Knowledge

High-speed railway track construction in France

Source đź“ť

275: 604:, riding on the rails, forces the stones underneath the sleepers. Each pass of this machine can raise the level of the track by 8 cm (3 in), so several passes of ballasting and of the machine are needed to build up a layer of ballast at least 32 cm (1 ft) thick under the sleepers. The ballast is also piled on each side of the track for lateral stability. The machine performs the initial alignment of the track. Next, a 283: 190: 22: 466:
underneath the gantry cranes. The cranes remove the panels of temporary track, and stack them onto the empty half of the sleeper train. Next, they pick up sets of 30 LGV sleepers, pre-arranged with the proper spacing (60 cm, or 24 in), using a special fixture. The sleepers are laid on the gravel bed where the panel track was. The sleeper train leaves the worksite loaded with sections of panel track.
243: 624:
Now that the first track is almost complete, work begins on the adjacent track. This time, however, it is not necessary to lay a temporary track. Trains running on the first track bring the sleepers, and then the rail, which is unloaded directly onto the sleepers by dispensing arms that swing out to
258:
on 27 September 1981. Contrary to its earlier fast services, SNCF intended TGV service for all types of passengers, with the same initial ticket price as trains on the parallel conventional line. To counteract the popular misconception that the TGV would be a premium service for business travellers,
465:
For the next step, a gantry crane is used again. This time, however, the crane rides on the two rails that were just laid alongside the temporary track. A train of flatcars, half loaded with LGV sleepers, arrives at the site. It is pushed by a special diesel locomotive, which is low enough to fit
167:
It is similar to the building of standard railway lines, but there are differences. In particular, construction process is more precise in order for the track to be suitable for regular use at 300 km/h (186 mph). The quality of construction was put to the test in particular during the
632:
masts need to be erected, and the wire strung on them. Once the catenary is complete, the track is given final alignment adjustments down to millimeter tolerances. The ballast is then blown to remove smaller gravel fragments and dust, which might be kicked up by trains. This step is especially
485:
is used to lift the rails onto their final position on the sleepers. This machine rides on the rails just like the gantry cranes, but can also support itself directly on a sleeper. By doing this, it can lift the rails, and shift them inwards over the ends of the sleepers, to the proper
569:, a weld shear and a grinder. When the thermite welding process is complete, the weld is ground to the profile of the rail, resulting in a seamless join between rail sections. Stress in the rail due to temperature variations is absorbed without 176:; the track was used at over 500 km/h (310 mph) without suffering significant damage. This contrasts with previous French world rail speed record (326/331 km/h in 1955) attempts which resulted in severe deformation of the track. 637:
trains are tested on the line at gradually increasing speeds. The track is qualified at speeds slightly higher than will be used in everyday operations (typically 350 km/h, or 210 mph), before being opened to commercial service.
437:
unloads the rail sections and places them on each side of the temporary track, approximately 3.5 m (12 ft) apart. This operation is usually carried out at night, for thermal reasons. The rail itself is standard
259:
SNCF started a major publicity campaign focusing on the speed, frequency, reservation policy, normal price, and broad accessibility of the service. This commitment to a democratised TGV service was enhanced in the
429:
of this first track. The rail comes from the factory in lengths varying from 200 m (660 ft) to 400 m (1310 ft). Such long pieces of rail are just laid across several
207: 39: 263:
era with the promotional slogan "Progress means nothing unless it is shared by all". The TGV was considerably faster (in terms of door to door travel time) than normal trains,
