797:
final locomotive of the first batch, D6544, was delivered fourteen months later than the original delivery date. Delivery of the first of the second batch of locomotives was on 7 March. The committee met again in April. Although delivery of the second batch of locomotives was still on schedule for 7 July, by the time at Phase 2 of the electrification scheme was put into operation in June, there would be a shortfall of fifteen locomotives against the number required. When the committee met in May, delivery of the last of the second batch of locomotives had been put back to 15 July. The third batch would not start to be delivered until 23 February 1962, with completion by 31 March. The fourth batch was scheduled to be delivered between 23 January and 31 March 1962. The committee met again in July. Completion of the second batch of locomotives had been pushed back to 29 July. Start of deliveries of the third and fourth batches had been delayed, but final deliver dates remained the same. The
Electrification Committee met for the final time on 14 September. Delivery of the fourth batch had started; 69 locomotives had been delivered up to that date. As Phase 2 of the electrification scheme had been implemented, the Southern Region set up the Traction Committee, which met for the first time on 15 December. Eighty-one of the 85 Restriction 4 locomotives had been delivered, but the final locomotive was not now due for delivery until 12 January 1962. Delivery of the locomotives for the Hastings line was due to start a week later, and be complete by 6 April 1962. At that meeting discussion took place in respect of the annual mileage the fleet would accrue. The original estimate of 2,375,624 miles (3,823,196 km) had been revised upwards to 3,943,414 miles (6,346,310 km) but had then been revised down to 2,465,000 miles (3,967,000 km) due to the introduction of electric multiple units for most passenger trains and changes in freight requirements. This meant that only 70 locomotives would be needed, leaving 28 surplus to requirements. Reallocation of the surplus locomotives was discussed. BTC approval was needed for reallocation, although the BTC had the power to order the locomotives to be reallocated. They could have challenged the Southern Region as to why the order had not been amended. By this time, two locomotives had been transferred to the Eastern Region to work cement trains between
781:. The BTC approved the locomotives for the Hastings line in May, but deferred a decision on the other 21. These locomotives would cost ยฃ78,858 each. In July, the Electrification Committee expressed the view that the remaining locomotives should be ordered without delay. In August, there was concern that late deliveries would impact on driver training. The BTC approved the order of the final 21 locomotives in September at a cost of ยฃ78,380 each. In December, BRCW reported to the Electrification Committee that the first locomotive would not be delivered until 8 January 1960. The Electrification Committee met again on 14 January, and were told that the first locomotive would not be delivered until 22 January, with another in February and a total of 9 by 16 April. It was hoped that all forty-five locomotives of the first batch will have been delivered by October. The committee met again on 19 January. It was stated that the intention was that the second batch of locomotives would have been delivered by 11 September 1961. The third batch (for the Hastings line) were needed in service by June 1962. It was hoped that deliveries would begin in July 1961 and be completed in September. The first locomotive, numbered D6500, was delivered on 30 January.
793:. The committee met again in May. As delivery of all forty-five locomotives of the first batch was projected not to be completed until 31 January 1961, the closure of Ramsgate MPD was postponed. The committee was told that delays in the delivery of the third batch would mean that the replacement of steam on the Hastings line would have to be postponed. The committee met in June. It was agreed that Ramsgate MPD could close once thirty-five locomotives had been delivered. It was anticipated that this would be achieved by 30 November allowing the shed to closed on 1 December. By the time the Electrification Committee met on 10 November, thirty locomotives had been delivered. Consequently, Ramsgate MPD would not be able to be closed until at least 19 December. Delivery of the locomotives for the Hastings line was also likely to be delayed. When the committee met in December, the thirty-five locomotives had been delivered and permission was given for the closure of Ramsgate MPD. The BTC wanted to arrange a test of the ETH system fitted to the locomotives. It was agreed that a locomotive would be released at the end of January 1961 for three weeks.
821:, 36 steam locomotives could be withdrawn from service. The oil traffic was a new introduction, for which no provision had been made in the locomotive building programme. By the time then next meeting of the committee in March, some of the locomotives had been temporarily transferred to the South Western Division. The BTC were apprised of the situation in respect of the spare locomotives. It was stated that the new timetable due for introduction in June had a substantial reduction in freight, which had only been recently decided upon and could not have been foreseen when the locomotives were ordered. The BTC replied that they were concerned at the drastic cut in numbers required. They felt that the locomotives could be used following Stages 2 and 3 of the electrification programme. Another possibility was using the locomotives in the
1649:
the two types and in order to standardize and remove a maintenance risk, in the early 1980s, three battery-powered units were constructed which mounted on a standard lamp bracket with no need to draw power from the train. This allowed the power and control circuitry for warning units to be removed during (and thus simplifying) overhaul. The old power sockets were gradually removed and plated-over but some remained until withdrawal of the stock. These new warning units enabled other types of stock to use the tramway including Class 73 and Class 37 (on a railtour - which struggled with the tight curves of the tramway due to its three-axle bogies). These later warning units were smaller with an on/off switch on the rear of the unit and no bell โ warnings being given using the train horn.
1553:
1644:, trains operating over public thoroughfare tramway without escort are required to be fitted with warning equipment for the general public. Before its withdrawal, the Class 33 Weymouth pilot would regularly take fuel-oil tank wagons (for the ferries) and occasionally boat-train stock between Weymouth yard and ferry terminal. It had a bell and beacon fitted at both ends above the lower-centre headcode lamp (along with SR style high-level brake pipes) which served to warn thoroughfare users and was controlled from the cab. For main-line stock, two warning units were built and housed in a cabinet at the track side of the quay spur at the throat of the yard. This equipment comprised a yellow control box with amber rotating
770:
until 5 December. Under the terms of the tender, deliveries were to start 21 months from the placing of the order, and continue at three per month thereafter. This meant that the first locomotives would be delivered in
November 1959 and completed by February 1961. None of the locomotives would be in service for the planned start date of Phase 1 of the electrification plan. At their January 1958 meeting, the Electrification Committee heard that delivery of the locomotives would be calculated once all technical details had been agreed. One locomotive would be delivered 21 months thereafter, two the following month and three per month after that. This pushed back final delivery until March 1961.
1018:
826:
Sheffield scheme, but would put forward proposals that kept the locomotives on the
Southern Region. In March, the General Manager's department held a meeting to discuss the use of the locomotives on the Fawley oil trains. The Traction Committee met in April. They were told that the South Western Division had identified that the twenty-one locomotives could be used on the Fawley oil trains. A formal justification would be made to the BTC for the use of locomotives on the cement trains. This traffic was profitable and the contract had been negotiated on the basis that diesel locomotives would be used.
1625:
1664:. In addition, trains on the tramway were "walked" by railway staff with flags, clearing the route of people and badly parked cars all the way between the points at which the tramway reverted to conventional track at the quay station and road crossing into Weymouth yard. On arrival at the quay terminus the guard would move the warning equipment to the other end of the train in readiness for the return journey. In later years, (e.g. for Railtours) the local Police fulfilled the role of traffic control and the process of moving a train along the tramway became less routine.
1050:
1325:
1883:
1871:
33:
1341:
1071:
1057:
1265:, operated by Eastern Region crews north of Ferme Park. This enabled an earlier arrival at York and the overall scheduled timing to Uddingston to be met. Seven locomotives were allocated to this traffic, allowing one to be spare. Operating costs were ยฃ104 per train, about half that of using steam locomotives. The round trip took 44 hours. One of these trains, hauled by D6558, appeared in
964:
721:. By November, it was thought that 98 locomotives of 1,000 to 1,250 horsepower (750 to 930 kW) would be needed. That figure was based on the locomotives collectively achieving 2,375,624 miles (3,823,196 km) annually. The locomotives would be used on passenger, van and freight trains, as well as working inter-regional services. The
1584:, using a 6-coach rake of unpowered multiple unit coaches (designated TC, standing for Trailer Control). The use of this equipment removed the necessity for the locomotive to run around to the front of its train at each terminus, as it could be controlled from the driving position of a TC unit and hence could propel its train from the rear.
774:
delivery, the phasing out of steam locomotives would be delayed. It was agreed to push for the purchase of the second batch of 20 locomotives. The BTC discussed the purchase later that month, and agreed to accept BRCWs tender of ยฃ78,940 per locomotive. Eleven locomotives were to be delivered by
December 1960 and the rest by February 1961.
635:: locomotive-hauled passenger traffic depended on seasonal tourist traffic and was heavier in the summer, when carriage heating was not needed. In the winter, their expected use was to be for freight. Thus, they became the most powerful BR Bo-Bo diesel locomotive. The perennially unreliable steam heating boiler could also be avoided.
1653:
1528:
sets) could be relied upon to produce a push-pull set on
Sundays. Often, electric rosters would be substituted by class 33/1 + 4TC if the line was de-energised during engineering work. Indeed, push-pull sets were a possibility over the entire range of Southern Region services including inter-regional
1219:
With the introduction of the winter timetable in
September, the class were largely withdrawn from passenger service due to carriages still being heated by steam. Some trains were worked by steam locomotives and others by the Type 2 locomotives. Occasionally the class worked unheated passenger trains.
