The Fischbach/Feucht interconnecting lot was awarded to six companies in 1997. The three major construction lots, north, middle and south, were let to general contractors on 3 September 1998 (according to another source: 1 October 1998) for a
2147:, a multi-stage karst exploration program was carried out as part of the planning. The mountains were divided into four stages with regard to their karstification and examined by a so-called Karst working group of planners, experts and consultants from the Bavarian Geological State Office and the
2114:
In mid-1994, the planning approval process for the new line was expected to be completed by 1995, while the process for the upgraded line was expected to be completed by 1996. The planning approval decisions for the new line were issued between 7 April 1994 (Fischbach–Feucht) and 26 February 1999
2794:
While the majority of long-distance trains between Munich and Nuremberg or Würzburg previously ran via Augsburg, many ICE trains took the faster route via Ingolstadt after the route was fully operational. This shift of ICE traffic to the new line deteriorated the connections between Augsburg and
2439:
In 2008, €31.3 million were spent on the project. The total costs incurred up to that point added up to €3,299.86 million. The planned total costs were €3,592 million in 2011 and €3,676 million in 2012 (as of 2012). The federal government estimeated the pure construction costs of the new line at
2387:
In mid-1994, the planned costs (prices as of 1 January 1993) were around DM 4 billion. This figure was based on the cost estimate of over DM 3.1 billion (1 January 1989 prices), compensated for the price increase and a "balance sheet surcharge". At that time, an economic feasibility study by the
2082:
dated 29 May 1991, the new route option had become unavoidable due to the changed traffic flows and forecasts after reunification. He cited the necessary increase in capacity due to the new line and the increased importance of reducing travel times between Nuremberg and Munich as reasons. If the
1864:
Considerations for upgrading the route from Würzburg via Ansbach and Treuchtlingen to Augsburg had already been discarded in 1983 to avoid bypassing the Nuremberg metropolitan area as a transport and economic centre. The planned new line, on the other hand, was intended to improve the connection
1528:
The first route of over 232 kilometres between Nuremberg and Munich meant than the line was 82 kilometres longer than the straight-line distance of 149.6 kilometres between the two main stations. The line was determined by the costs, transport demand and political goals of the 19th century, with
2629:
With the new line between Nuremberg and Munich, two to three independent routes are available, a total of at least four tracks. This has significantly improved capacity and operational flexibility in the event of a disruption. In the area of the new line, there is also extensive segregation, an
2443:
It was foreseeable that the agreed cost framework would be exceeded from 1999 and the framework was exceeded at the end of 2003. After the project was still officially on schedule in August 2000, DB admitted cost increases of up to DM 1 billion at the end of October 2000. On 6 December 2000, DB
2379:
In 1991, the project was economically evaluated. It was assumed that there would be around 180 trains per day, half passenger and half freight trains. 144 passenger and 176 freight trains were used as a basis for the upgraded line; some of the freight trains were to be switched to the route via
2063:
Two options were examined in depth: on the one hand, a new Nuremberg–Ingolstadt line for 250 km/h with an upgrade of the Ingolstadt–Munich line, without realising the planned long-distance railway replacement line. The second variant provided for an upgrade of the existing line between Roth and
1845:
option 6: Nuremberg – Postbauer-Heng – Ingolstadt – Munich. In order to keep the section of the new line as short as possible, the existing line between Nuremberg and Postbauer-Heng was to be used and partially upgraded. The new line would start at Postbauer-Heng and run through the Sulz valley
1841:
option 5: Nuremberg–Treuchtlingen as for variant 2, then: Treuchtlingen–Ingolstadt acceleration and further retention of the existing route. Extensive conversion between Obereichstaett and Ingolstadt. Ingolstadt–Munich like variant 1. Of a total of 205 kilometers, 104 kilometers would have been
1350:(km 11.5–86.6) in 120 metre-long sections. The tracks are designed for a maximum speed of 300 km/h over a total length of 69.4 kilometres. This shortens the long-distance travel time between Nuremberg and Ingolstadt from 66 minutes to around half an hour. Two new regional stations were built at
2798:
When the timetable changed in December 2006, Augsburg lost 30 of the previous 120 daily long-distance stops. At the same time, the range of services between Munich and Berlin was increased from a two-hour to an hourly frequency, with three to four daily pairs of trains running on this line via
1635:
for the project was 1.2. The exact alignment would still be examined. The main issues discussed were an upgrade of the existing line via Treuchtlingen/Augsburg with partial line improvements and the construction of a new line between Nuremberg and Ingolstadt with an upgrade of the line between
2821:
On weekdays, regional express trains also run between Nuremberg and Augsburg (alternating hourly and with a change in Treuchtlingen) with a journey time of around 110 minutes. On Saturdays, Regional-Express trains run at two-hour intervals, on Sundays at two-hour intervals. Furthermore, since
2607:
The route length between the main stations fell from 199.1 kilometres (old route via Augsburg) or 198.3 kilometres (via Treuchtlingen/Ingolstadt) to 170.8 kilometres. The linear distance between the main stations is 149.6 kilometres, the road connection via the motorway is 167 kilometres. The
2616:
When it went into full operation on 10 December 2006, the journey time between Nuremberg and Munich in the ICE fell from around 100 (with intermediate stops in Augsburg and Pasing) to 62 minutes (without intermediate stops, although some trains take up to 71 minutes) or 66 to 74 minutes with
1837:
option 4: Nuremberg–Roth as option 2. North of Georgensgmünd and north and south of Pleinfeld line rebuilding with large-scale departures from the existing line. New line from south of Weißenburg to the east. Confluence with the existing Munich–Treuchtlingen line southwest of Obereichstaett;
2546:
331 km/h on 29 March 1955, making it the fastest locomotive in the world. The top speed of 343.9 km/h at kilometre 34.3 was reached in the first attempt at around 3:15 p.m. The locomotive was in a largely standard condition, although some parts had been dismantled to improve air resistance.
2395:
The amount of DM 3,870 million includes planning and administration costs as well as expenses of around €170 million for construction, land acquisition and planning that were incurred prior to the signing of the agreement. Federal funding for the slab track was limited to DM 1,400 per meter
2154:
A total of 746 pieces of land were purchased. The developed area was around 446 hectares, while the ecological compensation areas were 294 hectares. Seven buildings were demolished for the line (as of 1992). Around 7.5 million cubic metres of excavated material were stored at 16 landfills.
2097:
The new and upgraded Nuremberg–Ingolstadt–Munich route was listed as a priority in the 1992 Federal Transport Plan, with a planned total investment of DM 3,000 million (€1,534 million at 1 January 1991 prices). The traffic forecast for the Federal Transport Routes Plan 1992 provided for 44
4625:"Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Dr. Anton Hofreiter, Bettina Herlitzius, Winfried Hermann, weiterer Abgeordneter und der Fraktion BÜNDNIS 90/DIE GRÜNEN: Umsetzung von Projekten des Neubaus, Ausbaus und der Erhaltung der Bundesschienenwege in Bayern"
2463:
In 2008, the Federal Court of Auditors criticised the fact that the Federal Ministry of Transport, Building and Urban Development had already paid out the entire subsidy amount to Deutsche Bahn AG, although services worth around €60 million were still outstanding on the upgraded line.
1406:
running west and Autobahn 9 running east. The line runs over the Schwarzach Viaduct over the Schwarzach and shortly afterwards through a trough structure under the Nuremberg/Feucht motorway triangle. While the A 73 ends here, the A 9 runs parallel to the line for around 35 kilometres.
2250:
The slab track was installed between April 2004 and April 2005; installation of rail track was completed in May and overhead line and signalling technology in November 2005. The first low-speed test and measurement runs were carried out between the end of May and October. The RAILab
2235:
investigations were largely completed. When the large-scale construction work started, it was assumed that the construction work would end in February 2003. At the beginning of 2001, it was clear that the planned completion date of the end of 2003 would be delayed by a year or two.
3666:
Bavarian Administrative Court, judgment of 10 January 1997, case numbers 20 A 96.40052, 20 A 96.40068, 20 A 96.40073 and decision on case numbers 20 AS 96.40069, 20 AS 96.40074; joint version as PDF (56 pages) from the library of the Bavarian Administrative Court, Ansbach; p. 4.
2982:
When the timetable changed in December 2006, the previous overlapping two-hour intervals on ICE lines 28 and 41 were increased to more or less hourly on both lines (with some missing services). As a result there is now a largely half-hourly service between Nuremberg and Munich.
1429:
In the subsequent Irlahüll tunnel (7,260 m), the line passes under the autobahn and then climbs by around 115 metres. In the subsequent Denkendorf tunnel, the gradient drops slightly for a short time before the line reaches its high point at kilometre 71 at around 500 metres
2331:
sets and carried out towing exercises. On 6 May 2006, a rescue exercise took place in the Euerwang Tunnel. The evacuation of an ICE with about 250 passengers was rehearsed through two emergency exits. A trial operation with several vehicles was carried out from 2 to 27 May.
2830:
The line has been used since 28 May 2006 by long-distance trains and since 10 December 2006 by regional trains of the Munich-Nuremberg Express. From 2006 to 2020, the Allersberg Express also ran on the section between Nuremberg and Allersberg, which was then replaced by
2577:
The record runs had been preceded by numerous "high-speed runs" since 21 August, in which the locomotive was gradually accelerated to 330 km/h. DB Netz issued a special permit for high-speed travel and the government of Middle Franconia issued an approval notice.
1401:
and crosses the line to Regensburg. While the lines towards Regensburg and Altdorf (S-Bahn) approach Feucht station on a left-hand curve, the high-speed line takes a slight right-hand curve through the municipality in a southerly direction. At km 13 it meets
2979:– Berlin (timetable route F20) used the route on Saturdays. These have been operating as ICE trains since the timetable change in December 2007. Some long-distance trains continue to run via Augsburg, leaving gaps in the pattern of services every 30 minutes.
2987:
using the new line in 2007. Before the line went into operation, DB expected growth rates of 30 to 40 percent within three years. According to Deutsche Bahn, the number of passengers increased by 60 percent as a result of the new and upgraded line by 2010.
1820:
option 2 (via Augsburg): from Nuremberg via Fischbach on existing tracks; from there with the so-called S-Bahn replacement route to Kornburg bundled with the Autobahn 6, then a bend to the south and a bundled course with the Rhein-Main-Danube Canal and the
1458:
increases from Nuremberg (330 m above sea level) to Ingolstadt (370 m above sea level), with a low point in the Altmühl valley (375 m above sea level, km 59) and high points at around km 35.5 (450 m above sea level) and 71 (500 m above sea level).
3187:
1540:
The Munich–Ingolstadt railway was opened in 1867 and extended to Treuchtlingen in 1870. Between 1870 and 1906 long-distance trains between Munich and Nuremberg used this line, with a total length of 198 kilometres. With the commissioning of the
2427:
In January 2006, DB Netz put the total cost of the high-speed line at €3.573 billion. Of this, €2.049 billion are attributable to the federal government (BSchwAG), €1.154 billion to Deutsche Bahn's own funds, €190 million to the European Union
2277:
On 25 November 2005 at 10 a.m., the overhead line was energised for the first time. The electronic interlockings in Nuremberg-Fischbach went into operation on 28 November. At the end of November, the first continuous journeys were made with an
2059:
After inclusion in the Federal Transport Plan, eight options were examined, between the upgrade of the Nuremberg–Donauwörth–Augsburg–Munich line in the west and the new and upgraded Nuremberg–Sengenthal–Ingolstadt–Munich line in the east.
4566:
1434:. In this section, the autobahn lies to the west of the railway line and is crossed again in the subsequent Stammham Tunnel. The line detaches itself from the autobahn and dives a little later into Geisberg tunnel. Within sight of the
5038:
1610:
The first federal transport route plan from 1973 provided for an upgraded route between Würzburg and Augsburg via Nuremberg as one of eight development projects. This project was included in the 1977 Coordinated Investment Program
2290:
class locomotives. High-speed test runs began on 1 December 2005. From 6 to 12 December 2005, the LZB carried out acceptance runs. Top speeds of over 330 km/h were reached during the test and acceptance runs. In addition to the
2630:
operationally desirable separation between (fast) passenger and (slow) freight traffic. Furthermore, for long-distance trains running between Würzburg via Nuremberg to Munich, there is no need to change direction in Nuremberg.
2510:
Since June 2005, a year before the new line was commissioned, several pairs of ICE 3 trains have been running on the old line via Treuchtlingen/Ingolstadt between Munich and Nuremberg, with a journey time of around two hours.
1287:
The line was officially inaugurated on 13 May 2006. Limited operation with a twice-hourly long-distance service started on 28 May 2006. The line has been in full operation since December 2006. Compared to the former track via
1838:
extensive tunnelling of the new line. Upgrade of the line between Obereichstaett and Ingolstadt. Ingolstadt-Munich like option 1. Of the total of around 191 kilometres, 126 kilometres should be designed for at least 200 km/h.
2191:("German Unity Railway Construction Planning Company") was commissioned with the project management of the new and upgraded line in 1996, effective January 1997, and set up a project centre in Nuremberg for this purpose.
2359:
to green. Two ICE 3 trains, each in double sets, then ran (from 11:34 a.m.) to Nuremberg, parallel for part of the line. After the arrival of the trains on Nuremberg, an opening ceremony for invited guests took place.
1602:. A significant reduction in travel time was not expected, despite the fact that north-south long-distance trains would not have had to change direction at Nuremberg station over the approximately six km longer route.
4987:
2574:
cylinder pressure (to avoid overheating on emergency stops), an increase in engine output from 6,400 kilowatts to (briefly) 7,300 kilowatts, changes to the vehicle software and the installation of numerous sensors.
3705:
Bavarian Administrative Court, judgment and decision of 29 March 1996, file nos. 20 A 94.40029, 20 A 94.0135, 20 AS 94.40136 and 20 AS 95.40100. PDF (18 pages) of the library of the Bavarian Administrative Court,
2136:
and an increase in the top speed from 250 km/h to 300 km/h were adopted. Allersberg and Kinding stations were also upgraded from overtaking loops to regional stations and regional transport services were adopted.