367:. TGV tracklaying then proceeds. The tracklaying process is not particularly specialized to high-speed lines; the same general technique is applicable to any track that uses 853: 348:
on each side of the trackbed, are constructed. Supply bases are established near the end of the high-speed tracks, where crews will form work trains to carry rail,
818: 813: 593:
pulled by diesel locomotives. Handling this train is challenging, since the ballast must be spread evenly. If the train stops, ballast can pile over the rails and
86: 58: 703: 65: 403:
track. These are laid roughly in the location where one of the tracks will be built (all LGVs have two tracks). Each panel is 18 metres (60 
474: 482: 371:. The steps outlined below are used around the world in modern tracklaying. TGV track, however, conforms to stringent requirements on materials, 72: 396: 54: 1002: 776: 781: 696: 1049: 1054: 79: 843: 473:, 2.4 m (7 ft 10 in.) wide, and weigh 245 kg (540 lb) each. They are equipped with hardware for 1059: 689: 797: 229: 105: 439: 211: 122: 43: 828: 823: 731: 625:
the proper alignment. The Nabla fasteners are secured, and the ballast is stuffed under the track as before.
459: 274: 1064: 570: 303: 1028: 848: 771: 712: 157: 553:
in the rail after it is joined into one continuous piece do not exceed certain limits, resulting in
838: 612:
machine shakes the track to perform the final tamping, effectively simulating the passing of 2,500
376: 200: 32: 368: 1069: 1023: 891: 886: 741: 169: 549:
Before the rail is joined, its length must be adjusted very accurately. This ensures that the
260: 746: 609: 404: 309: 477:, and a 9 mm (3/8 in.) rubber pad. (Rubber pads are always used under the rail on 1018: 901: 628:
The two tracks are now essentially complete, but the work on the line is not finished. The
8: 930: 470: 321: 633:
important on high-speed tracks, since the blast of a passing train is strong. Finally,
562: 161: 121:
This article was originally based on material from TGVweb, which is licensed under the
945: 896: 761: 969: 964: 672:
On The Fast Track: French Railway Modernisation and the Origins of the TGV, 1944–1983
657:
On The Fast Track: French Railway Modernisation and the Origins of the TGV, 1944–1983
605: 422: 337: 756: 308:, or LGV) begins with earthmoving. The trackbed is carved into the landscape, using 271:. The trains became widely popular, the public welcoming fast and practical travel. 550: 447: 913: 574: 527: 434: 287: 425:) can bring in the sections of continuous welded rail that will be used for the 991: 920: 726: 601: 543: 491: 400: 173: 1043: 869: 629: 586: 451: 426: 415: 681: 987: 940: 874: 833: 494:). It then lowers them onto the rubber sleeper cushions, and workers use a 443: 411: 349: 291: 766: 503: 360: 251: 153: 957: 935: 925: 594: 590: 495: 487: 455: 264: 214: in this section. Unsourced material may be challenged and removed. 469:
The sleepers, sometimes known as bi-bloc sleepers, are U41 twin block
952: 531: 433:; they are very flexible, so this does not pose a problem. A special 388: 372: 317: 268: 149: 282: 189: 148:
trains are to run, is prepared for their use, involving carving the
21: 881: 751: 558: 554: 530:
too quickly. Thermite is better suited to this job. It is a mix of
515: 478: 341: 329: 600:
A first layer of ballast is dumped directly onto the track, and a
736: 519: 430: 333: 499: 392: 356: 325: 313: 997: 908: 523: 345: 242: 589:
underneath the new track. The ballast arrives in a train of
613: 539: 535: 418:
is used at this stage, since the panel track is temporary.
408: 364: 255: 546:, and a great deal of heat, making it ideal to weld rail. 498:
machine to bolt down the Nabla clips with a predetermined
359:
is spread on the trackbed. This, after being compacted by
634: 566: 561:(in cold weather). The joining operation is performed by 145: 522:(using some type of flame) does not work well on large 421:
Once the panel track is laid, a work train (pulled by
250:
The first high-speed railway line outside of Japan,