825:
area, where the order of a number of Type 3 locomotives had already been authorised. The locomotives lack of steam heating was a factor against their use however. The committee responded that the use following the implementation of Stages 2 and 3 held good. They appreciated the BTCs position over the
737:
to determine whether or not a locomotive in the 1,500 to 1,750 horsepower (1,120 to 1,300 kW) range could be built. On 4 December, a meeting between the
General and Assistant General Managers of the Southern Region and the BTCs Secretary-General, Chief Mechanical Engineer and a Technical member,
1648:
and bell which fitted on a bracket just above the rubbing plate on the cab front. Class 33/1 and all TC stock were equipped with this bracket and had a socket where units plugged-in to draw power from the train systems, similar to the RCH socket on coaching stock. This was a specific complexity with
1473:
The usual configuration was 4TC+4TC+Loco with the locomotive at the country end. Light traffic would result in 4TC+Loco, and in rare operational circumstances 4TC+Loco+4TC was noted. This combination was not preferred, as it led to operational difficulties and inconvenience to waiting passengers who
926:
Electrically, the main traction generator was separate from the heating generator, although both were built mechanically as part of the same machine. A third auxiliary generator of 57 kW was arranged similarly, to provide a supply for the traction motor cooling blowers, pumps, brake exhausters
769:
electrical equipment and Sulzer engines. Deliveries were to start in April 1959, with thirty locomotives in service by June. Despite offering a cheaper locomotive and better delivery times, English
Electric did not gain the order. The BTC approved the order on 26 September. The order was not placed
1477:
The Class 33/1 with one or two 4TC sets (normally with the Class 33/1 at the country end of the train) were also the mainstay of the
Waterloo โ Salisbury service from their introduction. Platform congestion and the lack of facilities at the very busy Basingstoke station were two of the reasons for
842:
and four to the Cliffe cement traffic. The use of the locomotives on the South
Western Division would allow the withdrawal of forty-nine steam locomotives and a loss of thirty-five jobs. A meeting of Southern Region officials on 16 July discussed the exact information that the BTC required for the
1615:
They settled into sterling service, proving themselves highly useful and reliable. The prototype locomotive (D6580, later 33119) was the only member of Class 33 to run in green livery with the multiple unit control equipment โ not to be confused with preserved members of Class 33/1 that have been
1315:
and pairs, of 33 + 24, became common on winter passenger services. This resulted in unpopular, complex run-round manoeuvres at termini as the Class 24 needed to be coupled inside to provide steam heat. Emergency provisioning of through-piping for steam heat on some examples of class 33 alleviated
796:
The Electrification Committee met in February 1961. Delivery of the first of the second batch of locomotives was due to start on 24 February and be complete by 7 July. The third batch was due to be delivered between 8 December and 23 February 1962 and the fourth batch by the end of June 1962. The
773:
In February 1958, the BTC approved the purchase of thirty-four Type 2 locomotives, but deferred a decision on 51 others due to be built in 1959, including twenty needed for Phase 2 of the electrification programme. In November, the Electrification Committee was informed that due to the delays in
713:, which had not featured in any previous electrification proposals. Phase 2 would cover the remainder of the South Eastern section routes that were to be electrified. The initial assessment was that eighty-eight 1,000 horsepower (750 kW) and twenty 2,000 horsepower (1,500 kW) Bo-Bo
843:
permanent reallocation of the spare locomotives. The issue would be discussed at a Board meeting of the Southern Region to be held on 6 September. The Western Region had reservations about the locomotives working the Fawley oil trains single-headed. A test with a 1,000-ton train between
754:. of the plan at a social event. Vickers-Armstrong was the builder of Sulzer engines in the United Kingdom. The company was not happy with the situation and a protest was made. In February 1957, the BTC decided to put the process for the procurement of the new locomotives out to tender.
728:
By April 1956, it was apparent that the new locomotives would not be powerful enough, as the Southern Region was intent on eliminating the steam heating of its trains in favour of electric train heating (ETH). As an interim, it was intended that fifteen 1,160 horsepower (870 kW)
918:
The electrical heating system worked at a DC voltage of 800 V, with a generator capacity of 235 kilowatts (315 hp). As this was early days for ETH on BR, standards were not yet clear and there was a possibility in this region of a future need to heat continental stock from
784:
The Electrification Committee met again on 10 March, when they were told that only thirteen of the twenty locomotives of the first batch would be in service by June, although it was hoped that all forty-five would be in service by October. Concerns were expressed that Ramsgate
1240:
between 13 and 17 February. Phase 2 of the electrification scheme came into service on 12 June 1961. The last of the second batch of locomotives, D6564, was delivered on 28 July. Delivery of the fourth batch of locomotives took place between 18 August and 12 January 1962.
1523:
Class 33/1 and 4TC combinations were often used to supplement other services and were not just the purview of Bournemouth-Weymouth trains. Services could be rostered for a push-pull set due to stock shortages โ the Reading to Basingstoke service (normally a stronghold of
829:
A meeting between the Southern and Eastern Regions on 31 May resulted in a decision that only four locomotives would be needed to work the cement trains. The Central Division had identified that the three spare locomotives could be used on freight trains between
1316:
this somewhat. The Southern Region was unaccustomed to the operational overhead and maintenance associated with the use of Class 24s and they rapidly became unpopular. With the advent of modern stock and warmer seasons, they were returned to the Midland Region.
761:. Tenders were returned to the Electrification Committee in July 1957. The committee made its recommendations to the BTC, which met on 8 August. The BTC discussed an order for forty-five locomotives at a cost of ยฃ76,970 each. They were to be built by the
1611:
With the advent of TOPS, Class 34 was originally reserved for these modified locomotives - but it was not used and they were grouped, instead, into class 33/1 and the nineteen locomotives were renumbered, sequentially, in the range 33101โ33119.
812:
The Traction Committee met again in January 1962. With seven locomotives allocated to the cement trains, work had to be found for the remaining 21. If these locomotives were allocated to the South Western Division to work tank trains from
1587:
Following successful completion of trials, D6580 and a further eighteen other members of the class (D6511, D6513, D6514, D6516, D6517, D6519, D6520, D6521, D6525, D6527, D6528, D6529, D6531, D6532, D6533, D6535, D6536 and D6538) entered
987:. This required the bodies to be reduced in width to avoid clipping tunnel linings on that line, leading to their nickname of 'Slim Jims'. These locomotives were 8 feet 8 inches (2.64 m) wide over the steps and 8 ft
1256:
cement trains. These trains comprised 30 wagons, with a train weight of 1,050 tons. A pair of locomotives hauled the trains from Cliffe to Ferme Park, just north of King's Cross. Haulage of the train was then taken over by Eastern or
1469:
and Weymouth by Class 33/1. On the return leg, the locomotive propelled the train back to Bournemouth where it would be attached to a waiting London-bound 4REP and the locomotive detached to await the next Weymouth-bound portion.
1685:, hauled by D6506, overran signals and collided with it. The wreckage from the accident piled up under the bridge carrying the B2160 Maidstone Road. The line was blocked for 12 hours. D6506 was severely damaged. It arrived at
1817:
On 20 April 1989 locomotive number 33107 collided with the rear of a freight train at Holton Heath, between Wareham and Hamworthy Junction, according to television news the driver of 33107 was killed as he jumped from the
2759:
For the purpose of this article, the four batches are listed in the order that they were approved by the BTC. Batch 1 comprises D6500โ44, batch 2 comprises D6545โ64, batch 3 comprises D6586โ97 and batch 4 comprises
700:
established an Electrification Committee, which met monthly from August 1955. On the South Eastern section, electrification was to be carried out in two phases. Phase 1 would cover the north Kent routes via
757:
To enable Phase 1 of the electrification to be implemented in June 1959, forty-five diesel locomotives would be needed. In addition, fifteen Type 2 locomotives (later class 24) would be loaned by the
1481:
In later years Weymouth boat trains, conveying passengers between London and the Channel Islands ferry service out of Weymouth, were handed over to push-pull operation. The section of route from
1001: in (2.48 m) over the body. Originally numbered D6586 to D6597, they were later renumbered 33201 to 33212. These locomotives were fitted with slow-speed control to enable them to work
6010:
1656:
The bell and beacon unit for tramway operation, fitted to the rubbing plate and plugged into the train systems via a small connector on the front of all class 33/1 and TC multiple units
733:
locomotives would be allocated to the Southern Region. The Electrification Committee informed the BTC of their requirements in October, advising them that they had been in contact with
6005:
1261:
locomotives. It was soon found that these locomotives were unable to keep to the schedule demanded. The Southern Region agreed that their locomotives could work the train as far as
6000:
1280:
The third batch of locomotives was delivered between 2 February and 12 May 1962. In April, three locomotives were transferred to the South Western Division to work oil trains from
923:. Both two pole and single pole systems were supported; two pole becoming the standard on BR but some continental stock using a single pole system with return through the rails.
838:. The BTC met on 29 June to consider the reallocation of the spare locomotives. Fifteen were to be allocated to the Fawley oil traffic, nine to cross-London freight traffic from
1520:, little more than a high-powered shunter equivalent. The Type 3 power of Class 33/1 with only a 4 or 8 car train was rarely into the recovery margin of a schedule due to load.
947:
they became class 33/0 and the surviving locomotives, excluding the 19 that were converted for push-pull operation, were renumbered 33 001โ33 065. The locomotives were built to
665:
The locomotives were initially needed, unusually, because of an electrification scheme. The 'Kent Coast scheme' was one of five major electrification schemes put forward by the
1493:, following (and largely in the middle of) the harbour road. The quay spur did not pass through the station, but diverged westwards at the throat thus it was not possible for
1580:
to make it compatible with Multiple Unit stock. Commencing 21 July 1965 tests were carried out between Wimbledon Park and Basingstoke and then, from 17 January 1966, on the
1516:
Although class 73 and 74 electro-diesel locomotives had push-pull capability, they did not have the endurance for longer runs on diesel power โ their 600/650HP was not even
930:
Avoiding the weight of the boiler and its water and fuel supplies allowed the diesel fuel capacity to be increased from 500 gallons to 800 gallons, compared to the Type 2s.
1608:
with full yellow ends. D6521 had re-entered service by November 1966, so equipped, and by November 1967 the remainder had returned to traffic fitted for push-pull working.
1810:). Fifteen people were injured, but only the driver of the freight train seriously. 33032 was stored at Frome West stone terminal and on 4 June 1987 it was hauled back to
871:
works. The underframe and bodysides form an integral superstructure. The cabs are double skinned, with driving controls both sides to make shunting easier. The roof is of
1862:. Two more carriages had been added to the train by that summer. 83301 was withdrawn in November 1994. It was stripped of parts and then scrapped in the summer of 1996.
650:
locomotives, their bodywork and cab ends were of all steel construction. They were very similar in appearance to Class 26 locos, but carried Southern Region two-digit
1162:. A new timetable was introduced on 13 June. There were twelve locomotives available, enough to enable the class to be introduced to passenger trains, including the
6025:
1517:
851:
on 31 July had been successful. The Western Region had agreed that these trains could be worked single-handed by 12 September, when the Traction Committee met.
6086:
927:
etc. The electrical rating for traction power was the same whether heating was in use or not, but the excess engine power now became available for traction.
6081:
5832:
1715:, West Sussex and was in a rear-end collision with a freight train. Two people were killed. Damage was so extensive that the locomotive was cut up on site.