5095:
1441:
The high-speed section ends at kilometre 83.7, immediately before a curve that runs into the Audi tunnel via a ramp. The new section ends with the end of its southern ramp, which also includes the platforms of
3726:"Antwort der Bundesregierung auf eine kleine Anfrage (…): Einsparungsmöglichkeiten durch neuartige Trassierung von Schienenwegen für den Hochgeschwindigkeitsverkehr unter Berücksichtigung der Neigezugtechnik"
1339:
82 rail and road bridges were built, including five major steel bridges, and about 80 culverts (with a diameter less than 2 m). At 305 metres, the longest road bridge on the new line spans the new line, the
3191:
2514:
In July 2006, the TGV POS was used on the new line to complete trials runs at up to 330 km/h for approval in Germany. The line was fully commissioned when the timetable changed on 10 December 2006.
1545:, the line between Nuremberg and Augsburg was reduced to 137 kilometres in 1906, and between Nuremberg and Munich to 199 km. After this shortening, Augsburg was again served by north-south traffic.
3855:"Antwort der Bundesregierung auf eine kleine Anfrage des Abgeordneten Dr. Klaus-Dieter Feige und der Gruppe BÜNDNIS 90/DIE GRÜNEN: Wirtschaftlichkeit der "ICE-Neubaustrecken" – Drucksache 12/8381"
1849:
option 7: Nuremberg – Neumarkt – Ingolstadt – Munich. As with option 6, the Nuremberg–Regensburg line would have been used as far as Neumarkt. The new line should initially run along the existing
4719:"Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Sabine Leidig, Eva Bulling-Schröter, Herbert Behrens, weiterer Abgeordneter und der Fraktion DIE LINKE. – Drucksache 17/3021
4570:
4346:
1857:
have run like option 7 and would finally run parallel with the autobahn as in option 1. Of 180 kilometres, 51 kilometres would have been designed for 250 km/h and 59 kilometres for 200 km/h.
4750:"Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Winfried Hermann, Dr. Anton Hofreiter, Bettina Herlitzius, weiterer Abgeordneter und der Fraktion BÜNDNIS 90/DIE GRÜNEN"
3085:
Around 5,000 travelers use the Munich-Nuremberg Express every day. Approximately 700 passengers use the seven newly established bus routes in Allersberg and the two in Kinding on weekdays.
3043:
sets. Until December 2022, it was the only regional express in Germany operating at more than 180 km/h and the first to travel the full length of a new German high-speed line. Since then,
914:
2219:
On 15 July 1994, the ground-breaking ceremony for the extension of the railway bridge over Breslauer Straße took place in the Altenfurt district of Nuremberg. Bavarian Minister-president
3585:"Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Dr. Anton Hofreiter, Winfried Hermann, Peter Hettlich, weiterer Abgeordneter und der Fraktion BÜNDNIS 90/DIE GRÜNEN
2608:
distance between the main stations of Würzburg and Munich went from 277.6 kilometres (old line via Ansbach, Treuchtlingen, Augsburg) to 273.0 kilometres (via Nuremberg and Ingolstadt).
2175:
separate lot for DM 120 million in January 1999 (according to another source: December 1998). During the construction phase there were 157 plan change procedures (as of October 2005).
5276:
439:
2440:
around €2.27 billion or €13.8 million per track kilometre (prices as of: 2010). In the 1996 financing agreement, costs of €8 million per kilometre of new track were calculated.
2265:
The preparation and execution of the commissioning were controlled by the PXN working group set up by the DB board of directors in August 2000 and headed by DB Personenverkehr.
1830:
at Otting and Mündling. For capacity reasons, a new section was to be built between Augsburg and Mering. Of a total of 207 kilometres, 140 kilometres were designed for 200 km/h.
4991:
4961:
1298:
The high-speed connection was controversial in particular because of its high cost, its ecological effects, but also for its route. Routes via Augsburg were also considered.
2255:
was used, among other things, to check the track position, examine rails for material defects using ultrasound and measure the tunnel walls. On 13 September 2005, an ICE (
5345:
2467:
In its Black Book 2005, the taxpayers' association criticised the cost increases and emphasised that every minute of travel time reduction was bought for €65.2 million.
5189:
5748:
5099:
2367:
on 28 May 2006, prior to the start of preliminary operations. Until the formal commissioning of the line in December 2006, approval was granted in accordance with the
783:
5498:
647:
5377:"Ab 10. Dezember rollt zwischen München und Nürnberg der schnellste Regionalverkehr Deutschlands" (Press release) (in German). Deutsche Bahn AG. 6 December 2006.
3045:
1537:
the need for a direct connection between the two largest Bavarian cities as the "first and next need" and "the natural beginning of the entire railway system".
1450:, which has been widened to include a third track between the two Ingolstadt stations. After crossing the Danube on Ingolstadt railway bridge, the line reaches
557:
6572:
5754:
1465:
The line still under construction near the Hilpoltstein car park. The gradient, which reaches a maximum of 20 per thousand on the new line, is clearly visible.
5255:
2822:
December 2006 there has been a two-hour service every weekday with a change in Ingolstadt (Munich-Nuremberg Express) with a travel time of around two hours.
868:
5137:
6567:
2408:
Bahn. Bavaria also assumed half of the total costs in the section between Dachau and Obermenzing in accordance with the Municipal Transport Financing Act (
469:
1002:
1581:
lines, around 430 km of railways designed for operations at up to 250 km/h were under construction or in planning at the beginning of the 1980s, and the
1030:
5403:
5013:
5638:
2590:
car attached to it, setting a new record for the line. Further trial runs with a top speed of up to 400 km/h were to take place in the course of 2021.
5798:
1086:
1058:
810:
616:
5317:
4353:
2503:(Munich–Berlin–Hamburg) and the ICE 926/927 trains on line 31 also operated at off-peak times, during peak hour and on weekends. The IC train pair
1418:, while the line enters the 7.7 kilometre-long Euerwang tunnel towards the south-west. In a short interlude, the line runs aboveground through the
2795:
Nuremberg or Würzburg and between northern Bavaria and Bavarian Swabia, Upper Swabia and the Lake Constance area and led to longer travel times.
5476:
1414:
and Offenbau tunnel. At kilometre 46/47 the railway stops running parallel with the autobahn, which moves away in an easterly direction towards
1295:
Project costs were estimated to amount to €3.7 billion (as of 2012). In 1998, before construction began, it was forecast to cost €2.3 billion.
5491:
3470:
2368:
5284:
1498:
6552:
6407:
6167:
4008:
Strappler, Günter; Könnings, Heinz-Dieter (1999). "Neubaustrecke Nürnberg – Ingolstadt Knackpunkte in der Abwicklung der Tunnelprojekte".
2953:
2926:
2895:
2500:
2492:
6402:
6197:
6004:
5530:
3088:
Since 2020, a line S5 of the Nuremberg S-Bahn has run between Nuremberg and Allersberg as the successor to the Allersberg-Express. Four
6438:
6192:
6009:
6202:
1574:
6413:
6352:
6207:
2412:, GVFG), also at a fixed cost. The other half was financed from federal funds in accordance with the Federal Railways Expansion Act (
1578:
1497:
The first continuous rail connection between Nuremberg and Munich was completed in 1849. The Nuremberg–Augsburg section ran over the
6423:
5355:
5808:
5484:
4965:
4830:
Grübmeier, Jürgen; Heinisch, Roland (1985). "Planungen für das Schienennetz der Zukunft". In Gohlke, Reiner; Reimers, Knut (eds.).
2056:("The Better Railway Concept"). They favoured an upgrade of the existing route via Augsburg, later also using tilting technology.
6428:
6397:
6270:
6218:
5921:
5803:
5772:
5743:
5738:
5585:
5535:
3753:
Judgment of the Bavarian Administrative Court of 10 January 1997 and e-mail information from Dr. Martin Vieregg on 19 March 2007.
1378:
points to a parallel track from the Nuremberg marshalling yard. The straight-ahead tracks connect to the new line to Ingolstadt.
1273:
6418:
5982:
2850:
According to Deutsche Bahn, the number of passengers on the route increased by 60 percent in the first four years of operation.
1877:
Controversial interventions in the landscape and ecosystem – new line under construction with A 9 in the Köschinger Forst (2001)
1562:
1542:
6433:
6223:
5972:
5631:
5605:
4324:
Feldwisch, Wolfgang; Schülke, Holger (2006). "Die Inbetriebnahme der Großprojekte der Bahn zur Fußballweltmeisterschaft 2006".
1385:
Route near the Reichswald junction. The two tracks in the middle lead to Ingolstadt, the tracks to the right and left of it to
974:
4246:
Schülke, Holger; Weishaar, Herbert; Grein, Ottmar (2001). "Projekt PXN zur Inbetriebnahme der Neubaustrecke Köln–Rhein/Main".
2339:(Clear the line! Nuremberg–Ingolstadt–Munich—Bavaria's fastest rail axis"). In the late morning, Bavaria's Economics Minister
6462:
6290:
6233:
6228:
6186:
5600:
3133:
3052:
1484:
The distance between centres of the line and the parallel autobahn between kilometres 13 and 48 is between 40 and 60 metres.
4923:
6562:
6280:
6275:
5590:
2148:
3078:
locomotives were used, as was the case with the Munich-Nuremberg Express, which could travel at speeds of up to 200 km/h.
6285:
5977:
5793:
5668:
1522:
3538:
Woelker, Christian (1980). "Bundesverkehrswegeplan '80: Die Schiene holt auf". In Vaerst, Wolfgang; Koch, Peter (eds.).
2159:
total of €710 million (DM 1.4 billion) at a fixed price. The north construction lot went to a bidding consortium of the
1410:
The end of the Nuremberg Reichswald (forest) is followed by Allersberg station, Göggelsbuch tunnel, the bridge over the
1292:, it cut off 29 km (18 mi), or about 30 minutes journey time on long-distance and an hour on regional trains.
6392:
6310:
6300:
6295:
5595:
3408:
Weigelt, Horst; Nußberger, Peter (July–August 1994). "Neubaustrecke Nürnberg–Ingolstadt vom Konzept zum Spatenstich".
2594:
Most recently, a location in the former army ammunition facility in Feucht was considered and rejected in April 2023.
6582:
6557:
5624:
5442:
5233:
3547:
1281:
2470:
An estimate from 1985 assumed costs of DM 1.9 billion for a new line for 250 km/h between Nuremberg and Ingolstadt.
5678:
5647:
5163:
3919:
3269:(in German). Nürnberg: Planungsgesellschaft Bahnbau Deutsche Einheit mbH. 30 November 1999. pp. 3–5, 7, 8, 11.
2429:
1447:
1311:
1262:
1254:
1195:
1146:
394:
281:
185:
2808:
2558:
2231:
symbolically pressed a button. Planning and financing of the entire line had not yet been completed at this time.
1861:
Options 3 to 8 were discarded in 1987. Options 1 and 2 were ultimately selected for more in-depth investigations.
5777:
5514:
5506:
4101:
Duhme, Martin (2006). "Inbetriebnahme der Neubaustrecke Nürnberg–Ingolstadt zur Fußball-Weltmeisterschaft 2006".
3963:
Höwing, Klaus-Dieter; Eder, Stefan; Plank, Marcus (2003). "Baugrunderkundung für Verkehrswege in Karstgebieten".
2090:. The long-distance railway replacement route would only have to be built if the upgrade option was implemented.
1277:
588:
1355:
940:
5903:
5550:
5322:
5306:"Voller Erfolg: Bayern steigt um auf die Bahn" (Press release) (in German). Deutsche Bahn AG. 28 December 2007.
4067:
1481:. The cross-section of the running tunnel is 92 square metres, the distance between the tracks is 4.50 metres.
2909:
2432:) and a total of €180 million to the state of Bavaria and municipalities (in accordance with the GVFG and the
6122:
5788:
5080:
4900:
4802:
4785:
4375:
4306:
4289:
4200:
4042:
3639:
3026:
3014:
2996:
2878:
2618:
1850:
6074:
5824:
5782:
5767:
5560:
5545:
2074:
fundamentally changed the planning parameters. According to a letter from Deutsche Bundesbahn Board Member
2048:
was clearly rejected, in particular by the city of Augsburg and its chamber of commerce, as well as by the
1623:
1390:
1374:
1351:
526:
230:
170:
5467:
3058:
In addition, a regional train shuttle service operated between Nuremberg and Allersberg until 2020 as the
2818:
Since 2013, long-distance trains have been running from Augsburg to Berlin and Hamburg almost every hour.
5911:
5893:
5762:
4391:
1518:
256:
6178:
6084:
6066:
6032:
5580:
5350:
3105:
3089:
3032:) runs every two hours between Nuremberg and Munich. These trains are (since December 2020) made up of
2179:
6448:
6346:
6328:
6251:
6243:
6162:
6109:
6023:
2972:
2364:
2318:
ICE S during a measurement run in front of the Audi tunnel at the start of the new line in Ingolstadt
1632:
5964:
4851:
4447:
6384:
6262:
5987:
5916:
5724:
5555:
5525:
3309:
Weigelt, Horst (2003). "Ursprung, Funktion und Nutzen der Neubau-/Ausbaustrecke Nürnberg–München".
2526:
Locomotive 1216 050 and the measuring car on a world record run at 357 km/h at the truck stop near
1881:
1534:
2968:
5862:
5715:
5019:(Raumordnungsverfahren Nürnberg Neubau ICE-Werk Nürnberg) (in German). DB Netz. 24 September 2021
2129:
1451:
1443:
1266:
1172:
180:
5867:
3037:
3010:
6132:
5954:
3158:. Drucksache, 18/580 (in German). Köln: Deutscher Bundestag. 18 February 2014. pp. 91–94.
3093:
2874:
2586:
In March 2021, a speed of 360 km/h was reached during a measurement run with the ICE S and the
2554:
2207:
Controversial crossing of the Altmühl valley: construction site of the Kinding station in 2001.
1582:
4464:
3020:. The new line has also been used for local rail passenger transport since December 2006. The
1873:
6137:
2913:
2890:
2182:
system was used by all those involved, which used electronic signatures, among other things.
1411:
5458:
3944:
Wegerer, Peter (2003). "Bewältigung der Karstproblematik bei der NBS Nürnberg–Ingolstadt".