608:distributes the ballast evenly. Finally, a dynamic 156:. This construction technique is used both for the 46:. Unsourced material may be challenged and removed. 585:The next step consists of stuffing a deep bed of 363:, provides an adequate surface for vehicles with 55:"High-speed railway track construction in France" 1041: 324:. All fixed structures are built; these include 514:The sections of rail are welded together using 663: 648: 711: 697: 538:(iron oxide) powder, which reacts to produce 135: 704: 690: 162:other TGV-based networks outside of France 619: 509: 297: 254:, opened to the public between Paris and 230:Learn how and when to remove this message 106:Learn how and when to remove this message 526:pieces such as rails, since the heat is 281: 273: 241: 278:TGV in Europe's high speed rail system. 1042: 565:process which is equipped with a rail 481:sleepers, to avoid cracking). Next, a 685: 352:and other supplies to the work site. 132:High-speed railway track construction 212:adding citations to reliable sources 183: 44:adding citations to reliable sources 15: 669: 654: 382: 344:facilities, most notably the large 13: 14: 1081: 580: 602:tamping-lining-levelling machine 188: 20: 573:, except near bridges where an 442:section, 60 kg/m (40  302:The work on a high-speed line ( 199:needs additional citations for 31:needs additional citations for 844:LGV Provence-Alpes-CĂ´te d'Azur 506:inward at a slope of 1 in 20. 1: 1050:Rail infrastructure in France 732:LGV Bretagne-Pays de la Loire 641: 246:French TGV network as of 2019 1055:Maintenance of way equipment 7: 863:Operators and rolling stock 475:Nabla RNTC spring fasteners 10: 1086: 807:Planned or projected lines 395:tires is used to lay down 179: 117: 1060:High-speed rail in France 1029:Transmission Voie-Machine 1011: 981:Adjacent high-speed lines 980: 862: 829:Paris – Normandy new line 824:LGV Montpellier–Perpignan 806: 790: 772:LGV Sud Europe Atlantique 719: 713:High-speed rail in France 454:per square millimetre or 387:To begin laying track, a 355:Next, a layer of compact 137:Lignes Ă  Grandes Vitesses 134:is the process by which 791:Line under construction 777:LGV Perpignan–Barcelona 142:high-speed railway line 1024:TGV track construction 819:LGV Interconnexion Sud 742:LGV Interconnexion Est 620:Finishing construction 510:Joining track sections 496:pneumatically operated 369:continuous welded rail 305:ligne Ă  grande vitesse 298:Preparing the trackbed 294: 279: 247: 170:TGV world speed record 144:"), the land on which 136: 854:LGV Toulouse–Narbonne 849:LGV Bordeaux–Toulouse 782:LGV NĂ®mes–Montpellier 407:) long, and rests on 285: 277: 245: 839:LGV Poitiers–Limoges 557:(in hot weather) or 208:improve this article 40:improve this article 1003:Perpignan–Barcelona 659:. pp. 209–210. 577:is sometimes used. 571:longitudinal strain 471:reinforced concrete 814:LGV Bordeaux–Spain 423:diesel locomotives 295: 280: 248: 158:French TGV network 1065:Rail technologies 1037: 1036: 970:Frecciarossa 1000 965:Trenitalia France 606:ballast regulator 240: 239: 232: 116: 115: 108: 90: 1077: 747:LGV MĂ©diterranĂ©e 720:Lines in service 706: 699: 692: 683: 682: 676: 675: 670:Meunier, Jacob. 667: 661: 660: 655:Meunier, Jacob. 652: 563:thermite welding 551:thermal stresses 502:. The rails are 448:tensile strength 383:Laying the track 340:, and the like. 235: 228: 224: 221: 215: 192: 184: 139: 111: 104: 100: 97: 91: 89: 48: 24: 16: 1085: 1084: 1080: 1079: 1078: 1076: 1075: 1074: 1040: 1039: 1038: 1033: 1007: 976: 914:Renfe Class 100 858: 802: 786: 762:LGV RhĂ´ne-Alpes 715: 710: 680: 679: 668: 664: 653: 649: 644: 622: 583: 575:expansion joint 518:. Conventional 512: 385: 322:heavy machinery 300: 236: 225: 219: 216: 205: 193: 182: 152:and laying the 129: 112: 101: 95: 92: 49: 47: 37: 25: 12: 11: 5: 1083: 1073: 1072: 1067: 1062: 1057: 1052: 1035: 1034: 1032: 1031: 1026: 1021: 1015: 1013: 1009: 1008: 1006: 1005: 1000: 995: 992:Channel Tunnel 984: 982: 978: 977: 975: 974: 973: 972: 962: 961: 960: 950: 949: 948: 943: 938: 933: 931:TGV Atlantique 928: 921:SNCF Voyageurs 918: 917: 916: 906: 905: 904: 899: 894: 889: 879: 878: 877: 875:ICE 3 Velaro D 866: 864: 860: 859: 857: 856: 851: 846: 841: 836: 831: 826: 821: 816: 810: 808: 804: 803: 801: 800: 798:LGV Lyon–Turin 794: 792: 788: 787: 785: 784: 779: 774: 769: 764: 759: 757:LGV Rhin-RhĂ´ne 754: 749: 744: 739: 734: 729: 727:LGV Atlantique 723: 721: 717: 716: 