746:
policy in force at the time, but was done as it was thought that this would be the quickest way to acquire the locomotives. A few days later, BTC Chairman
6020:
1102:
4794:
1508:
The locomotive swap at Bournemouth (for both up and down trains) was eliminated and services were greatly improved with the removal of the troublesome
129:
6015:
3976:
1636:
in August 1981. Note the bell and beacon warning unit on the cab front and the platform height air brake pipes with two rolled flags wedged behind.
747:
890:, Lancashire. It has eight cylinders of 280 mm bore by 360 mm stroke and develops 1,550 horsepower (1,160 kW) at 750 rpm. A Sulzer
6076:
6071:
6066:
5647:
5587:
5333:
5328:
5283:
5273:
5228:
5208:
5108:
1719:
762:
639:
73:
1799:. The crew of the passenger train had failed to protect the rear of their train, Twelve people were injured. The locomotive was written off.
685:
would work passenger services. The scheme involved the electrification of 250 route miles (400 km) of track at a cost of approximately
1465:. At Bournemouth the train would be divided with the 4REP remaining at the London end of Bournemouth station and the 4TCs hauled onward to
1831:
works. It was fitted with bogies that had third rail collection shoes. The locomotive was renumbered 83301. A test train formed of 83301,
1049:
3787:
4049:
1780:
On 25 February 1979, locomotive No. 33115 was hauling a passenger train which was involved in a collision with an engineers' crane near
631:
and fitting a larger 8 cylinder version of the previous 6 cylinder engine. This was possible because of the traffic requirements of the
789:(MPD) would not be able to close by 14 November as planned. Its site was needed for the construction of a new maintenance facility for
5923:
3859:
2723:. This was based upon the earlier Lima model that Hornby acquired upon purchasing the liquidated assets of the Lima company in 2003.
1770:
On 11 September 1975, locomotive No. 33041 was involved in a collision at Bricklayers Arms Junction and was consequently written off.
1312:
758:
1405:
6051:
1258:
1377:
3697:"Report on the Collision that occurred on 25th February 1979 between Hilsea and Fratton in the Southern Region British Railways"
4787:
1942:
1875:
1358:
1233:
6030:
5842:
5672:
5521:
5511:
5238:
5218:
4206:
1384:
777:
In February 1959, the Electrification Committee discussed a third batch of 33 locomotives, including 12 suitable to work the
1718:
On 30 September 1966, locomotive D6535 was hauling a freight train that overran signals and was derailed by trap points at
1604:
electro-diesels and indeed any electro-pneumatically controlled (EP) multiple unit stock. They emerged, painted in the new
1530:
4304:
1859:
1454:
1155:
867:. The cabs were altered slightly, with the centre section housing a two figure route indicator. They were built at BRCWs
864:
844:
697:
632:
617:
501:
5806:
3810:"Railway Accident at Holton Heath: A Report on a Collision that occurred on 20 April 1989 :: The Railways Archive"
1887:
1806:. Locomotive No. 33032 was hauling a passenger train that was in a head-on collision with the freight train (hauled by
1391:
1245:
1237:
1221:
818:
505:
1552:
1501:
its train on arrival at the sea-terminal. The move to push-pull sets on boat trains removed two headaches for the SR:
882:
and brakes on all wheels. The handbrake works on the inner set of wheels of each bogie. The engine is a Sulzer 8LDA28
4780:
4602:
4575:
4548:
4521:
4494:
4468:
4427:
4408:
4389:
4351:
4323:
4285:
4266:
4244:
4225:
4187:
4160:
4141:
3430:
3390:
2556:
1424:
1307:
which passenger carriages largely used. Early delivery problems and a shortage of steam locomotives resulted in many
971:
A batch of twelve locomotives was built with narrow bodies, to allow them to work through the narrow tunnels between
951:, which was the normal standard and equivalent to British Railways standard C1 restriction. All 86 locomotives were
5562:
2853:
1992:
1201:
3722:
1568:
electrification was expanding on the Southern region, it was not then considered to be justified to extend beyond
1497:
to call at Weymouth station. Boat trains had been made up of conventional coaching stock and the locomotive would
1373:
5801:
5677:
1534:
1478:
class 33/1 operation throughout the route rather than just over the non-electrified section west of Basingstoke.
1442:
1329:
1229:
1159:
1026:
972:
702:
3540:
5918:
5358:
4449:
4437:
4370:
3885:
1660:
Trains for the quay would halt at the station throat, and the warning equipment was attached and tested by the
1362:
1213:
1193:
4772:
4628:. Derby: British Railways Board. October 1984. pp. 18โ19, 36, 88โ90 (per pdf) – via Barrowmore MRG.
1437:
The mainstay of push-pull operations was the operation over the then un-electrified track from Bournemouth to
5984:
1633:
1209:
1142:
D6500 entered service on 30 January 1960. D6501 on 28 February and D6502/3/4 in March. On 2 April, D6502 and
682:
1017:
4620:
1674:
1525:
1173:
722:
690:
193:
5837:
5426:
5406:
5243:
5223:
5133:
5128:
2430:
1577:
1569:
1457:
to Bournemouth. The consist was normally twelve cars made up of a powerful 3,200 hp (2,400 kW)
1185:
3972:
1056:
6056:
1693:
1541:
1450:
1304:
628:
613:
1773:
On 11 October 1977, locomotives No. 33036 and 33043 were hauling a freight train that was derailed at
6061:
1851:
1760:
1697:
1682:
1285:
1189:
1181:
831:
4461:
British Railways Locomotives and Multiple Units including Preserved Locomotives 1977 Combined Volume
5893:
5491:
5486:
5386:
5376:
5072:
5062:
5057:
5052:
5002:
4997:
4992:
4917:
2680:
2604:
2550:
2291:
2048:
1970:
1641:
1629:
1482:
1438:
1398:
976:
872:
298:
5827:
5047:
5037:
5032:
5027:
5017:
5007:
4977:
4967:
4947:
4937:
4927:
4912:
4820:
3936:
3911:
3823:
3622:
3488:
2580:
2482:
2212:
1847:
1738:
1708:
1351:
1151:
835:
706:
666:
3696:
943:
All 86 of the first delivery were built as standard locomotives, numbered D6500 to D6585. Under
646:
electrical equipment installed in them. Like their lower-powered BRCW sisters, the Class 26 and
623:
They were produced as a more powerful Type 3 (1,550 bhp) development of the 1,160 bhp
5878:
5735:
5725:
4023:
3761:
2402:
2074:
1749:
1462:
1458:
1293:
1022:
848:
790:
651:
38:
1544:
services during a stock shortage in 1999 and worked the service for some weeks without issue.
5968:
5947:
5942:
5888:
5873:
5822:
5796:
5791:
5786:
5770:
5765:
5760:
5755:
5745:
5740:
5720:
5715:
5710:
5705:
5700:
5695:
5667:
5662:
5657:
5652:
5642:
5637:
5632:
5627:
5617:
5612:
5607:
5602:
5597:
5592:
5582:
5577:
5572:
5567:
5541:
5536:
5531:
5526:
5516:
5506:
5501:
5496:
5471:
5466:
5461:
5456:
5451:
5446:
5441:
5436:
5431:
5421:
5416:
5411:
5401:
5396:
5353:
5348:
5343:
5338:
5323:
5318:
5313:
5308:
5303:
5298:
5293:
5288:
5278:
5268:
5263:
5258:
5253:
5248:
5233:
5213:
5203:
5198:
5183:
5178:
5173:
5168:
5163:
5158:
5153:
5148:
5143:
5138:
5123:
5118:
5113:
5103:
5098:
5093:
5088:
5067:
5042:
5022:
5012:
4987:
4982:
4972:
4962:
4957:
4952:
4942:
4932:
4880:
4875:
4870:
4865:
4860:
4855:
4850:
4845:
4840:
4835:
4830:
4825:
4815:
3809:
2456:
2320:
2239:
1891:
1839:
1832:
1807:
1726:
1624:
1601:
1597:
1509:
1474:
found themselves confronted with the side of the locomotive when their train drew to a halt.
1466:
1308:
1266:
1197:
1143:
860:
751:
743:
730:
647:
624:
303:
4133:
3623:"Report on the Collision that occurred on 4th January 1969 between Paddock Wood and Marden"
3422:
2838:
2177:
2160:
1490:
1262:
1002:
734:
510:
669:. Under Stage 1 of the scheme, the majority of railway lines east of a line drawn between
8:
5913:
5557:
2736:
2630:
2184:
2108:
2042:
718:
526:
1827:
In May 1991, locomotive 33115 was converted to a test locomotive in connection with the
1741:. The locomotive was withdrawn in November 1968 and was cut up for spares in March 1969.
1540:
Although in private ownership at the time, 33103 and 4TC 417 were spot-hired for use on
418:
5952:
5883:
5868:
5863:
5391:
5381:
4922:
4907:
4902:
2374:
2348:
2206:
1730:
1205:
1006:
952:
899:
786:
766:
670:
643:
580:
538:
374:
4107:
3998:
3863:
1787:
On 26 January 1985, locomotive 33104 ran into the rear of a passenger train formed of
1759:
On 28 July 1971, locomotive No. 6561 was hauling a parcels train that was derailed at
4729:
4721:
4702:
4694:
4687:
Dunn, Pip (18 June โ 1 July 1997). "The small locomotive with the big personality!".
4675:
4667:
4648:
4640:
4608:
4598:
4581:
4571:
4554:
4544:
4527:
4517:
4500:
4490:
4464:
4445:
4423:
4404:
4385:
4366:
4347:
4319:
4300:
4281:
4262:
4240:
4221:
4202:
4183:
4166:
4156:
4137:
4089:
4081:
3426:
3386:
3327:
2220:
1936:
1796:
1745:
1441:
and the service continued like this across three decades. Weymouth trains started at
1225:
1030:
903:
887:
714:
1324:
5908:
5903:
5898:
2267:
1692:
On 23 March 1963, locomotive D6520 was hauling a freight that was derailed between
1115:
739:
531:
378:
344:
311:
4689:
4662:
4635:
4054:
2740:
2716:
2528:
1998:
1811:
1777:, London. Due to damage sustained, 33036 was withdrawn from service and scrapped.