2944:
2917:
2812:
2071:
1340:
5872:
5852:
2882:
2344:
8:
6577:
5847:
5842:
5570:
5236:(in German). North Rhine-Westphalia Higher Administrative Court. 6 June 2012. 13 B 291/12
5039:"Standortsuche abgeschlossen: Keine geeignete Fläche für neues ICE-Werk im Raum Nürnberg"
4942:
4749:
4718:
4682:
4653:
4624:
4543:
4509:
4416:
4156:
4133:
3987:
3854:
3831:
3725:
3584:
3152:
3040:
2948:
2921:
2870:
2356:
2262:
Up to 1800 people were simultaneously employed on the construction sites along the line.
1627:
5435:
Schnellbahnachse Nürnberg–Ingolstadt–München – Neue Infrastruktur mit Spitzentechnologie
3352:
Fiedler, Gerhard (2000). "NBS Nürnberg–Ingolstadt – Systematik der Ausführungsplanung".
2423:
Additional costs of €11.5 million: additional agreed protection along roads on the line.
2086:
In 1990, the decision was made to build a single or double-track line for line 3 of the
1636:
Ingolstadt and Munich. In 1986 and 1987, a comparison of options was carried out by DB.
1438:
factory in Ingolstadt, the line briefly runs parallel to the Etting bypass to the west.
6495:
5877:
4839:
4132:(in German) (2). Planungsgesellschaft Bahnbau Deutsche Einheit mbH: 8. 31 August 1997.
3521:
Block, Rüdiger (1991). "Auf neuen Wegen. Die Neubaustrecken der Deutschen Bundesbahn".
3059:
2976:
2886:
2804:
2348:
2252:
1242:
6152:
3804:
Könnigs, Heinz-Dietrich (1999). "Ab 2003: In einer Stunde von Nürnberg nach München".
3763:
2587:
5857:
5438:
4934:
4905:
4400:] (in German). Federal Ministry of Justice and Consumer Protection. p. 1800.
4155:(in German) (2). Planungsgesellschaft Bahnbau Deutsche Einheit mbH: 9. 15 July 1996.
4110:
4047:
4017:
3644:
3543:
3159:
3129:
2133:
1585:
1403:
1347:
1323:
1276:
No. 8 from Berlin via Halle/Leipzig and Erfurt to Nuremberg. The line is part of the
500:
6147:
3986:(in German) (2). Planungsgesellschaft Bahnbau Deutsche Einheit: 15. 31 August 1997.
3676:
Judgment and decision of the Bavarian Administrative Court of 10 January 1997, p 33.
2185:
In July 2003, the contract for the line's safety technology was awarded to Siemens.
1822:
1590:
5732:
5565:
4721:
Schienengüterverkehr auf den Neubaustrecken Nürnberg–Ingolstadt und Wendlingen–Ulm"
3523:
3071:
2836:
2542:
2087:
2045:
1599:
1594:
1470:
1335:
1327:
1318:
1258:
363:
3272:
3214:
ICE-Neu und Ausbaustrecke Nürnberg - München – Stand der Baumaßnahmen im Juni 2005
2295:, which at times was running with one or seven intermediate cars, the locomotives
1362:, long-distance trains can run through the stations without reducing their speed.
6373:
6336:
6098:
5926:
5658:
5575:
4417:"Bemerkungen des Bundesrechnungshofes 1997 zur Haushalts- und Wirtschaftsführung"
4352:(in German). Deutsche Bahn AG, DB Systemtechnik. 2007. p. 15. Archived from
2352:
2144:
2079:
1474:
1431:
1398:
1365:
3033:
1426:
valley with Kinding station. The autobahn runs further east in this short area.
737:
677:
6117:
4946:
4547:
4160:
4137:
3991:
3835:
3000:
2832:
2478:
2220:
1812:
In a report published in 1987, the Deutsche Bundesbahn examined eight options:
1359:
162:
106:
4542:(in German) (1). Planungsgesellschaft Bahnbau Deutsche Einheit mbH: 15. 1997.
4265:"Letzte Lücke der Neubaustrecke Nürnberg–Ingolstadt bei Kinding geschlossen".
2052:("Federation of Nature Conservation of Bavaria") and the citizens' initiative
1306:
6546:
4938:
4909:
4883:
Schurig, Jörg (2007). "Europalok ES64U4 fährt Weltrekord mit 357 km/h".
4114:
4051:
4021:
3648:
3190:(in German). Bundesrechnungshof. 21 November 2007. p. 27. Archived from
3163:
2224:
2192:
1558:
1469:
In the new section, the track was built with a gradient of up to 2.0% with a
201:
2228:
2075:
1510:
1506:
6470:
6454:
6092:
5934:
5616:
4654:"Unterrichtung durch die Bundesregierung: Verkehrsinvestitionsbericht 2009"
3075:
3063:
2527:
2416:, BSchwAG). Bavaria provided DM 211 million (€108 million) for the S-Bahn.
2300:
2296:
2283:
2223:, State Secretary in the Federal Ministry of Transport Wilhelm Knittel and
2211:
1502:
1322:
Coming from Nuremberg (above left), the new line swings to run between the
4462:
Pfeiffer, Astrid (4 July 1996). "Neuer ICE-Trasse wird der Weg bereitet".
2314:
6157:
3768:
3070:, with a maximum speed of 140 km/h. Before they were integrated into the
3005:
2340:
2323:
1114:
134:
28:
3236:"Neubaustrecke Nürnberg–München: Bundesbahn für Strecke über Nürnberg".
2448:
point of view of the time, the project was burdened with further risks.
2242:
2164:
1553:
5834:
3686:"Bundesbahn beantragt Raumordnung für Neubaustrecke Nürnberg–München".
3067:
2866:
The line is used by the following long distance services (as of 2023):
2633:
2287:
2203:
1478:
1386:
1250:
707:
4990:(Press release) (in German). Deutsche Bahn. 2021-04-29. Archived from
1817:
Stammham, where it merges with the existing Munich–Treuchtlingen line.
1423:
3662:
3660:
3658:
3542:(in German). Vol. 31. Darmstadt: Hestra-Verlag. pp. 30–36.
2337:
Bahn frei! Nürnberg–Ingolstadt–München – Bayerns schnellste Bahnachse
2160:
1381:
1246:
5143:(Deutsche Bahn policy 402.0202) (in German). DB Netz. pp. 14–16
4834:(in German). Vol. 36. Darmstadt: Hestra-Verlag. pp. 30–39.
3701:
3699:
3697:
2858:
2718:(weekday, long-distance connections without transfers per direction)
2644:(weekday, long-distance connections without transfers per direction)
2246:
One of the first measurement runs to check the rails with ultrasound
6318:
6142:
5701:
4696:(in German) (17/8700). Deutscher Bundestag: 93–96. 20 February 2012
4569:(in German). Bundesrechnungshof. p. 23, 142 ff. Archived from
4567:"Bemerkungen 2003 zur Haushalts- und Wirtschaftsführung des Bundes"
3883:"ICE-Neu und Ausbaustrecke Nürnberg - München – Daten und Fakten".
3188:"Bemerkungen 2007 zur Haushalts- und Wirtschaftsführung des Bundes"
3062:. The regional trains were originally operated with locomotives of
2971:
ran on the route from Cologne to Munich every working day, and the
2862:
An ICE 1 leaves the Schellenberg tunnel just before Kinding station
2215:
Construction site of the new line in Los Süd near Ingolstadt (2004)
2168:
1514:
1419:
1289:
841:
3655:
2533:
1889:
6127:
5271:
5269:
4426:(in German) (13/8550). Deutscher Bundestag: 165 f. 8 October 1997
3694:
3051:
trains have been running in Baden-Württemberg at 200 km/h on the
2400:
1826:
1415:
1389:. The two tracks on the left edge of the picture are used by the
1330:(right) near Feucht. This was taken during the earthworks (2001).
76:
72:
54:
6535:* An asterisk indicates overlap with conventional services.
2363:
National approval for operations on the line was granted by the
2347:, Minister-president Edmund Stoiber, Federal Transport Minister
1631:
in the 1985 Federal Transport Infrastructure Plan. The economic
6367:
5509:
4519:(in German) (17/4005). Deutscher Bundestag: 3. 30 November 2010
2419:
2279:
2256:
1561:
locomotive runs through a tight curve in a deep cutting on the
1461:
5392:(in German) (Regionalteil Süd ed.): 23. July–August 2007.
5266:
4730:(in German) (17/3311). Deutscher Bundestag: 2. 14 October 2010
4663:(in German) (17/444). Deutscher Bundestag: 29. 14 January 2010
3527:(in German) (21: Special: Hochgeschwindigkeitsverkehr): 30–35.
1373:
Trains from Nuremberg to the new line run on the upgraded old
6056:
6050:
6045:
6040:
5096:"Fernverkehr: Augsburg bald stärker mit dem Norden verbunden"
4287:"Hochtastfahrten auf der Neubaustrecke Nürnberg–Ingolstadt".
4082:"SEIB: Einsatz von EPLASS beim Projekt Nürnberg–Ingolstadt".
3864:(in German) (12/8476). Deutscher Bundestag. 12 September 1994
3637:
Andersen, Sven (2006). "Der Fall NBS Nürnberg – Ingolstadt".
3321:
2960:
2937:
2933:
2902:
2570:
2496:
2488:
2328:
2292:
2141:
1885:
Large-scale construction work in the Köschinger forest (2001)
5121:
Jänsch, Eberhard (2015). "Mischverkehr auf Neubaustrecken".
4988:"ICE-Werk Nürnberg: Standortsuche geht in die nächste Phase"
4634:(in German) (16/11730). Deutscher Bundestag. 27 January 2009
4304:"LZB-Abnahmefahrten auf der Strecke Ingolstadt – Nürnberg".
3587:
Kostenüberschreitungen bei Bauprojekten der Deutsche Bahn AG
3453:
3451:
3449:
3447:
3445:
3443:
1865:
between the greater Nuremberg area and north-south traffic.
4492:
4490:
4488:
4486:
4484:
4482:
4480:
4478:
4476:
4341:
4339:
3902:
3900:
3898:
3896:
3894:
3622:"Alle ICE-Trassen-Pläne Nürnberg–München auf einen Blick".
3441:
3439:
3437:
3435:
3433:
3431:
3429:
3427:
3425:
3423:
3128:. Schweers + Wall. 2009. pp. 89, 97, 107, 162, 164–7.
2126:
1531:
Generaldirektor der Königlich Bayerischen Verkehrsanstalten
1492:
1435:
3735:(in German) (13/2130). Deutscher Bundestag. 10 August 1995
3504:
3502:
3096:
automatic train control system, now operate this service.
2335:
The official opening took place on 13 May under the motto
5277:"Deutsche Bahn: Bayerische Rennstrecke ein toller Erfolg"
5041:(Press release) (in German). Deutsche Bahn. 13 April 2023
4607:
4605:
3289:
3287:
3285:
3283:
3281:
2522:
2178:
To speed up and simplify the planning process, a uniform
1334:
The 77.4 km-long new line was largely routed parallel to
4592:
4590:
4588:
4473:
4336:
3891:
3876:
3598:(in German) (16/4783). Deutscher Bundestag. 2 March 2007
3420:
2044:
but also in other parts of Bavaria. The new line in the
1446:
on the high-speed line. Here, the tracks merge into the
4759:(in German) (17/955). Deutscher Bundestag. 3 March 2010
3499:
3153:"Verkehrsinvestitionsbericht für das Berichtsjahr 2012"
2517:
4962:"Mit 360 km/h unterwegs: Neuer Schnellzug von Siemens"
4602:
4445:
Milian, Peter (19 October 1995). "Bahn als Maulwurf".
4227:
3922:(in German). Federal Constitutional Court. 8 June 1998
3364:
3333:
3278:
3182:
3180:
2105:
1893:
New ecological compensation area at Allersberg station
1806:
Options 2, 3 with stops in Augsburg and Munich-Pasing
4685:
Verkehrsinvestitionsbericht für das Berichtsjahr 2010
4585:
3679:
2259:) ran over the line at low speed for the first time.
2167:(Neumarkt) companies, the middle construction lot to
1422:
valley, the Schellenberg tunnel (650 metres) and the
1358:. While stopping trains approach platform tracks via
4561:
4559:
4557:
4411:
4409:
4407:
4245:
3579:
3577:
3575:
3573:
3231:
3229:
3227:
3225:
3223:
3206:
2847:
complaint lodged by the authority was unsuccessful.
2634:
Traffic shift between Augsburg and Ingolstadt routes
2507:(IC 2410/2411) also ran over the line on Saturdays.
4174:"Hochgeschwindigkeitsstrecke Nürnberg–Ingolstadt".
3177:
3092:railcars (class 1440), specially equipped with the
2140:In view of the expected geological problems in the
5381:
4617:
4373:"Mit 300 km/h von Ingolstadt nach Nürnberg".
4040:"Bauaufträge für Nürnberg – Ingolstadt vergeben".
3756:
4829:
4554:
4404:
4007:
4003:
4001:
3821:
3819:
3570:
3471:"Der Zug der Zukunft lässt Schwaben links liegen"
3261:
3259:
3257:
3255:
3253:
3251:
3249:
3247:
3220:
3126:Eisenbahnatlas Deutschland (German railway atlas)
2549:The locomotive had attached a measuring car from
2541:On 2 September 2006, a Siemens locomotive of the
1615:) as well as in the 1980 Federal Transport Plan (
1589:Hauptbahnhof in a south-easterly direction along
1499:central section of the Ludwig South-North Railway
6544:
5214:"ERTMS: Korridor A kommt vor dem Starterpaket".
4455:
4323:
4258:
3617:
3615:
3613:
3407:
3403:
3401:
3399:
225:
5433:Weigelt, Horst (2006). Honerkamp, Bernd (ed.).
5338:
5164:"Seit fünf Jahren: Mit Tempo 300 nach Nürnberg"
4916:
4778:
4776:
4774:
4531:
4368:
4366:
4035:
4033:
4031:
3975:
3962:
3397:
3395:
3393:
3391:
3389:
3387:
3385:
3383:
3381:
3379:
1903:(Deutsche Bundesbahn estimates of 29 June 1987)
5396:
5310:
5226:
5059:2006/2007 winter time table of 17 January 2007
4823:
4319:
4317:
4193:
4191:
4189:
4144:
4121:
3998:
3816:
3304:
3302:
3244:
6573:Buildings and structures in Dachau (district)
5632:
5571:Innsbruck–Franzensfeste (Brenner Base Tunnel)
5492:
5248:
5207:
5155:
5114:
5031:
4980:
4953:
4713:
4711:
4438:
4282:
4280:
3939:
3937:
3885:Informationsblatt der DB ProjektBau, Nürnberg
3849:
3847:
3845:
3799:
3797:
3795:
3793:
3791:
3789:
3787:
3610:
3566:(in German). Schienennetz der DB. p. 20.