709: 708: 701: 694: 686: 678: 677: 662: 646: 645: 643: 640: 621: 618: 582: 581:Adding ballast 579: 544:aluminum oxide 528:conducted away 511: 508: 492:standard gauge 458:(116,000  391:that rides on 384: 381: 299: 296: 238: 237: 196: 194: 187: 181: 178: 174:LGV Atlantique 128: 127: 114: 113: 28: 26: 19: 9: 6: 4: 3: 2: 1082: 1071: 1070:Permanent way 1068: 1066: 1063: 1061: 1058: 1056: 1053: 1051: 1048: 1047: 1045: 1030: 1027: 1025: 1022: 1020: 1017: 1016: 1014: 1010: 1004: 1001: 999: 996: 993: 989: 986: 985: 983: 979: 971: 968: 967: 966: 963: 959: 956: 955: 954: 951: 947: 944: 942: 939: 937: 934: 932: 929: 927: 924: 923: 922: 919: 915: 912: 911: 910: 907: 903: 900: 898: 895: 893: 892:Eurostar e320 890: 888: 887:Eurostar e300 885: 884: 883: 880: 876: 873: 872: 871: 870:Deutsche Bahn 868: 867: 865: 861: 855: 852: 850: 847: 845: 842: 840: 837: 835: 832: 830: 827: 825: 822: 820: 817: 815: 812: 811: 809: 805: 799: 796: 795: 793: 789: 783: 780: 778: 775: 773: 770: 768: 765: 763: 760: 758: 755: 753: 750: 748: 745: 743: 740: 738: 735: 733: 730: 728: 725: 724: 722: 718: 714: 707: 702: 700: 695: 693: 688: 687: 684: 673: 666: 658: 651: 647: 639: 636: 631: 626: 617: 615: 611: 607: 603: 598: 596: 592: 588: 578: 576: 572: 568: 564: 560: 556: 555:lateral kinks 552: 547: 545: 541: 537: 533: 529: 525: 521: 517: 507: 505: 501: 497: 493: 489: 484: 483:rail threader 480: 476: 472: 467: 463: 461: 457: 453: 449: 446:/ft), with a 445: 441: 436: 432: 428: 427:permanent way 424: 419: 417: 413: 410: 406: 402: 401:prefabricated 398: 394: 390: 380: 378: 374: 370: 366: 362: 358: 353: 351: 347: 343: 339: 335: 331: 327: 323: 319: 315: 311: 307: 306: 293: 289: 284: 276: 272: 270: 266: 262: 257: 253: 244: 234: 231: 223: 213: 209: 203: 202: 197:This section 195: 191: 186: 185: 177: 175: 171: 165: 163: 159: 155: 151: 147: 143: 140:(LGV, litt. " 138: 133: 126: 124: 119: 118: 110: 107: 99: 88: 85: 81: 78: 74: 71: 67: 64: 60: 57: â€“  56: 52: 51:Find sources: 45: 41: 35: 34: 29:This article 27: 23: 18: 17: 1019:TGV stations 988:High Speed 1 834:LGV Picardie 674:. p. 7. 671: 665: 656: 650: 627: 623: 599: 584: 548: 513: 468: 464: 450:of 800  420: 389:gantry crane 386: 354: 338:game tunnels 304: 301: 292:Gare de Lyon 290:trainset at 249: 226: 220:January 2010 217: 206:Please help 201:verification 198: 172:runs on the 166: 141: 131: 130: 120: 102: 93: 83: 76: 69: 62: 50: 38:Please help 33:verification 30: 767:LGV Sud-Est 591:hopper cars 534:powder and 456:megapascals 252:LGV Sud-Est 1044:Categories 946:TGV RĂ©seau 936:TGV Duplex 642:References 377:tolerances 373:dimensions 320:and other 318:bulldozers 269:aeroplanes 261:Mitterrand 96:March 2016 66:newspapers 953:TGV Lyria 559:fractures 532:aluminium 150:track bed 902:TGV PBKA 882:Eurostar 752:LGV Nord 630:catenary 610:vibrator 516:thermite 479:concrete 431:flatcars 412:sleepers 350:sleepers 342:Drainage 334:culverts 330:flyovers 310:scrapers 958:TGV 2N2 941:TGV POS 926:TGV 2N2 897:TGV PBA 737:LGV Est 587:ballast 520:welding 452:newtons 416:ballast 361:rollers 346:ditches 326:bridges 314:graders 180:Service 80:scholar 595:derail 504:canted 500:torque 409:wooden 397:panels 393:rubber 357:gravel 288:Duplex 82:  75:  68:  61:  53:  1012:Other 998:HSL 1 990:(via 909:Renfe 614:axles 524:metal 488:gauge 435:crane 414:. No 365:tyres 267:, or 154:track 87:JSTOR 73:books 597:it. 540:iron 536:rust 405:feet 375:and 265:cars 256:Lyon 160:and 123:GFDL 59:news 635:TGV 567:saw 462:). 460:psi 440:UIC 399:of 210:by 146:TGV 42:by 1046:: 616:. 542:, 444:lb 379:. 336:, 332:, 328:, 316:, 312:, 286:A 164:. 994:) 705:e 698:t 691:v 490:( 233:) 227:( 222:) 218:( 204:. 125:. 109:) 103:( 98:) 94:( 84:· 77:· 70:· 63:· 36:.

Index


verification
improve this article
adding citations to reliable sources
"High-speed railway track construction in France"
news
newspapers
books
scholar
JSTOR
Learn how and when to remove this message
GFDL
TGV
track bed
track
French TGV network
other TGV-based networks outside of France
TGV world speed record
LGV Atlantique

verification
improve this article
adding citations to reliable sources
Learn how and when to remove this message

LGV Sud-Est
Lyon
Mitterrand
cars
aeroplanes

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.

↑