1734:
1686:
1593:
1589:
1573:
1281:
814:
435:
337:
1882:
5858:
5750:
5730:
4802:
1870:
1828:
1498:
1300:
879:
710:
686:
465:
362:
324:
316:
177:
3973:"Class 33 33103 pictured in engineers grey on the Ecclesbourne Valley Railway"
3833:
3482:
543:
D15/1, D15/2; 15/6, 15/6A; Class 33, Class 34 (reserved, not used), Class 83/3
6045:
4733:
4725:
4698:
4671:
4644:
4612:
4093:
4085:
3331:
2732:
2700:
2342:
2261:
1855:
1784:. One person was killed in the accident. 33115 was out of traffic until 1980.
1744:
On 4 January 1969, locomotive No. D6558 was hauling a parcels train that was
984:
980:
948:
883:
778:
678:
677:
would be electrified. On secondary and branch lines not electrified, such as
469:
448:
444:
369:
4752:
4706:
4679:
4660:
Hypher, John (October 1984). "Cromptons far and wide - Occasionally slim!".
4652:
4585:
4558:
4531:
4504:
4170:
2804:
1802:
On 24 March 1987, a freight train overran a signal at Frome North Junction,
955:
6. Two accident-damaged locomotives were withdrawn before TOPS took effect.
1712:
1678:
1249:
907:
895:
891:
798:
497:
382:
199:
3322:
Marsden, Colin J (November 1985 โ January 1986). "The Southern Type 3's".
1547:
207:
1661:
1652:
1168:
806:
514:
149:
1725:
On 16 October 1968, locomotive D6576 was involved in a collision with a
1461:
electric multiple unit on the rear with two leading units of un-powered
1365: in this section. Unsourced material may be challenged and removed.
32:
4716:
3726:
1774:
1581:
1565:
1494:
1446:
1253:
1147:
920:
802:
674:
1707:
On 5 March 1964, locomotive D6502 was hauling a freight train when it
4767:
4254:
2719:
started to sell the BR Class 33 in its Railroad range in BR Green in
2656:
2424:
2152:
2128:
2100:
1964:
1701:
1605:
1172:. The class was also introduced to service of freight trains between
1070:
868:
822:
280:
266:
4762:
1340:
1284:, Hampshire. Initially, they were used on trains between Fawley and
1228:
on 17 and 18 February in connection with a committee meeting of the
3762:"Report on the Collision that occurred on 24th March 1987 at Frome"
2728:
2720:
2712:
2704:
1803:
422:
272:
258:
4714:
Jones, Ben; Dent, George (January 2008). "Masterclass: Class 33".
5933:
4747:
3828:
2708:
2313:
1673:
At 02:02 on 8 December 1961, a freight train was setting back at
1289:
910:
and can work in multiple with any other "blue star" locomotives.
839:
518:
2836:"Type "3" Diesel Electric Locomotives for the Southern Region".
875:. Bogies are identical to those used on the Sulzer Type 2, with
2724:
2396:
1781:
1764:
1645:
4335:
Ultimate Allocations, British Railways Locomotives 1948 โ 1968
4080:. No. 33. Hersham: Ian Allan Publishing. pp. 82โ83.
591:
3 still in service, 24 preserved, 2 stored, remainder scrapped
4622:
Vehicle Diagram Book No. 100 for Main Line Diesel Locomotives
1177:
610:
276:
262:
218:
142:
4379:
963:
4893:
4803:
British railway locomotives and miscellany, 1948 to present
4720:. No. 113. Peterborough: EMAP Active. pp. 28โ35.
1792:
1788:
1753:
1486:
944:
4753:
Southern E-Group (SEMG) โ Class 33 details and photographs
1628:
33109 arrives at the ferry terminal having negotiated the
1244:
In November 1961, D6569 and D6559 were transferred to the
293:
800 imp gal (3,600 L; 960 US gal)
4758:
South East Locomotive Group โ owners of 33063 & 33065
4757:
1843:
1557:
958:
876:
551:
D6500โD6597; later 33001โ33065, 33101โ33 119, 33201โ33212
4693:. No. 307. EMAP Apex Publications. pp. 20โ25.
3741:
3451:
3151:
1505:
The necessity for the run-round at the quay was removed.
1296:. It worked a freight train back to Eastleigh that day.
4458:
3824:"Holton Heath Train Crash, Poole 1989 & Rail Crane"
3759:
3591:
3579:
3567:
3399:
3350:
3326:. No. 11. Weybridge: Ian Allan Ltd. pp. 4โ6.
3305:
3303:
3301:
3274:
3250:
3238:
3202:
3178:
3168:
3166:
3139:
3129:
3127:
3114:
3112:
3099:
3097:
3095:
3080:
3070:
3068:
3053:
3043:
3041:
3039:
3024:
3014:
3012:
3010:
3008:
3006:
2993:
2991:
2989:
2974:
2964:
2962:
2960:
2945:
1548:
Conversions โ Class 33/1 โ push-pull fitted locomotives
3664:
3640:
3512:
Locospotters Annual 1966 - By Push-pull to Bournemouth
3487:. The Rank Organisation. 1963. Event occurs at 8:05.
3338:
3286:
2891:
2889:
2876:
2874:
725:
approved the electrification scheme in February 1956.
285:
Class 33/2 โ 74.4 long tons (76 t; 83 short tons)
239:
Class 33/0 and 33/1: 9 ft 3 in (2.82 m)
3840:
3652:
3383:
British Railways Locomotives & Other Motive Power
2935:
2933:
2908:
2906:
2904:
2192:
Pioneer Locomotive Diesel Group, Barrow Hill BR Blue
967:
33208 in BR civil engineers livery at Eastleigh, 1995
657:
The original (1957) number sequence was D6500โD6597.
16:
Class of 98 BoโฒBoโฒ 1550hp diesel-electric locomotives
3725:. Network South East Railway Society. Archived from
3694:
3676:
3603:
3555:
3463:
3439:
3362:
3298:
3262:
3226:
3214:
3190:
3163:
3124:
3109:
3092:
3065:
3036:
3003:
2986:
2957:
2918:
2782:
1572:
and so, in 1965, D6580 was fitted with experimental
938:
642:(BRCW) and they were known as "Cromptons" after the
2886:
2871:
1874:D6501 runs round the train at Buckfastleigh on the
1795:unit 7395 which had been halted by a landslip near
627:. This was achieved, quite simply, by removing the
4633:Kelly, Peter (February 1983). "Workaday wonders".
2930:
2901:
817:to various destinations in the London Midland and
4639:. EMAP National Publications. pp. 4โ5, 7โ9.
4076:Wild, Mike (March 2010). "Class 33 from Heljan".
6043:
3380:
3785:
1180:. They were allowed to haul 500-ton trains via
913:
902:CG391-B1. The locomotives are fitted with dual
742:to build the locomotives. This was against the
4666:. EMAP National Publications. pp. 34โ39.
3788:"Q16.08 โ Accident-damaged Diesel Locomotives"
3529:. Tonbridge. 15 December 1961. pp. 1, 10.
1592:, to be fitted with a modified version of the
1288:. In late April, a locomotive worked a Fawleyโ
4788:
4514:The Class 33's: A Celebration of Thirty Years
4380:Stevens-Stratten, S.W.; Carter, R.S. (1978).
4346:(Fifth ed.). Shepperton: Ian Allan Ltd.
1898:Twenty-nine locomotives have been preserved.
1529:trains; they were not infrequent visitors to
763:Birmingham Railway Carriage and Wagon Company
640:Birmingham Railway Carriage and Wagon Company
241:Class 33/2: 8 ft 8 in (2.64 m)
74:Birmingham Railway Carriage and Wagon Company
6087:Diesel-electric locomotives of Great Britain
4748:71A Locomotive Group - Owners of D6515/33012
3321:
2831:
2829:
2827:
2825:
693:(BTC) approved the scheme in February 1956.
212:39 ft 0 in (11.89 m)
6082:Standard gauge locomotives of Great Britain
4566:Marsden, Colin J.; Fenn, Graham B. (1988).
4565:
4130:British Railways Locoshed Book 1974 edition
4050:"Hornby makes bid for failed Italian rival"
3790:. Railway Correspondence and Travel Society
4795:
4781:
3720:
1667:
83:DEL92โDEL156, DEL169-DEL189, DEL157-DEL168
4713:
4568:British Rail Main Line Diesel Locomotives
4442:Sulzer Diesel Locomotives of British Rail
3518:
2846:
2822:
1425:Learn how and when to remove this message
4487:Locomotive Profile: Class 33 'Cromptons'
4459:Williams, Alan; Percival, David (1977).
4360:
4275:
4155:. Chessington: Southern Electric Group.
4150:
3714:
3646:
3514:. Shepperton: Ian Allan. pp. 27โ33.
3509:
3381:Williams, Alan; Percival, David (1974).
3356:
3344:
3292:
1881:
1869:
1651:
1623:
1551:
1323:
1016:
962:
933:
863:locomotives that BRCW had built for the
4592:
4570:. Sparkford: Haynes. pp. 132โ141.
4538:
4417:
4398:
4313:
3747:
3658:
2799:
2797:
1319:
1303:was fitted, rather than the ubiquitous
1232:. The locomotive hauled trains between
6077:Railway locomotives introduced in 1965
6072:Railway locomotives introduced in 1962
6067:Railway locomotives introduced in 1960
6044:
4659:
4511:
4484:
4316:Motive power recognition:1 Locomotives
4294:
4234:
4215:
4196:
4177:
3937:"Bluebell Railway Locomotives - D6570"
3846:
3760:Department of Transport (6 May 1988).
3721:McCrickard, John P (16 October 2016).
3688:
3682:
3615:
3609:
3597:
3585:
3573:
3561:
3457:
3445:
3405:
3368:
3309:
3280:
3268:
3256:
3244:
3232:
3220:
3208:
3196:
3184:
3172:
3157:
3145:
3133:
3118:
3103:
3086:
3074:
3059:
3047:
3030:
3018:
2997:
2980:
2968:
2951:
2939:
2924:
2912:
2895:
1576:apparatus, high-level brake pipes and
959:Class 33/2 โ narrow-bodied locomotives
4776:
4632:
4363:Modern Railways Pictorial Annual 1986
4341:
4253:
4127:
4047:
3916:Pioneer Diesels Locomotive Group Page
3886:"71A's Class 33 D6515 back in action"
3753:
3670:
3533:
3491:from the original on 21 December 2021
3469:
3385:. Shepperton: Ian Allan. p. 36.
2880:
1132:
4768:Pioneer Diesel Group Owners of 33035
4686:
4436:
4299:. Manchester: Crรฉcy Publishing Ltd.