3486:
3484:
3463:
3118:
2369:Technical Specifications for Interoperability
2274:it was ceremoniously welded back into place.
2189:Planungsgesellschaft Bahnbau Deutsche Einheit
1346:The continuously welded track was built on a
5646:
5354:(in German). 4 December 2010. Archived from
5071:
4898:"Geschwindigkeits-Weltrekord der ES 64 U4".
4891:
4793:
4771:
4363:
4239:
4208:
4075:
4028:
3630:
3531:
3376:
2399:When the financing agreement was concluded,
2322:During the first test runs at high speed, a
1369:"Bundling" of high-speed railway and the A 9
6568:Buildings and structures in Roth (district)
5318:"In einer Stunde von München nach Nürnberg"
5256:"Weniger ICE – aber Strecke wird schneller"
5129:
5062:
4502:
4314:
4297:
4186:
4167:
4151:"PBDE übernimmt Projekt München–Nürnberg".
3299:
3147:
3145:
2355:symbolically switched the exit signal from
5639:
5625:
5499:
5485:
5195:(in German). Deutsche Bahn. September 2018
5182:
5098:(in German). 28 April 2010. Archived from
5078:"Augsburg: weniger ICE ab Dezember 2006".
5053:
4887:(in German) (3). Eisenbahnfreunde Hamburg.
4708:
4683:"Unterrichtung durch die Bundesregierung:
4675:
4277:
4094:
3934:
3842:
3784:
3718:
3481:
5283:(in German). 12 June 2007. Archived from
4742:
4646:
3982:"Nürnberg: Bauarbeiten in vollem Gange".
3514:
2853:
1804:Options 1, 4–8 with a stop in Ingolstadt;
1253:in Bavaria, Germany. It branches off the
5135:
4461:
3636:
3142:
3004:
2857:
2532:
2521:
2477:
2473:
2418:
2313:
2241:
2210:
2202:
1888:
1880:
1872:
1552:
1493:Development of the Nuremberg–Munich line
1460:
1380:
1364:
1317:
1305:
5432:
5138:"Planungsprocedere; Trassenanmeldungen"
5068:2006 summer timetable of 31 August 2006
4882:
4864:Deutsche Bahn Winter 2005/06 timetables
4611:
4596:
4538:"Finanzierungsvereinbarung getroffen".
4496:
4233:
4071:(in German). 9 January 1999. p. 2.
3943:
3906:
3803:
3537:
3508:
3457:
3370:
3351:
3339:
3327:
3308:
3293:
2624:
2495:(Dortmund/Essen–Nuremberg–Munich). The
2482:TGV POS on the Main-Danube-Canal Bridge
2299:235 with a sound measurement train and
1605:
1239:Nuremberg–Ingolstadt high-speed railway
22:Nuremberg–Ingolstadt high-speed railway
6545:
5694:
5161:
5120:
4878:
4876:
4874:
4872:
4870:
4444:
3271:(similar version from January 1999 as
2581:
45:Schnellfahrstrecke Nürnberg–Ingolstadt
5620:
5480:
5136:Butzbach, Volker (12 December 2021).
4959:
4100:
3520:
3216:(in German). Nürnberg: DB ProjektBau.
3013:push-pull train set operating as the
2641:Connections to Augsburg in comparison
2351:and the then CEO of Deutsche Bahn AG
1521:(62 kilometres) was completed by the
1397:The new line rises on the ramp to an
1310:The line separates from the existing
5674:
5388:"Perfekter Anschluss an Regiozüge".
3074:, former long-distance coaches with
2990:
2715:Traffic via Ingolstadt in comparison
2518:World record run on 2 September 2006
1900:Key data of the preliminary planning
1548:
1241:is a 78-kilometre-long (48 mi)
6553:High-speed railway lines in Germany
5437:(in German). Hamburg: Eurailpress.
5346:"Baubeginn bei 28-Millionen-Tunnel"
5014:"Netztestate Stufe 1 & Stufe 2"
4867:
2746:(continuing towards Leipzig/Berlin,
2672:(continuing towards Leipzig/Berlin,
2410:Gemeindeverkehrsfinanzierungsgesetz
2106:Construction of the high-speed line
13:
4904:(in German) (10): 504, 505. 2006.
4800:"Positive Verkehrsbilanz der DB".
3772:(in German) (30): 16. 12 July 1994
3715:Bundesverkehrswegeplan 1992, p 35.
1613:Koordinierten Investitionsprogramm
1261:to Ingolstadt, where it joins the
14:
6594:
5452:
5162:Walter, Dirk (13 November 2011).
4933:(in German) (3): 71. March 2021.
3053:Wendlingen–Ulm high-speed railway
2046:administrative district of Swabia
1533:), emphasised in a memorandum to
1282:Trans-European Transport Networks
5673:
5664:
5663:
5508:
5370:
3828:Roth-Hilpoltsteiner Volkszeitung
3267:Nürnberg–München in einer Stunde
2553:. The train protection systems (
2268:
2149:University of Erlangen–Nuremberg
1960:Key data after the investigation
1868:
1622:On 3 August 1983, the Nuremberg
1543:Donauwörth–Treuchtlingen railway
1501:built between 1843 and 1849 via
1272:The line is an extension of the
1184:
1159:
1135:
1128:
1100:
1072:
1044:
1016:
988:
957:
927:
897:
896:
889:
883:
882:
854:
824:
796:
766:
765:
758:
752:
751:
720:
691:
660:
630:
602:
571:
543:
513:
483:
452:
422:
421:
414:
408:
407:
383:
376:
346:
323:
301:
294:
269:
27:
5299:
5234:"Resolution of the 13th Senate"
5088:
5006:
4858:
4820:Auszug aus dem Schwarzbuch 2005
4810:
4398:Federal Law Gazette 1995 Part I
4383:
4215:"Nürnberg–Ingolstadt–München".
4058:
3956:
3912:
3887:(in German). 22 September 2005.
3747:
3709:
3670:
3556:
3345:
3036:(DB class 102) locomotives and
2787:(with a stop in Ingolstadt: 22)
2780:(all with a stop in Ingolstadt)
2771:(from Leipzig/Berlin, Frankfurt
2762:(with a stop in Ingolstadt: 22)
2755:(all with a stop in Ingolstadt)
2611:
2602:
2198:
2195:later took over this function.
2125:In the course of planning, the
1523:Munich–Augsburg Railway Company
1473:of up to 160 millimetres and a
1391:Nuremberg–Feucht–Altdorf S-Bahn
1101:
1073:
1045:
1017:
989:
958:
855:
825:
797:
721:
661:
631:
603:
572:
544:
484:
453:
347:
312:from Nuremberg marshalling yard
121:77.572 km (48.201 mi)
5323:Frankfurter Allgemeine Zeitung
5190:"Digitale Schiene Deutschland"
4128:"Erfolge innovativer Arbeit".
4068:Frankfurter Allgemeine Zeitung
3491:"Neuer Schnellfahrabschnitt".
2537:The 1216 050 in Ingolstadt Hbf
2414:Bundesschienenwegeausbaugesetz
1274:German Unity Transport Project
1245:running between the cities of
1136:
1129:
384:
302:
295:
96:900.1 (long-distance services)
1:
6123:LGV Bretagne-Pays de la Loire
5123:Eisenbahntechnische Rundschau
5081:Eisenbahn-Revue International
4960:Demel, Julia (5 March 2021).
4901:Eisenbahn-Revue International
4803:Eisenbahn-Revue International
4786:Eisenbahn-Revue International
4379:(in German) (7): 334 f. 2006.
4376:Eisenbahn-Revue International
4326:Eisenbahntechnische Rundschau
4307:Eisenbahn-Revue International
4290:Eisenbahn-Revue International
4248:Eisenbahntechnische Rundschau
4217:Eisenbahntechnische Rundschau
4201:Eisenbahn-Revue International
4176:Eisenbahntechnische Rundschau
4084:Eisenbahntechnische Rundschau
4046:(in German) (10): 441. 1998.
4043:Eisenbahn-Revue International
3946:Eisenbahntechnische Rundschau
3806:Eisenbahntechnische Rundschau
3690:(in German) (9): 807 f. 1989.
3640:Eisenbahn-Revue International
3495:(in German): 270. April 1981.
3493:Eisenbahntechnische Rundschau
3410:Eisenbahntechnische Rundschau
3354:Eisenbahntechnische Rundschau
3311:Eisenbahntechnische Rundschau
3111:
2825:
2773:and originally from Hannover)
1663:Environmental sustainability
1563:Donauwörth–Treuchtlingen line
1343:and the A 9 near Großhöbing.
1223:Source: German railway atlas
1185:
377:
336:Nürnberg Reichswald junction
270:
175:4,085 m (13,402 ft)
4818:München-Ingolstadt-Nürnberg.
4789:(in German) (12): 532. 2000.
3920:"1 BvR 650/97; 1 BvR 830/98"
3626:(in German). 11 August 1987.
3540:Jahrbuch des Eisenbahnwesens
3240:(in German) (10): 818. 1991.
2699:continuing towards Hannover)
1977:(without tilting technology)
1448:Munich–Treuchtlingen railway
1375:Nuremberg-Regensburg railway
1263:Munich–Treuchtlingen railway
1255:Nuremberg–Regensburg railway
915:Eichstätt–Beilngries railway
890:
759:
740:2227 near Großhöbing (305 m)
415:
196:300 km/h (186 mph)
7:
6563:Rail transport in Nuremberg
5515:Berlin–Palermo railway axis
5084:(in German) (4): 158. 2006.
4964:(in German). Archived from
4806:(in German) (5): 210. 2002.
4293:(in German) (1): 2 f. 2006.
4065:"Unternehmensnachrichten".
3830:(in German). 9 March 1992.
3564:Bundesverkehrswegeplan 1985
3099:
2975:train pair IC 2410/IC 2411
2959:, hourly with gaps, ICE 1,
2392:be borne by Deutsche Bahn.
2327:familiarisation trips with
1160:
928:
692:
514:
324:
16:Key Bavarian transport link
10:
6599:
5773:Lanzhou (Xining)–Guangzhou
5669:High-speed rail by country
5606:Salerno–Reggio di Calabria
5426:
5404:"S5 hat weiter Verspätung"
5351:Oberbayerisches Volksblatt
4924:"ICE-S auf rasanter Fahrt"
4310:(in German) (1): 57. 2006.
4204:(in German) (2): 50. 2001.
3643:(in German) (3): 148–151.
3106:High-speed rail in Germany
3090:Alstom Coradia Continental
2994:
2967:In the 2007 timetable, an
2597:
2120:Bund Naturschutz in Bayern
2050:Bund Naturschutz in Bayern
1487:
1314:near Feucht (bottom right)
440:Feucht–Wendelstein railway
6533:
6519:
6507:
6490:
6483:
6461:
6447:
6383:
6360:
6345:
6327:
6309:
6261:
6242:
6177:
6163:LGV Sud Europe Atlantique
6108:
6083:
6065:
6031:
6022:
5997:
5963:
5947:
5922:Suseo–Pyeongtaek HSR Line
5902:
5886:
5833:
5817:
5723:
5714:
5687:
5654:
5521:
3477:(in German). 12 May 2006.
2714:
2640:
2365:Federal Railway Authority
1963:(DB board of 31 May 1991)
1959:
1899:
1851:Neumarkt–Dietfurt railway
1803:
1312:Nuremberg–Regensburg line
1257:and runs parallel to the
1193:
1178:
1171:
1153:
1144:
1122:
1112:
1094:
1084:
1066:
1056:
1038:
1028:
1010:
1000:
982:
972:
951:
921:
911:
876:
866:
848:
839:
818:
808:
790:
780:
745:
735:
714:
706:
685:
675:
654:
645:
624:
614:
596:
586:
565:
555:
537:
507:
498:
477:
467:
446:
436:
401:
392:
370:
361:
340:
335:
317:
310:
288:
278:
263:
241:
210:
200:
192:
179:
169:
133:
125:
117:
112:
102:
87:
82:
68:
60:
50:
44:
40:
35:
26:
21:
6583:Rail transport in Munich
6558:Railway lines in Bavaria
5749:Harbin–Hong Kong (Macau)
5648:High-speed railway lines
5410:(in German). 7 June 2019
5326:(in German). 14 May 2006
5262:(in German). 5 May 2010.
5222:(11): 60. November 2019.
4469:(in German). p. 46.
4467:, Regionalausgabe Bayern
4347:"Tätigkeitsbericht 2006"
4267:ZEVrail, Glasers Annalen
3022:Munich-Nuremberg Express
3015:Munich Nuremberg Express
2997:München-Nürnberg-Express
2681:(opposite direction: 19)
2619:Munich-Nuremberg Express
2434:Eisenbahnkreuzungsgesetz
2132:, the installation of a
1301:
6374:St. Petersburg-Helsinki
6168:LGV Perpignan–Barcelona
6099:St. Petersburg-Helsinki
5863:Nishi Kyushu Shinkansen
5125:(in German) (6): 28–32.
4816:Bund der Steuerzahler:
3330:, pp. 109 f., 120.
2748:Frankfurt and Hannover)
2737:(from 10 December 2006)
2730:(until 9 December 2006)
2688:(opposite direction: 8)
2674:Frankfurt and Hannover)
2663:(from 10 December 2006)
2656:(until 9 December 2006)
2374:
2130:train protection system
2054:Das bessere Bahnkonzept
2025:(with a stop in Pasing)
1660:(approx, in DM billion)
1519:Munich–Augsburg railway
1452:Ingolstadt Hauptbahnhof
1444:Ingolstadt Nord station
1267:Ingolstadt Nord station
589:Rhine–Main–Danube Canal
93:900 (regional services)
6133:LGV Interconnexion Est
5472:railway-technology.com
5281:Der Mobilitäts-Manager
5216:Der Eisenbahningenieur
4448:Nürnberger Nachrichten
3094:Linienzugbeeinflussung
3017:
2863:
2854:Long-distance services
2538:
2530:
2483:
2424:
2319:
2247:
2216:
2208:
1894:
1886:
1878:
1842:designed for 200 km/h.