4075:
3786:Paul Chancellor (20 February 2019).
3779:
2842:. April 1960. pp. 238โ241, 246.
2794:
2788:
2769:Not including the traincrew's wages.
1363:adding citations to reliable sources
1334:
1311:locomotives being borrowed from the
1220:D6504 was used for ETH tests on the
616:, ordered in 1957 and built for the
4763:Cromptons โ BR Class 33 Locomotives
4332:
3961:. No. August 2022. p. 80.
3475:
2854:"Kent Coast Electrification Scheme"
1737:and examination, it was considered
1021:A pair of 33s - D6527 and D6505 at
898:is fitted. The main generator is a
865:Scottish Region of British Railways
618:Southern Region of British Railways
231:50 ft 9 in (15.47 m)
188:3 ft 7 in (1,090 mm)
13:
4478:
4297:The Class 33s A Sixty Year History
3979:from the original on 29 April 2021
2703:produced a Class 33, initially in
1677:station when the 00:20 goods from
1596:apparatus โ fully compatible with
1222:Eastern Region of British Railways
859:The locomotives were based on the
249:12 ft 8 in (3.86 m)
223:10 ft 0 in (3.05 m)
14:
6098:
4741:
3912:"Heritage Diesel Locomotive Hire"
3832:. 25 January 2020. Archived from
3767:. Her Majesty's Stationery Office
3628:. Her Majesty's Stationery Office
3324:Modern Railways Pictorial Profile
2694:
2688:BR Green (Yellow Warning Panels)
2006:BR Green (Yellow Warning Panels)
1978:BR Green (Yellow Warning Panels)
1619:
1273:, part of its documentary series
1196:. On 17 July, locomotives D6506,
939:Class 33/0 โ standard locomotives
3892:. No. July 2022. p. 29
2661:Operational, Mainline Certified
2133:Operational, Mainline Certified
2105:Operational, Mainline Certified
1339:
1069:
1055:
1048:
886:, built by Vickers-Armstrong at
638:A total of 98 were built by the
31:
6052:British Rail diesel locomotives
4220:. Cheltenham: Peter Nicholson.
4199:Diesels and Electrics for scrap
4100:
4069:
4041:
4028:Hornby Railways Collector Guide
4016:
3991:
3965:
3950:
3929:
3904:
3878:
3852:
3816:
3802:
3503:
3411:
3374:
3315:
2763:
2753:
1902:Table of preserved locomotives
1865:
1814:, where it was later broken up.
1350:needs additional citations for
4541:Rail Portfolios: The Cromptons
4382:British Rail Main-Line Diesels
4048:Reece, Damian (9 March 2004).
3543:. British Pathรฉ. December 1961
3525:"Rail Crash: Inquiry begins".
3419:British Railways Locoshed Book
1012:
683:diesel electric multiple units
1:
4595:Diesel Retrospective:Class 33
4463:. Shepperton: Ian Allan Ltd.
4384:. Shepperton: Ian Allan Ltd.
4365:. Shepperton: Ian Allan Ltd.
4318:. Shepperton: Ian Allan Ltd.
3541:"Train crash at Paddock Wood"
2809:Southern Railway E-mail Group
2776:
2181:(Name not Currently Carried)
1746:run into by a passenger train
1512:locomotive from the equation.
1483:Weymouth to the ship terminal
1208:for rail joint tests between
717:would be needed, plus twenty
679:Tonbridge โ West St. Leonards
660:
515:English, Welsh & Scottish
456:26,000 lbf (116 kN)
42:
2356:Railfreight Mainline Sector
1038:Distribution of locomotives,
914:Electric Train Heating (ETH)
723:British Transport Commission
691:British Transport Commission
7:
6026:Departmental multiple units
4403:. Redruth: Atlantic Books.
4344:Southern Electric 1909-1979
4261:. Redruth: Atlantic Books.
4182:. Southampton: Kingfisher.
4151:Beecroft, Geoffrey (1986).
4003:Lima British HO Locomotives
2612:BR Blue (Full Yellow Ends)
2431:Ecclesbourne Valley Railway
1846:set 8007 were used between
1184:, dropping to 460 tons via
614:diesel-electric locomotives
609:or Crompton, is a class of
430:1,215 hp (906 kW)
406:85 mph (140 km/h)
10:
6103:
4337:. Wirral. Michael McManus.
4314:Marsden, Colin J. (1981).
4280:. Penryn: Atlantic Books.
4201:. Penryn: Atlantic Books.
4153:The Hastings Diesels Story
3723:"January 1982 to May 1986"
3695:HM Railways Inspectorate.
2379:Undergoing heavy overhaul
1888:Kidderminster Town station
1835:London Chamber of Commerce
1791:units 7754 & 7703 and
1689:for repair on 29 December.
1005:. All 12 locomotives were
738:it was agreed to approach
6011:Miscellaneous locomotives
5993:
5977:
5961:
5932:
5851:
5815:
5779:
5686:
5550:
5367:
5081:
4889:
4808:
4418:Vaughan, Adrian (2003) .
4401:Trains in Trouble: Vol. 2
4278:Trains in Trouble: Vol. 7
4259:Trains in Trouble: Vol. 4
4112:www.class33crompton.co.uk
1560:unit from Weymouth, 1987.
1124:
1044:
854:
654:between the cab windows.
587:
576:
555:
547:
537:
489:
484:
480:
460:
434:
410:
402:
397:
393:
368:
358:
343:
333:
323:
310:
297:
289:
253:
245:
235:
227:
216:
206:
192:
184:
148:
139: โข Commonwealth
138:
127:
118:
113:
109:
95:
87:
79:
69:
61:
56:
52:
30:
23:
4399:Trevena, Arthur (1981).
4361:Morrison, Brian (1985).
3425:. 1974. pp. 24โ25.
2746:
2739:) produce a Class 33 in
2681:Battlefield Line Railway
2605:Battlefield Line Railway
2551:Hertfordshire Rail Tours
2328:BR Green (Yellow Front)
2292:Battlefield Line Railway
2247:BR Green (Yellow Front)
2049:Battlefield Line Railway
1971:Battlefield Line Railway
1822:
1733:. Following recovery to
1642:Weymouth Harbour Tramway
1630:Weymouth Harbour Tramway
1033:oil train in March 1964.
873:glass reinforced plastic
6021:Electric multiple units
4539:Marsden, Colin (2005).
4444:. David & Charles.
4276:Earnshaw, Alan (1991).
4197:Butlin, Ashley (2015).
2858:Southern Electric Group
2581:East Lancashire Railway
2483:East Lancashire Railway
2213:East Lancashire Railway
2025:Undergoing Restoration
1975:Undergoing Restoration
1668:Accidents and incidents
1533:and have been noted at
1374:"British Rail Class 33"
791:electric multiple units
667:1955 Modernisation Plan
620:between 1960 and 1962.
4593:Vaughan, John (2008).
4516:. Runpast Publishing.
4422:. Hersham: Ian Allan.
4342:Moody, G. T. (1979) .
4295:Lilley, Simon (2020).
4216:Denton, Brian (1981).
2478:Captain Bill Smith RNR
2403:Churnet Valley Railway
2075:Churnet Valley Railway
1895:
1879:
1739:uneconomical to repair
1657:
1640:Allocated to work the
1637:
1561:
1449:electric traction via
1332:
1301:electric train heating
1224:. It was exhibited at
1034:
968:
6016:Diesel multiple units
4512:Hypher, John (1991).
4485:Cooper, B.K. (1990).
4235:Glover, John (2001).
4178:Bishop, Bill (1984).
2727:make BR Class 33s in
2699:Italian manufacturer
2557:Great Central Railway
2457:Severn Valley Railway
2321:West Somerset Railway
2240:West Somerset Railway
2217:Stored (spares Loco)
2157:Stored (spares loco)
2096:Glen Falloch / Sultan
1892:Severn Valley Railway
1885:
1873:
1713:Itchingfield Junction
1655:
1627:
1555:
1327:
1271:High, Wide and Faster
1267:The Rank Organisation
1020:
1003:merry-go-round trains
966:
934:New-build locomotives
759:London Midland Region
752:Vickers-Armstrong Ltd
744:competitive tendering
26:British Rail Class 33
6006:Electric locomotives
4024:"Hornby BR Class 33"
3890:Railways Illustrated
3527:Tonbridge Free Press
3510:Jeffries, M (1966).
3484:High Wide and Faster
2839:The Railway Magazine
2664:West Coast Railways
2509:Undergoing Overhaul
2161:Direct Rail Services
2136:West Coast Railways
2056:DCE Grey and Yellow
1531:Bristol Temple Meads
1359:improve this article
1320:Push-pull operations
1292:oil train as far as
1259:North Eastern Region
735:Sulzer Brothers Ltd.
719:electric locomotives
629:steam heating boiler
605:, also known as the
511:Direct Rail Services
4128:Allan, Ian (1974).
3866:on 29 February 2008
3836:on 5 December 2021.
2737:Bachmann Industries
2685:Undergoing Repairs
2631:Mid Norfolk Railway
2585:Undergoing Repairs
2317:(Name not Carried)
2185:Wensleydale Railway
2109:West Coast Railways
1943:South Devon Railway
1903:
1876:South Devon Railway
1860:Dover Western Docks
1709:ran through signals
1556:33102 propelling a
1234:London King's Cross
1156:Dover Western Docks
1125:Withdrawn (1964โ68)
1041:
750:told a director of
748:Sir Brian Robertson
527:West Coast Railways
398:Performance figures
363:Electric Train Heat
6001:Diesel locomotives
5082:Main-line diesels:
4420:Tracks to Disaster
4333:McManus, Michael.
3999:"Lima BR Class 33"
3702:. Railways Archive
3460:, pp. 29, 31.
3160:, pp. 39, 41.
2626:Dennis G. Robinson
2512:Departmental grey
2506:On a private site
2438:BR Engineers Grey
2375:Spa Valley Railway
2349:Spa Valley Railway
2022:On a private site
1901:
1896:
1880:
1731:Reading, Berkshire
1658:
1638:
1562:
1542:Barking-Gospel Oak
1333:
1299:Only the then new
1238:Edinburgh Waverley
1206:Brighton Main Line
1037:
1035:
1007:route availability
969:
953:route availability
900:Crompton Parkinson
787:Motive Power Depot
767:Crompton Parkinson
715:diesel locomotives
644:Crompton Parkinson
581:Route availability
519:Fragonset Railways
329:DC traction motors
271:Class 33/1 โ 77.6
257:Class 33/0 โ 73.8
6057:Bo-Bo locomotives
6039:
6038:
6031:Steam locomotives
5962:Steam locomotives
5843:Other Series
5368:Main-line diesels
4237:Southern Electric
4208:978-0-906899-27-4
4108:"Crompton Models"
3957:"Running Lines".
3750:, pp. 10โ11.
3673:, pp. 44โ45.
3600:, pp. 85โ87.
3588:, pp. 83โ85.
3576:, pp. 65โ68.
3408:, pp. 24โ25.
3283:, pp. 24โ25.
3259:, pp. 20โ21.
3247:, pp. 18โ30.
3211:, pp. 42โ43.
3187:, pp. 41โ42.
3148:, pp. 38โ39.
3089:, pp. 32โ33.
3062:, pp. 30โ31.
3033:, pp. 29โ30.
2983:, pp. 10โ11.
2954:, pp. 8, 10.
2791:, pp. 43โ45.
2692:
2691:
2221:South West Trains
1993:Lt Jenny Lewis RN
1950:BR Two-Tone Grey
1886:33108 pulls into
1797:Popham, Hampshire
1616:repainted green.
1606:BR corporate blue
1435:
1434:
1427:
1409:
1226:Stratford, London
1204:were used on the
1192:and 450 tons via
1140:
1139:
888:Barrow-in-Furness
601:The British Rail
599:
598:
595:
594:
562:(All locomotives)
532:heritage railways
476:
475:
389:
388:
354:33/1 SR MU System
105:
104:
6094:
6062:BRCW locomotives
4797:
4790:
4783:
4774:
4773:
4737:
4710:
4683:
4656:
4629:
4627:
4616:
4589:
4562:
4535:
4508:
4474:
4455:
4433:
4414:
4395:
4376:
4357:
4338:
4329:
4310:
4291:
4272:
4250:
4231:
4212:
4193:
4174:
4147:
4116:
4115:
4104:
4098:
4097:
4073:
4067:
4066:
4064:
4062:
4045:
4039:
4038:
4036:
4034:
4020:
4014:
4013:
4011:
4009:
3995:
3989:
3988:
3986:
3984:
3969:
3963:
3962:
3954:
3948:
3947:
3945:
3943:
3933:
3927:
3926:
3924:
3922:
3908:
3902:
3901:
3899:
3897:
3882:
3876:
3875:
3873:
3871:
3862:. Archived from
3856:
3850:
3844:
3838:
3837:
3820:
3814:
3813:
3806:
3800:
3799:
3797:
3795:
3783:
3777:
3776:
3774:
3772:
3766:
3757:
3751:
3745:
3739:
3738:
3736:
3734:
3718:
3712:
3711:
3709:
3707:
3701:
3692:
3686:
3680:
3674:
3668:
3662:
3656:
3650:
3644:
3638:
3637:
3635:
3633:
3627:
3619:
3613:
3607:
3601:
3595:
3589:
3583:
3577:
3571:
3565:
3559:
3553:
3552:
3550:
3548:
3537:
3531:
3530:
3522:
3516:
3515:
3507:
3501:
3500:
3498:
3496:
3479:
3473:
3467:
3461:
3455:
3449:
3443:
3437:
3436:
3415:
3409:
3403:
3397:
3396:
3378:
3372:
3366:
3360:
3354:
3348:
3342:
3336:
3335:
3319:
3313:
3307:
3296:
3290:
3284:
3278:
3272:
3266:
3260:
3254:
3248:
3242:
3236:
3230:
3224:
3218:
3212:
3206:
3200:
3194:
3188:
3182:
3176:
3170:
3161:
3155:
3149:
3143:
3137:
3131:
3122:
3116:
3107:
3101:
3090:
3084:
3078:
3072:
3063:
3057:
3051:
3045:
3034:
3028:
3022:
3016:
3001:
2995:
2984:
2978:
2972:
2966:
2955:
2949:
2943:
2937:
2928:
2922:
2916:
2910:
2899:
2893:
2884:
2878:
2869:
2868:
2866:
2864:
2850:
2844:
2843:
2833:
2820:
2819:
2817:
2815:
2801:
2792:
2786:
2770:
2767:
2761:
2757:
2268:Bluebell Railway
2082:Post Office Red
1904:
1900:
1430:
1423:
1419:
1416:
1410:
1408:
1367:
1343:
1335:
1073:
1059:
1052:
1042:
1036:
1000:
999:
995:
992:
740:English Electric
709:, including the
530:Various British
482:
481:
395:
394:
351:
180:
174:
170:
168:
167:
163:
160:
111:
110:
98:
54:
53:
47:
44:
35:
21:
20:
6102:
6101:
6097:
6096:
6095:
6093:
6092:
6091:
6042:
6041:
6040:
6035:
5989:
5973:
5957:
5928:
5847:
5811:
5775:
5688:
5682:
5546:
5369:
5363:
5077:
4891:
4890:Diesel shunters
4885:
4809:Diesel shunters
4804:
4801:
4744:
4663:Rail Enthusiast
4636:Rail Enthusiast
4625:
4619:
4605:
4578:
4551:
4524:
4497:
4481:
4479:Further reading
4471:
4452:
4430:
4411:
4392:
4373:
4354:
4326:
4307:
4306:978-191080-9662
4288:
4269:
4247:
4228:
4218:Southern Survey
4209:
4190:
4163:
4144:
4119:
4106:
4105:
4101:
4078:Hornby Magazine
4074:
4070:
4060:
4058:
4055:The Independent
4046:
4042:
4032:
4030:
4022:
4021:
4017:
4007:
4005:
3997:
3996:
3992:
3982:
3980:
3971:
3970:
3966:
3956:
3955:
3951:
3941:
3939:
3935:
3934:
3930:
3920:
3918:
3910:
3909:
3905:
3895:
3893:
3884:
3883:
3879:
3869:
3867:
3858:
3857:
3853:
3845:
3841:
3822:
3821:
3817:
3808:
3807:
3803:
3793:
3791:
3784:
3780:
3770:
3768:
3764:
3758:
3754:
3746:
3742:
3732:
3730:
3729:on 26 June 2018
3719:
3715:
3705:
3703:
3699:
3693:
3689:
3681:
3677:
3669:
3665:
3657:
3653:
3645:
3641:
3631:
3629:
3625:
3621:
3620:
3616:
3608:
3604:
3596:
3592:
3584:
3580:
3572:
3568:
3560:
3556:
3546:
3544:
3539:
3538:
3534:
3524:
3523:
3519:
3508:
3504:
3494:
3492:
3481:
3480:
3476:
3468:
3464:
3456:
3452:
3444:
3440:
3433:
3417:
3416:
3412:
3404:
3400:
3393:
3379:
3375:
3367:
3363:
3355:
3351:
3343:
3339:
3320:
3316:
3308:
3299:
3291:
3287:
3279:
3275:
3267:
3263:
3255:
3251:
3243:
3239:
3231:
3227:
3219:
3215:
3207:
3203:
3195:
3191:
3183:
3179:
3171:
3164:
3156:
3152:
3144:
3140:
3132:
3125:
3117:
3110:
3102:
3093:
3085:
3081:
3073:
3066:
3058:
3054:
3046:
3037:
3029:
3025:
3017:
3004:
2996:
2987:
2979:
2975:
2967:
2958:
2950:
2946:
2938:
2931:
2927:, pp. 7โ8.
2923:
2919:
2911:
2902:
2894:
2887:
2879:
2872:
2862:
2860:
2852:
2851:
2847:
2835:
2834:
2823:
2813:
2811:
2803:
2802:
2795:
2787:
2783:
2779:
2774:
2773:
2768:
2764:
2758:
2754:
2749:
2743:(1/148 scale).