1617:Bundesverkehrswegeplan
1583:Intercity Experimental
1566:
1517:(170 kilometres). The
1466:
1394:
1370:
1331:
1315:
5937:(Cheongnyangni-Dodam)
4198:"Teure ICE-Strecke".
3826:"Sehe nur Probleme".
3475:Augsburger Allgemeine
3008:
2943:Munich – Nuremberg –
2908:Munich – Nuremberg –
2861:
2734:2007 summer timetable
2727:Summer timetable 2006
2660:2007 summer timetable
2653:Summer timetable 2006
2536:
2525:
2481:
2474:Preliminary operation
2422:
2317:
2245:
2214:
2206:
2078:to Minister of State
1892:
1884:
1876:
1825:. After crossing the
1556:
1464:
1384:
1368:
1321:
1309:
6368:Moscow–St.Petersburg
6214:Nuremberg–Ingolstadt
5576:Franzensfeste–Verona
5541:Nuremberg–Ingolstadt
2932:, hourly with gaps,
2901:, hourly with gaps,
2625:Capacity, operations
2343:, Interior Minister
2161:Bilfinger and Berger
2072:German reunification
1606:First considerations
1356:Kinding (Altmühltal)
1352:Allersberg (Rothsee)
941:Kinding (Altmühltal)
784:Roth–Greding railway
527:Allersberg (Rothsee)
188:AC overhead catenary
6408:Barcelona–Perpignan
6252:Athens–Thessaloniki
6075:Copenhagen–Ringsted
5848:Hokuriku Shinkansen
5843:Hokkaido Shinkansen
5755:Guangzhou–Hong Kong
5358:on 11 February 2013
5102:on 22 November 2015
4783:"Kostenexplosion".
4465:Süddeutsche Zeitung
3194:on 13 December 2021
2582:Further development
2357:Munich Hauptbahnhof
1653:Running time saving
1641:
1628:Deutsche Bundesbahn
869:Schellenberg Tunnel
6496:Northeast Corridor
6403:Madrid–Extremadura
6353:Grodzisk–Zawiercie
6208:Mannheim–Stuttgart
6005:Tashkent–Samarkand
5878:Tōkaidō Shinkansen
5794:Lianyungang–Ürümqi
5778:Suifenhe–Manzhouli
5702:Casablanca–Tangier
5551:Rosenheim–Kufstein
3764:"Falsch gerechnet"
3624:Nürnberger Zeitung
3060:Allersberg Express
3018:
2864:
2543:EuroSprinter 64 U4
2539:
2531:
2484:
2425:
2349:Wolfgang Tiefensee
2320:
2253:track geometry car
2248:
2217:
2209:
2016:Travel time saving
1941:Travel time saving
1895:
1887:
1879:
1640:Option comparison
1639:
1633:cost–benefit ratio
1579:Mannheim–Stuttgart
1567:
1535:King Maximilian II
1467:
1399:overpass structure
1395:
1371:
1332:
1316:
1243:high-speed railway
1147:from Treuchtlingen
558:Göggelsbuch Tunnel
470:Schwarzach Viaduct
395:line to Regensburg
282:from Nuremberg Hbf
6540:
6539:
6529:
6503:
6502:
6479:
6478:
6224:Rastatt–Offenburg
6193:Cologne–Frankfurt
6018:
6017:
6010:Samarkand–Bukhara
5938:
5930:
5929:(Wonju-Gangneung)
5912:Gyeongbu HSR Line
5873:Tōhoku Shinkansen
5868:San'yō Shinkansen
5858:Kyushu Shinkansen
5853:Jōetsu Shinkansen
5809:Guangzhou–Kunming
5757:
5744:Beijing–Hong Kong
5710:
5709:
5614:
5613:
4885:Hamburger Blätter
4499:, pp. 56 ff.
4392:Bundesgesetzblatt
4223:(7/8): 412. 1999.
3909:, pp. 50 ff.
3135:978-3-89494-139-0
2991:Regional services
2792:
2791:
2788:
2781:
2774:
2763:
2756:
2749:
2738:
2731:
2719:
2710:
2709:
2700:
2689:
2682:
2675:
2664:
2657:
2645:
2345:Günther Beckstein
2134:ballastless track
2041:
2040:
2037:DM 2,637 billion
2026:
1978:
1971:Ingolstadt option
1964:
1955:
1954:
1945:
1911:Ingolstadt option
1904:
1810:
1809:
1655:(approx, in min.)
1591:federal highway 4
1586:Intercity Express
1549:Initial situation
1412:Main–Danube Canal
1235:
1234:
1231:
1230:
1227:
1226:
1218:
1217:
1031:Denkendorf Tunnel
6590:
6528:
6488:
6487:
6414:Madrid–Barcelona
6271:Bologna–Florence
6234:Wolfsburg–Berlin
6219:Nuremberg–Erfurt
6203:Hanover–Würzburg
6138:LGV Méditerranée
6029:
6028:
5936:
5928:
5927:Gyeonggang Line
5804:Shanghai–Kunming
5799:Shanghai–Chengdu
5789:Qingdao–Yinchuan
5753:
5739:Beijing–Shanghai
5733:Coastal corridor
5721:
5720:
5692:
5691:
5677:
5676:
5667:
5666:
5641:
5634:
5627:
5618:
5617:
5586:Bologna–Florence
5566:Innsbruck bypass
5546:Munich–Rosenheim
5536:Erfurt–Nuremberg
5513:
5512:
5501:
5494:
5487:
5478:
5477:
5448:
5420:
5419:
5417:
5415:
5400:
5394:
5393:
5385:
5379:
5378:
5374:
5368:
5367:
5365:
5363:
5342:
5336:
5335:
5333:
5331:
5314:
5308:
5307:
5303:
5297:
5296:
5294:
5292:
5273:
5264:
5263:
5252:
5246:
5245:
5243:
5241:
5230:
5224:
5223:
5211:
5205:
5204:
5202:
5200:
5194:
5186:
5180:
5179:
5177:
5175:
5159:
5153:
5152:
5150:
5148:
5142:
5133:
5127:
5126:
5118:
5112:
5111:
5109:
5107:
5092:
5086:
5085:
5075:
5069:
5066:
5060:
5057:
5051:
5050:
5048:
5046:
5035:
5029:
5028:
5026:
5024:
5018:
5010:
5004:
5003:
5001:
4999:
4984:
4978:
4977:
4975:
4973:
4957:
4951:
4950:
4928:
4920:
4914:
4913:
4895:
4889:
4888:
4880:
4865:
4862:
4856:
4855:
4849:
4845:
4843:
4835:
4827:
4821:
4814:
4808:
4807:
4797:
4791:
4790:
4780:
4769:
4768:
4766:
4764:
4754:
4746:
4740:
4739:
4737:
4735:
4725:
4715:
4706:
4705:
4703:
4701:
4691:
4679:
4673:
4672:
4670:
4668:
4658:
4650:
4644:
4643:
4641:
4639:
4629:
4621:
4615:
4609:
4600:
4594:
4583:
4582:
4580:
4578:
4563:
4552:
4551:
4535:
4529:
4528:
4526:
4524:
4514:
4506:
4500:
4494:
4471:
4470:
4459:
4453:
4452:
4442:
4436:
4435:
4433:
4431:
4421:
4413:
4402:
4401:
4387:
4381:
4380:
4370:
4361:
4360:
4359:on 18 July 2011.
4358:
4351:
4343:
4334:
4333:
4321:
4312:
4311:
4301:
4295:
4294:
4284:
4275:
4274:
4273:(10): 447. 2005.
4262:
4256:
4255:
4243:
4237:
4231:
4225:
4224:
4212:
4206:
4205:
4195:
4184:
4183:
4182:(1/2): 88. 1999.
4171:
4165:
4164:
4148:
4142:
4141:
4125:
4119:
4118:
4098:
4092:
4091:
4079:
4073:
4072:
4062:
4056:
4055:
4037:
4026:
4025:
4005:
3996:
3995:
3979:
3973:
3972:
3960:
3954:
3953:
3941:
3932:
3931:
3929:
3927:
3916:
3910:
3904:
3889:
3888:
3880:
3874:
3873:
3871:
3869:
3859:
3851:
3840:
3839:
3823:
3814:
3813:
3801:
3782:
3781:
3779:
3777:
3760:
3754:
3751:
3745:
3744:
3742:
3740:
3730:
3722:
3716:
3713:
3707:
3703:
3692:
3691:
3683:
3677:
3674:
3668:
3664:
3653:
3652:
3634:
3628:
3627:
3619:
3608:
3607:
3605:
3603:
3593:
3581:
3568:
3567:
3560:
3554:
3553:
3535:
3529:
3528:
3524:Eisenbahn-Kurier
3518:
3512:
3506:
3497:
3496:
3488:
3479:
3478:
3467:
3461:
3460:, p. 14 ff.
3455:
3418:
3417:
3405:
3374:
3368:
3362:
3361:
3349:
3343:
3337:
3331:
3325:
3319:
3318:
3306:
3297:
3291:
3276:
3270:
3263:
3242:
3241:
3233:
3218:
3217:
3210:
3204:
3203:
3201:
3199:
3184:
3175:
3174:
3172:
3170:
3157:
3149:
3140:
3139:
3122:
3072:Nuremberg S-Bahn
3064:class 111 or 112
3050:
3048:
3031:
3029:
2958:
2956:
2931:
2929:
2900:
2898:
2837:Nuremberg S-Bahn
2786:
2779:
2770:
2768:Nuremberg–Munich
2761:
2754:
2745:
2743:Munich–Nuremberg
2736:
2729:
2717:
2712:
2711:
2696:
2687:
2680:
2671:
2669:Munich–Nuremberg
2662:
2655:
2643:
2638:
2637:
2551:DB Systemtechnik
2309:DB Systemtechnik
2088:Nuremberg S-Bahn
2034:DM 3,010 billion
2024:
1976:
1962:
1957:
1956:
1944:Munich–Nuremberg
1943:
1914:Augsburg option
1902:
1897:
1896:
1642:
1638:
1624:railway division
1600:Nuremberg S-Bahn
1575:Hanover–Würzburg
1454:(main station).
1188:
1187:
1163:
1162:
1139:
1138:
1132:
1131:
1104:
1103:
1076:
1075:
1048:
1047:
1020:
1019:
992:
991:
969:
961:
960:
931:
930:
908:
900:
899:
893:
892:
886:
885:
858:
857:
836:
828:
827:
800:
799:
777:
769:
768:
762:
761:
755:
754:
732:
724:
723:
703:
695:
694:
672:
664:
663:
642:
634:
633:
606:
605:
583:
575:
574:
547:
546:
517:
516:
495:
487:
486:
464:
456:
455:
433:
425:
424:
418:
417:
411:
410:
387:
386:
380:
379:
358:
350:
349:
327:
326:
305:
304:
298:
297:
273:
272:
239:
238:
226:
212:
211:
165:
159:
157:
156:
152:
149:
141:
126:Number of tracks
46:
31:
19:
18:
6598:
6597:
6593:
6592:
6591:
6589:
6588:
6587:
6543:
6542:
6541:
6536:
6527:
6515:
6499:
6475:
6457:
6443:
6379:
6356:
6341:
6337:Gardermoen Line
6323:
6305:
6257:
6238:
6173:
6153:LGV Rhône-Alpes
6104:
6079:
6061:
6014:
5993:
5973:Ankara–Istanbul
5959:
5943:
5898:
5882:
5829:
5813:
5783:Beijing–Lanzhou
5768:Beijing–Kunming
5706:
5683:
5659:High-speed rail
5650:
5645:
5615:
5610:
5561:Wörgl–Innsbruck
5517:
5507:
5505:
5455:
5445:
5429:
5424:
5423:
5413:
5411:
5402:
5401:
5397:
5387:
5386:
5382:
5376:
5375:
5371:
5361:
5359:
5344:
5343:
5339:
5329:
5327:
5316:
5315:
5311:
5305:
5304:
5300:
5290:
5288:
5287:on 21 June 2015
5275:
5274:
5267:
5254:
5253:
5249:
5239:
5237:
5232:
5231:
5227:
5213:
5212:
5208:
5198:
5196:
5192:
5188:
5187:
5183:
5173:
5171:
5160:
5156:
5146:
5144:
5140:
5134:
5130:
5119:
5115:
5105:
5103:
5094:
5093:
5089:
5077:
5076:
5072:
5067:
5063:
5058:
5054:
5044:
5042:
5037:
5036:
5032:
5022:
5020:
5016:
5012:
5011:
5007:
4997:
4995:
4986:
4985:
4981:
4971:
4969:
4968:on 6 March 2021
4958:
4954:
4926:
4922:
4921:
4917:
4897:
4896:
4892:
4881:
4868:
4863:
4859:
4847:
4846:
4837:
4836:
4828:
4824:
4815:
4811:
4799:
4798:
4794:
4782:
4781:
4772:
4762:
4760:
4752:
4748:
4747:
4743:
4733:
4731:
4723:
4720:
4717:
4716:
4709:
4699:
4697:
4689:
4681:
4680:
4676:
4666:
4664:
4656:
4652:
4651:
4647:
4637:
4635:
4627:
4623:
4622:
4618:
4610:
4603:
4595:
4586:
4576:
4574:
4565:
4564:
4555:
4537:
4536:
4532:
4522:
4520:
4512:
4508:
4507:
4503:
4495:
4474:
4460:
4456:
4443:
4439:
4429:
4427:
4419:
4415:
4414:
4405:
4389:
4388:
4384:
4372:
4371:
4364:
4356:
4349:
4345:
4344:
4337:
4322:
4315:
4303:
4302:
4298:
4286:
4285:
4278:
4264:
4263:
4259:
4244:
4240:
4232:
4228:
4214:
4213:
4209:
4197:
4196:
4187:
4173:
4172:
4168:
4150:
4149:
4145:
4127:
4126:
4122:
4099:
4095:
4090:(4): 246. 1999.