2741:British N gauge
2717:Hornby Railways
2697:
2529:Swanage Railway
2272:Under overhaul
1999:Swanage Railway
1919:Current Status
1868:
1825:
1812:Eastleigh Works
1735:Eastleigh Works
1687:Eastleigh Works
1670:
1622:
1590:Eastleigh Works
1550:
1443:London Waterloo
1431:
1420:
1414:
1411:
1368:
1366:
1356:
1344:
1330:London Waterloo
1322:
1282:Fawley Refinery
1152:London Victoria
1083:
1082:
1081:
1080:
1079:
1078:
1074:
1066:
1065:
1064:
1060:
1039:
1027:Bromford Bridge
1015:
997:
993:
990:
988:
983:was designated
973:Tunbridge Wells
961:
941:
936:
916:
880:roller bearings
857:
819:Western Regions
815:Fawley Refinery
698:Southern Region
663:
652:headcode blinds
633:Southern Region
625:Type 2 Class 26
577:Axle load class
568:
563:
529:
525:
521:
517:
513:
509:
506:Eastern Regions
496:
466:long tons-force
452:
436:Tractive effort
426:
353:
349:
338:Diesel electric
325:Traction motors
284:
270:
240:
176:
172:
165:
161:
158:
156:
155:4 ft
154:
120:
96:
65:Diesel-electric
57:Type and origin
48:
45:
25:
17:
12:
11:
5:
6100:
6090:
6089:
6084:
6079:
6074:
6069:
6064:
6059:
6054:
6037:
6036:
6034:
6033:
6028:
6023:
6018:
6013:
6008:
6003:
5994:
5991:
5990:
5988:
5987:
5981:
5979:
5975:
5974:
5972:
5971:
5965:
5963:
5959:
5958:
5956:
5955:
5950:
5945:
5939:
5937:
5930:
5929:
5927:
5926:
5921:
5916:
5911:
5906:
5901:
5896:
5891:
5886:
5881:
5876:
5871:
5866:
5861:
5855:
5853:
5849:
5848:
5846:
5845:
5840:
5835:
5830:
5825:
5819:
5817:
5813:
5812:
5810:
5809:
5804:
5799:
5794:
5789:
5783:
5781:
5777:
5776:
5774:
5773:
5768:
5763:
5758:
5753:
5748:
5743:
5738:
5733:
5728:
5723:
5718:
5713:
5708:
5703:
5698:
5692:
5690:
5684:
5683:
5681:
5680:
5675:
5670:
5665:
5660:
5655:
5650:
5645:
5640:
5635:
5630:
5625:
5620:
5615:
5610:
5605:
5600:
5595:
5590:
5585:
5580:
5575:
5570:
5565:
5560:
5554:
5552:
5548:
5547:
5545:
5544:
5539:
5534:
5529:
5524:
5519:
5514:
5509:
5504:
5499:
5494:
5489:
5484:
5479:
5474:
5469:
5464:
5459:
5454:
5449:
5444:
5439:
5434:
5429:
5424:
5419:
5414:
5409:
5404:
5399:
5394:
5389:
5384:
5379:
5373:
5371:
5365:
5364:
5362:
5361:
5356:
5351:
5346:
5341:
5336:
5331:
5326:
5321:
5316:
5311:
5306:
5301:
5296:
5291:
5286:
5281:
5276:
5271:
5266:
5261:
5256:
5251:
5246:
5241:
5236:
5231:
5226:
5221:
5216:
5211:
5206:
5201:
5196:
5191:
5186:
5181:
5176:
5171:
5166:
5161:
5156:
5151:
5146:
5141:
5136:
5131:
5126:
5121:
5116:
5111:
5106:
5101:
5096:
5091:
5085:
5083:
5079:
5078:
5076:
5075:
5070:
5065:
5060:
5055:
5050:
5045:
5040:
5035:
5030:
5025:
5020:
5015:
5010:
5005:
5000:
4995:
4990:
4985:
4980:
4975:
4970:
4965:
4960:
4955:
4950:
4945:
4940:
4935:
4930:
4925:
4920:
4915:
4910:
4905:
4899:
4897:
4887:
4886:
4884:
4883:
4878:
4873:
4868:
4863:
4858:
4853:
4848:
4843:
4838:
4833:
4828:
4823:
4818:
4812:
4810:
4806:
4805:
4800:
4799:
4792:
4785:
4777:
4771:
4770:
4765:
4760:
4755:
4750:
4743:
4742:External links
4740:
4739:
4738:
4711:
4684:
4657:
4630:
4617:
4603:
4590:
4576:
4563:
4549:
4536:
4522:
4509:
4495:
4480:
4477:
4476:
4475:
4469:
4456:
4450:
4434:
4428:
4415:
4409:
4396:
4390:
4377:
4371:
4358:
4352:
4339:
4330:
4324:
4311:
4305:
4292:
4286:
4273:
4267:
4251:
4245:
4232:
4226:
4213:
4207:
4194:
4188:
4175:
4161:
4148:
4142:
4132:. Shepperton:
4124:
4123:
4118:
4117:
4099:
4068:
4040:
4015:
3990:
3964:
3949:
3928:
3903:
3877:
3851:
3849:, p. 158.
3839:
3815:
3801:
3778:
3752:
3740:
3713:
3687:
3675:
3663:
3651:
3639:
3614:
3602:
3590:
3578:
3566:
3554:
3532:
3517:
3502:
3474:
3472:, p. 143.
3462:
3450:
3438:
3431:
3421:. Shepperton:
3410:
3398:
3391:
3373:
3361:
3359:, p. 115.
3349:
3337:
3314:
3297:
3285:
3273:
3261:
3249:
3237:
3225:
3213:
3201:
3189:
3177:
3162:
3150:
3138:
3123:
3108:
3091:
3079:
3064:
3052:
3035:
3023:
3002:
2985:
2973:
2956:
2944:
2929:
2917:
2900:
2885:
2883:, p. 125.
2870:
2845:
2821:
2793:
2780:
2778:
2775:
2772:
2771:
2762:
2751:
2750:
2748:
2745:
2696:
2695:Model railways
2693:
2690:
2689:
2686:
2683:
2678:
2675:
2672:
2666:
2665:
2662:
2659:
2654:
2649:
2644:
2640:
2639:
2636:
2633:
2628:
2623:
2618:
2614:
2613:
2610:
2607:
2602:
2599:
2594:
2590:
2589:
2586:
2583:
2578:
2575:
2570:
2566:
2565:
2562:
2559:
2554:
2547:
2544:
2538:
2537:
2534:
2531:
2526:
2523:
2518:
2514:
2513:
2510:
2507:
2504:
2501:
2496:
2492:
2491:
2488:
2485:
2480:
2475:
2470:
2466:
2465:
2462:
2459:
2454:
2449:
2444:
2440:
2439:
2436:
2433:
2428:
2421:
2416:
2412:
2411:
2408:
2405:
2400:
2393:
2388:
2384:
2383:
2380:
2377:
2372:
2367:
2362:
2358:
2357:
2354:
2351:
2346:
2339:
2334:
2330:
2329:
2326:
2323:
2318:
2310:
2307:
2301:
2300:
2297:
2294:
2289:
2286:
2281:
2277:
2276:
2273:
2270:
2265:
2258:
2255:
2249:
2248:
2245:
2242:
2237:
2234:
2231:
2225:
2224:
2218:
2215:
2210:
2203:
2198:
2194:
2193:
2190:
2187:
2182:
2174:
2169:
2165:
2164:
2158:
2155:
2150:
2147:
2142:
2138:
2137:
2134:
2131:
2126:
2121:
2116:
2112:
2111:
2106:
2103:
2098:
2093:
2088:
2084:
2083:
2080:
2077:
2072:
2067:
2062:
2058:
2057:
2054:
2051:
2046:
2039:
2034:
2030:
2029:
2026:
2023:
2020:
2017:
2012:
2008:
2007:
2004:
2001:
1996:
1989:
1986:
1980:
1979:
1976:
1973:
1968:
1961:
1958:
1952:
1951:
1948:
1945:
1940:
1933:
1930:
1924:
1923:
1920:
1917:
1914:
1911:
1908:
1867:
1864:
1854:, and between
1829:Channel Tunnel
1824:
1821:
1820:
1819:
1815:
1800:
1785:
1778:
1771:
1768:
1757:
1742:
1729:locomotive at
1723:
1716:
1705:
1690:
1669:
1666:
1632:on its way to
1621:
1620:Tramway safety
1618:
1549:
1546:
1514:
1513:
1506:
1433:
1432:
1347:
1345:
1338:
1321:
1318:
1313:Midland Region
1246:Eastern Region
1214:Haywards Heath
1194:Maidstone East
1138:
1137:
1134:
1130:
1129:
1126:
1122:
1121:
1118:
1113:
1109:
1108:
1105:
1100:
1096:
1095:
1092:
1089:
1085:
1084:
1076:
1075:
1068:
1067:
1062:
1061:
1054:
1053:
1047:
1046:
1045:
1014:
1011:
979:, Sussex. The
960:
957:
940:
937:
935:
932:
915:
912:
856:
853:
711:Sheerness line
662:
659:
597:
596:
593:
592:
589:
585:
584:
578:
574:
573:
557:
553:
552:
549:
545:
544:
541:
535:
534:
491:
487:
486:
478:
477:
474:
473:
462:
458:
457:
438:
432:
431:
412:
408:
407:
404:
400:
399:
391:
390:
387:
386:
372:
366:
365:
360:
356:
355:
347:
341:
340:
335:
331:
330:
327:
321:
320:
314:
308:
307:
301:
295:
294:
291:
287:
286:
255:
251:
250:
247:
243:
242:
237:
233:
232:
229:
225:
224:
221:
214:
213:
210:
204:
203:
202:(80.47 m)
196:
190:
189:
186:
185:Wheel diameter
182:
181:
178:standard gauge
152:
146:
145:
140:
136:
135:
132:
125:
124:
121:
119:Configuration:
116:
115:
114:Specifications
107:
106:
103:
102:
99:
97:Total produced
93:
92:
89:
85:
84:
81:
77:
76:
71:
67:
66:
63:
59:
58:
50:
49:
37:A Class 33 at
36:
28:
27:
15:
9:
6:
4:
3:
2:
6099:
6088:
6085:
6083:
6080:
6078:
6075:
6073:
6070:
6068:
6065:
6063:
6060:
6058:
6055:
6053:
6050:
6049:
6047:
6032:
6029:
6027:
6024:
6022:
6019:
6017:
6014:
6012:
6009:
6007:
6004:
6002:
5999:
5996:
5995:
5992:
5986:
5983:
5982:
5980:
5976:
5970:
5967:
5966:
5964:
5960:
5954:
5951:
5949:
5946:
5944:
5941:
5940:
5938:
5935:
5931:
5925:
5922:
5920:
5917:
5915:
5912:
5910:
5907:
5905:
5902:
5900:
5897:
5895:
5892:
5890:
5887:
5885:
5882:
5880:
5877:
5875:
5872:
5870:
5867:
5865:
5862:
5860:
5857:
5856:
5854:
5850:
5844:
5841:
5839:
5836:
5834:
5831:
5829:
5826:
5824:
5821:
5820:
5818:
5814:
5808:
5805:
5803:
5800:
5798:
5795:
5793:
5790:
5788:
5785:
5784:
5782:
5778:
5772:
5769:
5767:
5764:
5762:
5759:
5757:
5754:
5752:
5749:
5747:
5744:
5742:
5739:
5737:
5734:
5732:
5729:
5727:
5724:
5722:
5719:
5717:
5714:
5712:
5709:
5707:
5704:
5702:
5699:
5697:
5694:
5693:
5691:
5685:
5679:
5676:
5674:
5671:
5669:
5666:
5664:
5661:
5659:
5656:
5654:
5651:
5649:
5646:
5644:
5641:
5639:
5636:
5634:
5631:
5629:
5626:
5624:
5621:
5619:
5616:
5614:
5611:
5609:
5606:
5604:
5601:
5599:
5596:
5594:
5591:
5589:
5586:
5584:
5581:
5579:
5576:
5574:
5571:
5569:
5566:
5564:
5561:
5559:
5556:
5555:
5553:
5549:
5543:
5540:
5538:
5535:
5533:
5530:
5528:
5525:
5523:
5520:
5518:
5515:
5513:
5510:
5508:
5505:
5503:
5500:
5498:
5495:
5493:
5490:
5488:
5485:
5483:
5480:
5478:
5475:
5473:
5470:
5468:
5465:
5463:
5460:
5458:
5455:
5453:
5450:
5448:
5445:
5443:
5440:
5438:
5435:
5433:
5430:
5428:
5425:
5423:
5420:
5418:
5415:
5413:
5410:
5408:
5405:
5403:
5400:
5398:
5395:
5393:
5390:
5388:
5385:
5383:
5380:
5378:
5375:
5374:
5372:
5366:
5360:
5357:
5355:
5352:
5350:
5347:
5345:
5342:
5340:
5337:
5335:
5332:
5330:
5327:
5325:
5322:
5320:
5317:
5315:
5312:
5310:
5307:
5305:
5302:
5300:
5297:
5295:
5292:
5290:
5287:
5285:
5282:
5280:
5277:
5275:
5272:
5270:
5267:
5265:
5262:
5260:
5257:
5255:
5252:
5250:
5247:
5245:
5242:
5240:
5237:
5235:
5232:
5230:
5227:
5225:
5222:
5220:
5217:
5215:
5212:
5210:
5207:
5205:
5202:
5200:
5197:
5195:
5192:
5190:
5187:
5185:
5182:
5180:
5177:
5175:
5172:
5170:
5167:
5165:
5162:
5160:
5157:
5155:
5152:
5150:
5147:
5145:
5142:
5140:
5137:
5135:
5132:
5130:
5127:
5125:
5122:
5120:
5117:
5115:
5112:
5110:
5107:
5105:
5102:
5100:
5097:
5095:
5092:
5090:
5087:
5086:
5084:
5080:
5074:
5071:
5069:
5066:
5064:
5061:
5059:
5056:
5054:
5051:
5049:
5046:
5044:
5041:
5039:
5036:
5034:
5031:
5029:
5026:
5024:
5021:
5019:
5016:
5014:
5011:
5009:
5006:
5004:
5001:
4999:
4996:
4994:
4991:
4989:
4986:
4984:
4981:
4979:
4976:
4974:
4971:
4969:
4966:
4964:
4961:
4959:
4956:
4954:
4951:
4949:
4946:
4944:
4941:
4939:
4936:
4934:
4931:
4929:
4926:
4924:
4921:
4919:
4916:
4914:
4911:
4909:
4906:
4904:
4901:
4900:
4898:
4895:
4888:
4882:
4879:
4877:
4874:
4872:
4869:
4867:
4864:
4862:
4859:
4857:
4854:
4852:
4849:
4847:
4844:
4842:
4839:
4837:
4834:
4832:
4829:
4827:
4824:
4822:
4819:
4817:
4814:
4813:
4811:
4807:
4798:
4793:
4791:
4786:
4784:
4779:
4778:
4775:
4769:
4766:
4764:
4761:
4759:
4756:
4754:
4751:
4749:
4746:
4745:
4735:
4731:
4727:
4723:
4719:
4718:
4712:
4708:
4704:
4700:
4696:
4692:
4691:
4685:
4681:
4677:
4673:
4669:
4665:
4664:
4658:
4654:
4650:
4646:
4642:
4638:
4637:
4631:
4624:
4623:
4618:
4614:
4610:
4606:
4604:9780711032842
4600:
4597:. Ian Allan.