4081:
4080:
4076:
4064:
4063:
4059:
4039:
4038:
4029:
4006:
3999:
3981:
3980:
3976:
3961:
3957:
3942:
3935:
3925:
3923:
3918:
3917:
3913:
3905:
3892:
3882:
3881:
3877:
3867:
3865:
3857:
3853:
3852:
3843:
3825:
3824:
3817:
3802:
3785:
3775:
3773:
3762:
3761:
3757:
3752:
3748:
3738:
3736:
3728:
3724:
3723:
3719:
3714:
3710:
3704:
3695:
3685:
3684:
3680:
3675:
3671:
3665:
3656:
3635:
3631:
3621:
3620:
3611:
3601:
3599:
3591:
3583:
3582:
3571:
3562:
3561:
3557:
3550:
3536:
3532:
3519:
3515:
3511:, p. 18 f.
3507:
3500:
3490:
3489:
3482:
3469:
3468:
3464:
3456:
3421:
3406:
3377:
3369:
3365:
3350:
3346:
3338:
3334:
3326:
3322:
3307:
3300:
3296:, p. 12 f.
3292:
3279:
3265:
3264:
3245:
3235:
3234:
3221:
3212:
3211:
3207:
3197:
3195:
3186:
3185:
3178:
3168:
3166:
3155:
3151:
3150:
3143:
3136:
3124:
3123:
3119:
3114:
3102:
3066:and modernised
3046:
3044:
3041:push–pull train
3027:
3025:
3003:
2995:Main articles:
2993:
2954:
2952:
2927:
2925:
2896:
2894:
2856:
2828:
2785:
2778:
2772:
2769:
2760:
2753:
2747:
2744:
2735:
2728:
2716:
2698:
2695:
2694:Munich–Würzburg
2686:
2679:
2673:
2670:
2661:
2654:
2642:
2636:
2627:
2614:
2605:
2600:
2584:
2520:
2476:
2377:
2353:Hartmut Mehdorn
2271:
2201:
2145:Franconian Jura
2108:
2080:Peter Gauweiler
2023:
1975:
1974:Augsburg option
1961:
1942:
1936:DM 1.7 billion
1901:
1871:
1805:
1659:
1654:
1649:
1608:
1551:
1495:
1490:
1475:cant deficiency
1432:above sea level
1326:(left) and the
1304:
1198:
1189:
1173:Ingolstadt Nord
1169:
1164:
1149:
1140:
1133:
1118:
1110:
1105:
1090:
1087:Geisberg Tunnel
1082:
1077:
1062:
1059:Stammham Tunnel
1054:
1049:
1034:
1026:
1021:
1006:
1003:Irlahüll Tunnel
998:
993:
978:
970:
967:
962:
947:
937:
932:
917:
909:
906:
901:
894:
887:
872:
864:
859:
844:
837:
834:
829:
814:
811:Euerwang Tunnel
806:
801:
786:
778:
775:
770:
763:
756:
741:
733:
730:
725:
704:
701:
696:
681:
673:
670:
665:
650:
643:
640:
635:
620:
617:Offenbau Tunnel
612:
607:
592:
584:
581:
576:
561:
553:
548:
533:
523:
518:
503:
496:
493:
488:
473:
465:
462:
457:
442:
434:
431:
426:
419:
412:
397:
388:
381:
366:
359:
356:
351:
333:
328:
313:
306:
299:
284:
274:
259:
250:
233:
217:
202:Maximum incline
193:Operating speed
181:Electrification
161:
154:
150:
147:
145:
144:4 ft
143:
139:
17:
12:
11:
5:
6596:
6586:
6585:
6580:
6575:
6570:
6565:
6560:
6555:
6538:
6537:
6534:
6531:
6530:
6523:
6521:
6517:
6516:
6511:
6509:
6505:
6504:
6501:
6500:
6494:
6492:
6485:
6481:
6480:
6477:
6476:
6474:
6473:
6467:
6465:
6463:United Kingdom
6459:
6458:
6453:
6451:
6445:
6444:
6442:
6441:
6439:Madrid–Levante
6436:
6431:
6429:Madrid–Seville
6426:
6421:
6416:
6411:
6405:
6400:
6398:Madrid–Galicia
6395:
6389:
6387:
6381:
6380:
6378:
6377:
6371:
6364:
6362:
6358:
6357:
6351:
6349:
6343:
6342:
6340:
6339:
6333:
6331:
6325:
6324:
6322:
6321:
6315:
6313:
6307:
6306:
6304:
6303:
6298:
6293:
6291:Naples–Salerno
6288:
6283:
6278:
6273:
6267:
6265:
6259:
6258:
6256:
6255:
6248:
6246:
6240:
6239:
6237:
6236:
6231:
6229:Wendlingen–Ulm
6226:
6221:
6216:
6211:
6205:
6200:
6198:Erfurt–Leipzig
6195:
6190:
6183:
6181:
6175:
6174:
6172:
6171:
6165:
6160:
6155:
6150:
6148:LGV Rhin-Rhône
6145:
6140:
6135:
6130:
6125:
6120:
6118:LGV Atlantique
6114:
6112:
6106:
6105:
6103:
6102:
6096:
6089:
6087:
6081:
6080:
6078:
6077:
6071:
6069:
6063:
6062:
6060:
6059:
6054:
6048:
6043:
6037:
6035:
6026:
6020:
6019:
6016:
6015:
6013:
6012:
6007:
6001:
5999:
5995:
5994:
5992:
5991:
5985:
5980:
5975:
5969:
5967:
5961:
5960:
5958:
5957:
5951:
5949:
5945:
5944:
5942:
5941:
5932:
5924:
5919:
5917:Honam HSR Line
5914:
5908:
5906:
5900:
5899:
5897:
5896:
5890:
5888:
5884:
5883:
5881:
5880:
5875:
5870:
5865:
5860:
5855:
5850:
5845:
5839:
5837:
5831:
5830:
5828:
5827:
5821:
5819:
5815:
5814:
5812:
5811:
5806:
5801:
5796:
5791:
5786:
5780:
5775:
5770:
5765:
5763:Hohhot–Nanning
5760:
5759:
5758:
5746:
5741:
5736:
5729:
5727:
5718:
5712:
5711:
5708:
5707:
5705:
5704:
5698:
5696:
5689:
5685:
5684:
5682:
5681:
5671:
5661:
5655:
5652:
5651:
5644:
5643:
5636:
5629:
5621:
5612:
5611:
5609:
5608:
5603:
5601:Naples–Salerno
5598:
5593:
5588:
5583:
5581:Verona–Bologna
5578:
5573:
5568:
5563:
5558:
5556:Kufstein–Wörgl
5553:
5548:
5543:
5538:
5533:
5528:
5522:
5519:
5518:
5504:
5503:
5496:
5489:
5481:
5475:
5474:
5465:
5454:
5453:External links
5451:
5450:
5449:
5443:
5428:
5425:
5422:
5421:
5395:
5380:
5369:
5337:
5309:
5298:
5265:
5247:
5225:
5206:
5181:
5154:
5128:
5113:
5087:
5070:
5061:
5052:
5030:
5005:
4979:
4952:
4915:
4890:
4866:
4857:
4822:
4809:
4792:
4770:
4757:Printed Matter
4741:
4728:Printed Matter
4707:
4694:Printed Matter
4674:
4661:Printed Matter
4645:
4632:Printed Matter
4616:
4614:, p. 213.
4601:
4584:
4573:on 15 May 2016
4553:
4530:
4517:Printed Matter
4501:
4472:
4454:
4437:
4424:Printed Matter
4403:
4382:
4362:
4335:
4313:
4296:
4276:
4257:
4254:(12): 736–747.
4238:
4236:, p. 130.
4226:
4207:
4185:
4166:
4143:
4120:
4103:Signal + Draht
4093:
4074:
4057:
4027:
4016:(5): 358–366.
3997:
3974:
3955:
3933:
3911:
3890:
3875:
3862:Printed Matter
3841:
3815:
3783:
3755:
3746:
3733:Printed Matter
3717:
3708:
3693:
3688:Die Bundesbahn
3678:
3669:
3654:
3629:
3609:
3596:Printed Matter
3569:
3555:
3548:
3530:
3513:
3498:
3480:
3462:
3419:
3375:
3373:, p. 103.
3363:
3344:
3342:, p. 116.
3332:
3320:
3298:
3277:
3243:
3238:Die Bundesbahn
3219:
3205:
3176:
3141:
3134:
3116:
3115:
3113:
3110:
3109:
3108:
3101:
3098:
3001:S5 (Nuremberg)
2992:
2989:
2965:
2964:
2941:
2906:
2855:
2852:
2827:
2824:
2790:
2789:
2782:
2775:
2765:
2764:
2757:
2750:
2740:
2739:
2732:
2725:
2721:
2720:
2708:
2707:
2704:
2701:
2697:(via Ansbach ,
2691:
2690:
2683:
2676:
2666:
2665:
2658:
2651:
2647:
2646:
2635:
2632:
2626:
2623:
2613:
2610:
2604:
2601:
2599:
2596:
2583:
2580:
2519:
2516:
2475:
2472:
2376:
2373:
2270:
2267:
2221:Edmund Stoiber
2200:
2197:
2107:
2104:
2039:
2038:
2035:
2032:
2028:
2027:
2020:
2017:
2013:
2012:
2009:
2006:
2002:
2001:
2000:200 km/h
1998:
1995:
1991:
1990:
1987:
1984:
1980:
1979:
1972:
1969:
1966:
1965:
1953:
1952:
1949:
1946:
1938:
1937:
1934:
1933:DM 2.4 billion
1931:
1927:
1926:
1923:
1920:
1916:
1915:
1912:
1909:
1906:
1905:
1870:
1867:
1859:
1858:
1854:
1847:
1843:
1839:
1835:
1831:
1818:
1808:
1807:
1801:
1800:
1797:
1794:
1791:
1788:
1784:
1783:
1780:
1777:
1774:
1771:
1767:
1766:
1763:
1760:
1757:
1754:
1750:
1749:
1746:
1743:
1740:
1737:
1733:
1732:
1729:
1726:
1723:
1720:
1716:
1715:
1712:
1709:
1706:
1703:
1699:
1698:
1695:
1692:
1689:
1686:
1682:
1681:
1678:
1675:
1672:
1669:
1665:
1664:
1661:
1656:
1651:
1646:
1607:
1604:
1550:
1547:
1494:
1491:
1489:
1486:
1360:sets of points
1303:
1300:
1233:
1232:
1229:
1228:
1225:
1224:
1220:
1219:
1216:
1215:
1213:
1211:
1209:
1207:
1205:
1203:
1200:
1199:
1194:
1192:
1190:
1183:
1181:
1179:
1176:
1175:
1170:
1167:
1165:
1158:
1156:
1154:
1151:
1150:
1145:
1143:
1141:
1134:
1127:
1125:
1123:
1120:
1119:
1113:
1111:
1108:
1106:
1099:
1097:
1095:
1092:
1091:
1085:
1083:
1080:
1078:
1071:
1069:
1067:
1064:
1063:
1057:
1055:
1052:
1050:
1043:
1041:
1039:
1036:
1035:
1029:
1027:
1024:
1022:
1015:
1013:
1011:
1008:
1007:
1001:
999:
996:
994:
987:
985:
983:
980:
979:
975:Altmühl Bridge
973:
971:
965:
963:
956:
954:
952:
949:
948:
945:
943:
938:
935:
933:
926:
924:
922:
919:
918:
912:
910:
904:
902:
895:
888:
881:
879:
877:
874:
873:
867:
865:
862:
860:
853:
851:
849:
846:
845:
840:
838:
832:
830:
823:
821:
819:
816:
815:
809:
807:
804:
802:
795:
793:
791:
788:
787:
781:
779:
773:
771:
764:
757:
750:
748:
746:
743:
742:
736:
734:
728:
726:
719:
717:
715:
712:
711:
705:
699:
697:
690:
688:
686:
683:
682:
676:
674:
668:
666:
659:
657:
655:
652:
651:
646:
644:
638:
636:
629:
627:
625:
622:
621:
615:
613:
610:
608:
601:
599:
597:
594:
593:
587:
585:
579:
577:
570:
568:
566:
563:
562:
556:
554:
551:
549:
542:
540:
538:
535:
534:
531:
529:
524:
521:
519:
512:
510:
508:
505:
504:
499:
497:
491:
489:
482:
480:
478:
475:
474:
468:
466:
460:
458:
451:
449:
447:
444:
443:
437:
435:
429:
427:
420:
413:
406:
404:
402:
399:
398:
393:
391:
389:
382:
375:
373:
371:
368:
367:
362:
360:
354:
352:
345:
343:
341:
338:
337:
334:
331:
329:
322:
320:
318:
315:
314:
311:
309:
307:
300:
293:
291:
289:
286:
285:
279:
277:
275:
268:
266:
264:
261:
260:
255:
253:
251:
248:
246:
244:
242:
235:
234:
229:
219:
218:
215:
208:
207:
204:
198:
197:
194:
190:
189:
183:
177:
176:
173:
171:Minimum radius
167:
166:
163:standard gauge
137:
131:
130:
127:
123:
122:
119:
115:
114:
110:
109:
107:DB Fernverkehr
104:
100:
99:
98:
97:
94:
89:
85:
84:
80:
79:
70:
66:
65:
62:
58:
57:
52:
48:
47:
42:
38:
37:
33:
32:
24:
23:
15:
9:
6:
4:
3:
2:
6595:
6584:
6581:
6579:
6576:
6574:
6571:
6569:
6566:
6564:
6561:
6559:
6556:
6554:
6551:
6550:
6548:
6532:
6526:
6522:
6520:South America
6518:
6514:
6510:
6506:
6497:
6493:
6491:United States
6489:
6486:
6484:North America
6482:
6472:
6469:
6468:
6466:
6464:
6460:
6456:
6452:
6450:
6446:
6440:
6437:
6435:
6434:Madrid–Toledo
6432:
6430:
6427:
6425:
6424:Madrid–Malaga
6422:
6420:
6417:
6415:
6412:
6409:
6406:
6404:
6401:
6399:
6396:
6394:
6393:Atlantic Axis
6391:
6390:
6388:
6386:
6382:
6375:
6372:
6369:
6366:
6365:
6363:
6359:
6354:
6350:
6348:
6344:
6338:
6335:
6334:
6332:
6330:
6326:
6320:
6317:
6316:
6314:
6312:
6308:
6302:
6299:
6297:
6294:
6292:
6289:
6287:
6284:
6282:
6281:Milan–Bologna
6279:
6277:
6276:Florence–Rome
6274:
6272:
6269:
6268:
6266:
6264:
6260:
6253:
6250:
6249:
6247:
6245:
6241:
6235:
6232:
6230:
6227:
6225:
6222:
6220:
6217:
6215:
6212:
6209:
6206:
6204:
6201:
6199:
6196:
6194:
6191:
6188:
6187:Cologne–Düren
6185:
6184:
6182:
6180:
6176:
6169:
6166:
6164:
6161:
6159:
6156:
6154:
6151:
6149:
6146:
6144:
6141:
6139:
6136:
6134:
6131:
6129:
6126:
6124:
6121:
6119:
6116:
6115:
6113:
6111:
6107:
6100:
6097:
6094:
6091:
6090:
6088:
6086:
6082:
6076:
6073:
6072:
6070:
6068:
6064:
6058:
6055:
6052:
6049:
6047:
6044:
6042:
6039:
6038:
6036:
6034:
6030:
6027:
6025:
6021:
6011:
6008:
6006:
6003:
6002:
6000:
5996:
5989:
5988:Konya–Karaman
5986:
5984:
5983:Polatlı–Konya
5981:
5979:
5976:
5974:
5971:
5970:
5968:
5966:
5962:
5956:
5953:
5952:
5950:
5946:
5939:
5935:Jungang Line
5933:
5931:
5925:
5923:
5920:
5918:
5915:
5913:
5910:
5909:
5907:
5905:
5901:
5895:
5892:
5891:
5889:
5885:
5879:
5876:
5874:
5871:
5869:
5866:
5864:
5861:
5859:
5856:
5854:
5851:
5849:
5846:
5844:
5841:
5840:
5838:
5836:
5832:
5826:
5823:
5822:
5820:
5816:
5810:
5807:
5805:
5802:
5800:
5797:
5795:
5792:
5790:
5787:
5784:
5781:
5779:
5776:
5774:
5771:
5769:
5766:
5764:
5761:
5756:
5752:
5751:
5750:
5747:
5745:
5742:
5740:
5737:
5734:
5731:
5730:
5728:
5726:
5722:
5719:
5717:
5713:
5703:
5700:
5699:
5697:
5693:
5690:
5686:
5680:
5672:
5670:
5662:
5660:
5657:
5656:
5653:
5649:
5642:
5637:
5635:
5630:
5628:
5623:
5622:
5619:
5607:
5604:
5602:
5599:
5597:
5594:
5592:
5591:Florence–Rome
5589:
5587:
5584:
5582:
5579:
5577:
5574:
5572:
5569:
5567:
5564:
5562:
5559:
5557:
5554:
5552:
5549:
5547:
5544:
5542:
5539:
5537:
5534:
5532:
5529:
5527:
5524:
5523:
5520:
5516:
5511:
5502:
5497:
5495:
5490:
5488:
5483:
5482:
5479:
5473:
5469:
5466:
5464:
5463:structurae.de
5460:
5457:
5456:
5446:
5444:3-7771-0350-0
5440:
5436:
5431:
5430:
5409:
5405:
5399:
5391:
5384:
5373:
5357:
5353:
5352:
5347:
5341:
5325:
5324:
5319:
5313:
5302:
5286:
5282:
5278:
5272:
5270:
5261:
5257:
5251:
5235:
5229:
5221:
5218:(in German).
5217:
5210:
5191:
5185:
5169:
5168:Merkur online
5165:
5158:
5139:
5132:
5124:
5117:
5101:
5097:
5091:
5083:
5082:
5074:
5065:
5056:
5040:
5034:
5015:
5009:
4994:on 1 May 2021
4993:
4989:
4983:
4967:
4963:
4956:
4948:
4944:
4940:
4936:
4932:
4925:
4919:
4911:
4907:
4903:
4902:
4894:
4886:
4879:
4877:
4875:
4873:
4871:
4861:
4853:
4841:
4833:
4832:Die neue Bahn
4826:
4819:
4813:
4805:
4804:
4796:
4788:
4787:
4779:
4777:
4775:
4758:
4751:
4745:
4729:
4722:
4714:
4712:
4695:
4688:
4686:
4678:
4662:
4655:
4649:
4633:
4626:
4620:
4613:
4608:
4606:
4599:, p. 60.
4598:
4593:
4591:
4589:
4572:
4568:
4562:
4560:
4558:
4549:
4545:
4541:
4534:
4518:
4511:
4505:
4498:
4493:
4491:
4489:
4487:
4485:
4483:
4481:
4479:
4477:
4468:
4466:
4458:
4450:
4449:
4441:
4425:
4418:
4412:
4410:
4408:
4399:
4395:
4393:
4386:
4378:
4377:
4369:
4367:
4355:
4348:
4342:
4340:
4332:(5): 289–300.
4331:
4328:(in German).
4327:
4320:
4318:
4309:
4308:
4300:
4292:
4291:
4283:
4281:
4272:
4269:(in German).
4268:
4261:
4253:
4250:(in German).
4249:
4242:
4235:
4230:
4222:
4219:(in German).
4218:
4211:
4203:
4202:
4194:
4192:
4190:
4181:
4178:(in German).
4177:
4170:
4162:
4158:
4154:
4147:
4139:
4135:
4131:
4124:
4116:
4112:
4108:
4105:(in German).
4104:
4097:
4089:
4086:(in German).
4085:
4078:
4070:
4069:
4061:
4053:
4049:
4045:
4044:
4036:
4034:
4032:
4023:
4019:
4015:
4012:(in German).
4011:
4004:
4002:
3993:
3989:
3985:
3978:
3970:
3967:(in German).
3966:
3959:
3952:(4): 182–191.
3951:
3948:(in German).
3947:
3940:
3938:
3921:
3915:
3908:
3903:
3901:
3899:
3897:
3895:
3886:
3879:
3863:
3856:
3850:
3848:
3846:
3837:
3833:
3829:
3822:
3820:
3811:
3808:(in German).
3807:
3800:
3798:
3796:
3794:
3792:
3790:
3788:
3771:
3770:
3765:
3759:
3750:
3734:
3727:
3721:
3712:
3702:
3700:
3698:
3689:
3682:
3673:
3663:
3661:
3659:
3650:
3646:
3642:
3641:
3633:
3625:
3618:
3616:
3614:
3597:
3590:
3588:
3580:
3578:
3576:
3574:
3565:
3559:
3551:
3549:3-7771-0160-5
3545:
3541:
3534:
3526:
3525:
3517:
3510:
3505:
3503:
3494:
3487:
3485:
3476:
3472:
3466:
3459:
3454:
3452:
3450:
3448:
3446:
3444:
3442:
3440:
3438:
3436:
3434:
3432:
3430:
3428:
3426:
3424:
3415:
3412:(in German).
3411:
3404:
3402:
3400:
3398:
3396:
3394:
3392:
3390:
3388:
3386:
3384:
3382:
3380:
3372:
3367:
3359:
3356:(in German).
3355:
3348:
3341:
3336:
3329:
3324:
3317:(4): 192–201.
3316:
3313:(in German).
3312:
3305:
3303:
3295:
3290:
3288:
3286:
3284:
3282:
3274:
3268:
3262:
3260:
3258:
3256:
3254:
3252:
3250:
3248:
3239:
3232:
3230:
3228:
3226:
3224:
3215:
3209:
3193:
3189:
3183:
3181:
3165:
3161:
3154:
3148:
3146:
3137:
3131:
3127:
3121:
3117:
3107:
3104:
3103:
3097:
3095:
3091:
3086:
3083:
3079:
3077:
3073:
3069:
3065:
3061:
3056:
3054:
3049:
3042:
3039:
3035:
3030:
3023:
3016:
3012:
3007:
3002:
2998:
2988:
2984:
2980:
2978:
2974:
2970:
2962:
2957:
2951:(– Hamburg) (
2950:
2946:
2942:
2939:
2935:
2930:
2923:
2919:
2915:
2911:
2907:
2904:
2899:
2892:
2888:
2884:
2880:
2876:
2872:
2869:
2868:
2867:
2860:
2851:
2848:
2844:
2840:
2838:
2834:
2823:
2819:
2816:
2814:
2810:
2806:
2800:
2796:
2783:
2776:
2767:
2766:
2758:
2751:
2742:
2741:
2733:
2726:
2723:
2722:
2713:
2705:
2702:
2693:
2692:
2684:
2677:
2668:
2667:
2659:
2652:
2649:
2648:
2639:
2631:
2622:
2620:
2609:
2595:
2591:
2589:
2579:
2575:
2572:
2566:
2562:
2560:
2556:
2552:
2547:
2544:
2535:
2529:
2524:
2515:
2512:
2508:
2506:
2502:
2498:
2494:
2490:
2480:
2471:
2468:
2465:
2461:
2457:
2453:
2449:
2445:
2441:
2437:
2435:
2431:
2421:
2417:
2415:
2411:
2405:
2402:
2397:
2393:
2389:
2385:
2381:
2372:
2370:
2366:
2361:
2358:
2354:
2350:
2346:
2342:
2338:
2333:
2330:
2325:
2316:
2312:
2310:
2306:
2303:502 with the
2302:
2298:
2294:
2289:
2285:
2281:
2275:
2269:Commissioning
2266:
2263:
2260:
2258:
2254:
2244:
2240:
2236:
2232:
2230:
2226:
2225:Deutsche Bahn
2222:
2213:
2205:
2196:
2194:
2193:DB ProjektBau
2190:
2186:
2183:
2181:
2176:
2172:
2170:
2166:
2163:(Munich) and
2162:
2156:
2152:
2150:
2146:
2143:
2138:
2135:
2131:
2128:
2123:
2121:
2116:
2112:
2103:
2099:
2095:
2091:
2089:
2084:
2081:
2077:
2073:
2069:
2065:
2061:
2057:
2055:
2051:
2047:
2036:
2033:
2030:
2029:
2021:
2018:
2015:
2014:
2010:
2007:
2004:
2003:
1999:
1997:250 km/h
1996:
1993:
1992:
1988:
1985:
1982:
1981:
1973:
1970:
1968:
1967:
1958:
1950:
1947:
1940:
1939:
1935:
1932:
1929:
1928:
1924:
1921:
1918:
1917:
1913:
1910:
1908:
1907:
1898:
1891:
1883:
1875:
1869:Route dispute
1866:
1862:
1855:
1852:
1848:
1844:
1840:
1836:
1832:
1828:
1824:
1819:
1815:
1814:
1813:
1802:
1798:
1795:
1792:
1789:
1786:
1785:
1781:
1778:
1775:
1772:
1769:
1768:
1764:
1761:
1758:
1755:
1752:
1751:
1747:
1744:
1741:
1738:
1735:
1734:
1731:questionable
1730:
1727:
1724:
1721:
1718:
1717:
1713:
1710:
1707:
1704:
1701:
1700:
1696:
1693:
1690:
1687:
1684:
1683:
1679:
1676:
1673:
1670:
1667:
1666:
1662:
1657:
1652:
1647:
1644:
1643:
1637:
1634:
1629:
1625:
1620:
1618:
1614:
1603:
1601:
1596:
1592:
1587:
1584:
1580:
1576:
1573:With the new
1571:
1564:
1560:
1555:
1546:
1544:
1538:
1536:
1532:
1526:
1524:
1520:
1516:
1512:
1508:
1504:
1500:
1485:
1482:
1480:
1476:
1472:
1463:
1459:
1455:
1453:
1449:
1445:
1439:
1437:
1433:
1427:
1425:
1421:
1417:
1413:
1408:
1405:
1400:
1392:
1388:
1383:
1379:
1376:
1367:
1363:
1361:
1357:
1353:
1349:
1344:
1342:
1337:
1329:
1325:
1320:
1313:
1308:
1299:
1296:
1293:
1291:
1285:
1283:
1279:
1275:
1270:
1268:
1264:
1260:
1256:
1252:
1248:
1244:
1240:
1222:
1221:
1214:
1212:
1210:
1208:
1206:
1204:
1202:
1201:
1197:
1191:
1182:
1180:
1177:
1174:
1166:
1157:
1155:
1152:
1148:
1142:
1126:
1124:
1121:
1116:
1107:
1098:
1096:
1093:
1088:
1079:
1070:
1068:
1065:
1060:
1051:
1042:
1040:
1037:
1032:
1023:
1014:
1012:
1009:
1004:
995:
986:
984:
981:
976:
964:
955:
953:
950:
944:
942:
939:
934:
925:
923:
920:
916:
903:
880:
878:
875:
870:
861:
852:
850:
847:
843:
831:
822:
820:
817:
812:
803:
794:
792:
789:
785:
772:
749:
747:
744:
739:
727:
718:
716:
713:
709:
698:
689:
687:
684:
679:
667:
658:
656:
653:
649:
637:
628:
626:
623:
618:
609:
600:
598:
595:
590:
578:
569:
567:
564:
559:
550:
541:
539:
536:
530:
528:
525:
520:
511:
509:
506:
502:
490:
481:
479:
476:
471:
459:
450:
448:
445:
441:
428:
405:
403:
400:
396:
390:
374:
372:
369:
365:
353:
344:
342:
339:
330:
321:
319:
316:
308:
292:
290:
287:
283:
276:
267:
265:
262:
258:
254:
252:
247:
245:
243:
240:
237:
236:
232:
228:
227:
224:
221:
220:
214:
213:
209:
205:
203:
199:
195:
191:
187:
186:15 kV/16.7 Hz
184:
182:
178:
174:
172:
168:
164:
140:1,435 mm
138:
136:
132:
128:
124:
120:
116:
111:
108:
105:
101:
95:
92:
91:
90:
86:
81:
78:
74:
71:
67:
63:
59:
56:
53:
49:
43:
39:
34:
30:
25:
20:
6524:
6512:
6471:High Speed 1
6455:Bothnia Line
6286:Milan–Verona
6213:
6093:Kerava-Lahti
5978:Ankara–Sivas
5894:Haramain HSR
5887:Saudi Arabia
5540:
5531:Halle–Erfurt
5526:Berlin–Halle
5471:
5462:
5434:
5412:. Retrieved
5408:Donau Kurier
5407:
5398:
5389:
5383:
5372:
5360:. Retrieved
5356:the original
5349:
5340:
5328:. Retrieved
5321:
5312:
5301:
5289:. Retrieved
5285:the original
5280:
5259:
5250:
5238:. Retrieved
5228:
5219:
5215:
5209:
5197:. Retrieved
5184:
5172:. Retrieved
5167:
5157:
5145:. Retrieved
5131:
5122:
5116:
5104:. Retrieved
5100:the original
5090:
5079:
5073:
5064:
5055:
5043:. Retrieved
5033:
5021:. Retrieved
5008:
4996:. Retrieved
4992:the original
4982:
4970:. Retrieved
4966:the original
4955:
4930:
4918:
4899:
4893:
4884:
4860:
4831:
4825:
4817:
4812:
4801:
4795:
4784:
4761:. Retrieved
4756:
4744:
4732:. Retrieved
4727:
4698:. Retrieved
4693:
4684:
4677:
4665:. Retrieved
4660:
4648:
4636:. Retrieved
4631:
4619:
4612:Weigelt 2006
4597:Weigelt 2006
4575:. Retrieved
4571:the original
4539:
4533:
4521:. Retrieved
4516:
4504:
4497:Weigelt 2006
4463:
4457:
4451:(in German).
4446:
4440:
4428:. Retrieved
4423:
4397:
4390:
4385:
4374:
4354:the original
4329:
4325:
4305:
4299:
4288:
4270:
4266:
4260:
4251:
4247:
4241:
4234:Weigelt 2006
4229:
4220:
4216:
4210:
4199:
4179:
4175:
4169:
4152:
4146:
4129:
4123:
4109:(6): 12–14.
4106:
4102:
4096:
4087:
4083:
4077:
4066:
4060:
4041:
4013:
4009:
3983:
3977:
3968:
3964:
3958:
3949:
3945:
3924:. Retrieved
3914:
3907:Weigelt 2006
3884:
3878:
3866:. Retrieved
3861:
3827:
3809:
3805:
3774:. Retrieved
3767:
3758:
3749:
3737:. Retrieved
3732:
3720:
3711:
3687:
3681:
3672:
3638:
3632:
3623:
3600:. Retrieved
3595:
3586:
3563:
3558:
3539:
3533:
3522:
3516:
3509:Weigelt 2006
3492:
3474:
3465:
3458:Weigelt 2006
3413:
3409:
3371:Weigelt 2006
3366:
3357:
3353:
3347:
3340:Weigelt 2006
3335:
3328:Weigelt 2006
3323:
3314:
3310:
3294:Weigelt 2006
3266:
3237:
3213:
3208:
3196:. Retrieved
3192:the original
3167:. Retrieved
3125:
3120:
3087:
3084:
3080:
3057:
3034:Škoda 109 E3
3021:
3019:
2985:
2981:
2969:ICE Sprinter
2966:
2865:
2849:
2845:
2841:
2829:
2820:
2817:
2801:
2797:
2793:
2628:
2615:
2612:Travel times
2606:
2603:Route length
2592:
2585:
2576:
2567:
2563:
2550:
2548:
2540:
2528:Hilpoltstein
2513:
2509:
2504:
2485:
2469:
2466:
2462:
2458:
2454:
2450:
2446:
2442:
2438:
2433:
2426:
2413:
2409:
2406:
2398:
2394:
2390:
2386:
2382:
2378:
2362:
2336:
2334:
2321:
2308:
2304:
2276:
2272:
2264:
2261:
2249:
2237:
2233:
2218:
2199:Construction
2188:
2187:
2184:
2177:
2173:
2157:
2153:
2139:
2124:
2119:
2117:
2113:
2109:
2100:
2096:
2092:
2085:
2070:
2066:
2062:
2058:
2053:
2049:
2042:
1989:210 km
1925:207 km
1863:
1860:
1811:
1626:of the then
1621:
1616:
1612:
1609:
1572:
1568:
1539:
1530:
1527:
1503:Gunzenhausen
1496:
1483:
1468:
1456:
1440:
1428:
1409:
1396:
1372:
1345:
1333:
1297:
1294:
1286:
1271:
1238:
1236:
222:
88:Route number
6419:Madrid–León
6311:Netherlands
6301:Turin–Milan
6296:Rome–Naples
6158:LGV Sud-Est
5904:South Korea
5596:Rome–Naples
5260:Donaukurier
5170:(in German)
4848:|work=
4394:1995 Teil I
3971:(1): 13–21.
3769:Der Spiegel
3360:(7/8): 505.
2430:TEN program
2341:Erwin Huber
2324:tunnel boom
1986:171 km
1922:171 km
1404:Autobahn 73
1259:A9 Autobahn
1115:Audi Tunnel
135:Track gauge
118:Line length
103:Operator(s)
61:Line number
41:Native name
6578:Ingolstadt
6547:Categories
5998:Uzbekistan
5955:Taiwan HSR
5825:Whoosh HSR
4540:Info-Brief
4153:Info-Brief
4130:Info-Brief
3992:62668166-3
3984:Info-Brief
3416:: 479–488.
3112:References
2977:Mittenwald
2826:Operations
2805:Oberstdorf
2799:Augsburg.
2724:Connection
2650:Connection
2380:Augsburg.
2229:Heinz Dürr
2142:karstified
2076:Heinz Dürr
1595:Autobahn 9
1511:Donauwörth
1507:Nördlingen
1479:block post
1387:Regensburg
1348:slab track
1341:Schwarzach
1336:Autobahn 9
1251:Ingolstadt
648:Eichelbach
5818:Indonesia
5459:Datasheet
4947:1221702-5
4939:0949-586X
4910:1421-2811
4850:ignored (
4840:cite book
4548:2668166-3
4161:2668166-3
4138:2668166-3
4115:0037-4997
4052:1421-2811
4022:0174-6979
3836:1264431-6
3812:(4): 216.
3649:1421-2811
3164:0722-8333
3082:traffic.
3076:class 101
3068:n-coaches
2973:Intercity
2879:Frankfurt
2875:Nuremberg
2505:Karwendel
2227:chairman
2005:Max grade
1994:Max speed
1559:class 110
1525:in 1840.
1284:(TEN-T).
1247:Nuremberg
1196:to Munich
216:Route map
113:Technical
6319:HSL-Zuid
6143:LGV Nord
3706:Ansbach.
3100:See also
2914:Hannover
2891:Dortmund
2833:line S 5
2169:Hochtief
1983:Distance
1919:Distance
1515:Augsburg
1420:Anlauter
1290:Augsburg
1117:(1258 m)
1089:(3289 m)
1061:(1320 m)
1033:(1925 m)
1005:(7260 m)
842:Anlauter
813:(7700 m)
619:(1333 m)
560:(2287 m)
158: in
36:Overview
6508:Oceania
6179:Germany
6128:LGV Est
6085:Finland
6067:Denmark
6033:Belgium
5695:Morocco
5679:Commons
5468:Article
5427:Sources
5414:24 July
5390:DB Welt
5362:23 July
5330:23 July
5291:23 July
5240:23 July
5199:23 July
5174:23 July
5147:23 July
5106:22 July
5045:22 July
5023:22 July
4998:22 July
4972:22 July
4945::
4763:20 July
4734:20 July
4700:20 July
4667:20 July
4638:20 July
4577:21 July
4546::
4523:20 July
4430:21 July
4159::
4136::
4010:Felsbau
3990::
3965:Felsbau
3926:18 July
3868:20 July
3834::
3776:18 July
3739:17 July
3602:21 July
3198:11 July
3169:11 July
3047:IRE 200
2945:Leipzig
2918:Hamburg
2883:Cologne
2835:of the
2809:Kempten
2598:Effects
2501:line 28
2493:line 41
2401:DB Netz
1827:Rednitz
1598:of the
1488:History
1424:Altmühl
1416:Greding
913:former
871:(650 m)
782:former
591:(141 m)
472:(104 m)
438:former
153:⁄
83:Service
77:Germany
73:Bavaria
55:DB Netz
6449:Sweden
6361:Russia
6347:Poland
6329:Norway
6244:Greece
6110:France
6024:Europe
5965:Turkey
5948:Taiwan
5688:Africa
5441:
4943:ZDB-ID
4937:
4931:[mobil
4908:
4544:ZDB-ID
4157:ZDB-ID
4134:ZDB-ID
4113:
4050:
4020:
3988:ZDB-ID
3832:ZDB-ID
3647:
3546:
3162:
3132:
2955:ICE 28
2949:Berlin
2928:ICE 25
2922:Bremen
2910:Kassel
2897:ICE 41
2871:Munich
2813:Lindau
2811:, and
2569:train
2305:RAILab
2280:ICE TD
2257:ICE TD
2019:31 min
2011:1.25%
1951:8 min
1948:31 min
1648:Length
1645:Option
1278:Line 1
1168:87.012
1109:85.023
1081:78.112
1053:76.019
1025:67.579
997:59.564
977:(79 m)
936:58.929
863:57.844
805:49.154
710:Lohen
611:40.537
552:29.002
522:25.447
231:Legend
223:
69:Locale
6385:Spain
6263:Italy
6057:HSL 4
6051:HSL 3
6046:HSL 2
6041:HSL 1
5835:Japan
5725:China
5193:(PDF)
5141:(PDF)
5017:(PDF)
4927:(PDF)
4753:(PDF)
4724:(PDF)
4690:(PDF)
4657:(PDF)
4628:(PDF)
4513:(PDF)
4420:(PDF)
4396:[
4357:(PDF)
4350:(PDF)
3858:(PDF)
3729:(PDF)
3592:(PDF)
3156:(PDF)
3038:Škoda
3011:Škoda
2961:ICE 4
2938:ICE 2
2934:ICE 1
2903:ICE 3
2887:Essen
2571:ICE S
2497:ICE T
2489:ICE 3
2329:ICE 3
2307:from
2293:ICE S
2022:7 min
1302:Route
946:375 m
905:~58.8
833:~57.7
669:~43.2
580:~33.6
532:390 m
492:~15.5
461:~15.0
430:~12.0
355:~10.6
332:9.440
280:from
51:Owner
6525:None
6513:None
5716:Asia
5439:ISBN
5416:2023
5364:2023
5332:2023
5293:2023
5242:2023
5201:2023
5176:2023
5149:2023
5108:2023
5047:2023
5025:2023
5000:2023
4974:2023
4935:ISSN
4906:ISSN
4852:help
4765:2023
4736:2023
4702:2023
4669:2023
4640:2023
4579:2023
4525:2023
4432:2023
4111:ISSN
4048:ISSN
4018:ISSN
3928:2023
3870:2023
3778:2023
3741:2023
3645:ISSN
3604:2023
3544:ISBN
3200:2023
3171:2023
3160:ISSN
3130:ISBN
3028:RE 1
2999:and
2588:Novo
2557:and
2375:Cost
2288:ER20
2286:and
2282:and
2165:Bögl
2127:ETCS
2118:The
2031:Cost
2008:2.0%
1930:Cost
1748:yes
1697:yes
1680:yes
1658:Cost
1650:(km)
1593:and
1577:and
1509:and
1471:cant
1436:Audi
1354:and
1324:A 73
1249:and
1237:The
966:59.4
776:,000
731:,000
700:42.4
680:2391
641:,000
501:A 73
257:elev
206:2.0%
64:5934
5470:at
5461:at
4271:129
3273:PDF
3009:A
2893:) (
2889:(-
2621:).
2559:PZB
2555:LZB
2499:on
2491:on
2301:120
2297:103
2284:218
2180:EDP
1799:no
1796:2.5
1790:180
1782:no
1779:2.6
1773:180
1765:no
1762:2.5
1756:174
1745:1.2
1739:205
1728:2.1
1722:191
1714:no
1711:2.6
1705:203
1694:1.7
1688:207
1677:2.4
1671:171
1619:).
1513:to
1328:A 9
1280:of
1265:at
774:~47
729:~46
639:~43
364:A 6
6549::
5406:.
5348:.
5320:.
5279:.
5268:^
5258:.
5220:70
5166:.
4941:.
4929:.
4869:^
4844::
4842:}}
4838:{{
4773:^
4755:.
4726:.
4710:^
4692:.
4659:.
4630:.
4604:^
4587:^
4556:^
4515:.
4475:^
4422:.
4406:^
4365:^
4338:^
4330:55
4316:^
4279:^
4252:50
4221:48
4188:^
4180:48
4107:98
4088:48
4030:^
4014:17
4000:^
3969:21
3950:52
3936:^
3893:^
3860:.
3844:^
3818:^
3810:48
3786:^
3766:.
3731:.
3696:^
3667:f.
3657:^
3612:^
3594:.
3572:^
3501:^
3483:^
3473:.
3422:^
3414:43
3378:^
3358:49
3315:52
3301:^
3280:^
3246:^
3222:^
3179:^
3144:^
3055:.
2947:–
2936:,
2920:/
2916:–
2912:–
2885:/
2881:–
2877:–
2873:–
2839:.
2815:.
2807:,
2784:40
2777:12
2759:36
2752:11
2706:4
2678:18
2371:.
2311:.
1823:B2
1793:19
1776:21
1759:24
1725:17
1708:15
1674:31
1557:A
1505:,
1269:.
968:00
907:00
835:00
738:St
708:Bk
702:00
678:St
671:00
582:00
494:00
463:00
432:00
357:00
249:km
160:)
75:,
6498:*
6410:*
6376:*
6370:*
6355:*
6254:*
6210:*
6189:*
6170:*
6101:*
6095:*
6053:*
5990:*
5940:*
5785:*
5735:*
5640:e
5633:t
5626:v
5500:e
5493:t
5486:v
5447:.
5418:.
5366:.
5334:.
5295:.
5244:.
5203:.
5178:.
5151:.
5110:.
5049:.
5027:.
5002:.
4976:.
4949:.
4912:.
4854:)
4767:.
4738:.
4704:.
4687:"
4671:.
4642:.
4581:.
4550:.
4527:.
4434:.
4163:.
4140:.
4117:.
4054:.
4024:.
3994:.
3930:.
3872:.
3838:.
3780:.
3743:.
3651:.
3606:.
3589:"
3552:.
3275:)
3202:.
3173:.
3138:.
3024:(
2963:)
2940:)
2924:(
2905:)
2703:7
2685:9
2428:(
1787:8
1770:7
1753:6
1742:7
1736:5
1719:4
1702:3
1691:8
1685:2
1668:1
1611:(
1565:.
1393:.
155:2
151:1
148:+
146:8
142:(
129:2
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.