4596:
4591:
4587:
4583:
4579:
4577:9780860933182
4573:
4569:
4564:
4560:
4556:
4552:
4550:9780711031029
4546:
4543:. Ian Allan.
4542:
4537:
4533:
4529:
4525:
4523:9781870754194
4519:
4515:
4510:
4506:
4502:
4498:
4496:9780711018945
4492:
4489:. Ian Allan.
4488:
4483:
4482:
4472:
4470:0-7110-0751-9
4466:
4462:
4457:
4453:
4447:
4443:
4439:
4435:
4431:
4429:0-7110-2985-7
4425:
4421:
4416:
4412:
4410:0-906899-03-6
4406:
4402:
4397:
4393:
4391:0-7110-0617-2
4387:
4383:
4378:
4374:
4368:
4364:
4359:
4355:
4353:0-7110-0924-4
4349:
4345:
4340:
4336:
4331:
4327:
4325:0-7110-1109-5
4321:
4317:
4312:
4308:
4302:
4298:
4293:
4289:
4287:0-906899-50-8
4283:
4279:
4274:
4270:
4268:0-906899-07-9
4264:
4260:
4256:
4252:
4248:
4246:0-7110-2807-9
4242:
4239:. Ian Allan.
4238:
4233:
4229:
4227:0-907036-05-8
4223:
4219:
4214:
4210:
4204:
4200:
4195:
4191:
4189:0-946184-06-2
4185:
4181:
4180:Off the Rails
4176:
4172:
4168:
4164:
4162:0-906988-20-9
4158:
4154:
4149:
4145:
4143:0-7110-0558-3
4139:
4135:
4131:
4126:
4125:
4121:
4120:
4113:
4109:
4103:
4095:
4091:
4087:
4083:
4079:
4072:
4057:
4056:
4051:
4044:
4029:
4025:
4019:
4004:
4000:
3994:
3978:
3974:
3968:
3960:
3953:
3938:
3932:
3917:
3913:
3907:
3891:
3887:
3881:
3865:
3861:
3855:
3848:
3843:
3835:
3831:
3830:
3825:
3819:
3811:
3805:
3789:
3782:
3763:
3756:
3749:
3744:
3728:
3724:
3717:
3698:
3691:
3685:, p. 30.
3684:
3679:
3672:
3667:
3661:, p. 33.
3660:
3655:
3649:, p. 44.
3648:
3647:Earnshaw 1991
3643:
3624:
3618:
3612:, p. 60.
3611:
3606:
3599:
3594:
3587:
3582:
3575:
3570:
3564:, p. 50.
3563:
3558:
3542:
3536:
3528:
3521:
3513:
3506:
3490:
3486:
3485:
3478:
3471:
3466:
3459:
3454:
3448:, p. 28.
3447:
3442:
3434:
3432:0-7110-0558-3
3428:
3424:
3420:
3414:
3407:
3402:
3394:
3392:0-7110-0534-6
3388:
3384:
3377:
3371:, p. 26.
3370:
3365:
3358:
3357:Morrison 1985
3353:
3347:, p. 12.
3346:
3345:Beecroft 1986
3341:
3333:
3329:
3325:
3318:
3312:, p. 27.
3311:
3306:
3304:
3302:
3295:, p. 10.
3294:
3293:Beecroft 1986
3289:
3282:
3277:
3271:, p. 22.
3270:
3265:
3258:
3253:
3246:
3241:
3235:, p. 13.
3234:
3229:
3223:, p. 14.
3222:
3217:
3210:
3205:
3199:, p. 42.
3198:
3193:
3186:
3181:
3175:, p. 41.
3174:
3169:
3167:
3159:
3154:
3147:
3142:
3136:, p. 38.
3135:
3130:
3128:
3121:, p. 37.
3120:
3115:
3113:
3106:, p. 33.
3105:
3100:
3098:
3096:
3088:
3083:
3077:, p. 32.
3076:
3071:
3069:
3061:
3056:
3050:, p. 30.
3049:
3044:
3042:
3040:
3032:
3027:
3021:, p. 29.
3020:
3015:
3013:
3011:
3009:
3007:
3000:, p. 12.
2999:
2994:
2992:
2990:
2982:
2977:
2971:, p. 10.
2970:
2965:
2963:
2961:
2953:
2948:
2941:
2936:
2934:
2926:
2921:
2914:
2909:
2907:
2905:
2898:, p. 78.
2897:
2892:
2890:
2882:
2877:
2875:
2859:
2855:
2849:
2841:
2840:
2832:
2830:
2828:
2826:
2810:
2806:
2800:
2798:
2790:
2785:
2781:
2766:
2756:
2752:
2744:
2742:
2738:
2735:(now part of
2734:
2733:Graham Farish
2730:
2726:
2722:
2718:
2714:
2711:and later in
2710:
2706:
2702:
2687:
2684:
2682:
2679:
2676:
2673:
2671:
2668:
2667:
2663:
2660:
2658:
2655:
2653:
2650:
2648:
2645:
2642:
2641:
2637:
2634:
2632:
2629:
2627:
2624:
2622:
2619:
2616:
2615:
2611:
2608:
2606:
2603:
2600:
2598:
2595:
2592:
2591:
2587:
2584:
2582:
2579:
2576:
2574:
2571:
2568:
2567:
2563:
2560:
2558:
2555:
2553:
2552:
2548:
2545:
2543:
2540:
2539:
2535:
2532:
2530:
2527:
2524:
2522:
2519:
2516:
2515:
2511:
2508:
2505:
2502:
2500:
2497:
2494:
2493:
2489:
2486:
2484:
2481:
2479:
2476:
2474:
2471:
2468:
2467:
2463:
2460:
2458:
2455:
2453:
2450:
2448:
2445:
2442:
2441:
2437:
2434:
2432:
2429:
2427:
2426:
2422:
2420:
2417:
2414:
2413:
2409:
2406:
2404:
2401:
2399:
2398:
2394:
2392:
2389:
2386:
2385:
2381:
2378:
2376:
2373:
2371:
2368:
2366:
2363:
2360:
2359:
2355:
2352:
2350:
2347:
2345:
2344:
2343:R.J. Mitchell
2340:
2338:
2335:
2332:
2331:
2327:
2324:
2322:
2319:
2316:
2315:
2311:
2308:
2306:
2303:
2302:
2298:
2295:
2293:
2290:
2287:
2285:
2282:
2279:
2278:
2274:
2271:
2269:
2266:
2264:
2263:
2259:
2256:
2254:
2251:
2250:
2246:
2243:
2241:
2238:
2235:
2232:
2230:
2227:
2226:
2222:
2219:
2216:
2214:
2211:
2209:
2208:
2204:
2202:
2199:
2196:
2195:
2191:
2188:
2186:
2183:
2180:
2179:
2175:
2173:
2170:
2167:
2166:
2162:
2159:
2156:
2154:
2151:
2148:
2146:
2143:
2140:
2139:
2135:
2132:
2130:
2127:
2125:
2122:
2120:
2117:
2114:
2113:
2110:
2107:
2104:
2102:
2099:
2097:
2094:
2092:
2089:
2086:
2085:
2081:
2078:
2076:
2073:
2071:
2068:
2066:
2063:
2060:
2059:
2055:
2053:Under repair
2052:
2050:
2047:
2045:
2044:
2040:
2038:
2035:
2032:
2031:
2027:
2024:
2021:
2018:
2016:
2013:
2010:
2009:
2005:
2002:
2000:
1997:
1995:
1994:
1990:
1987:
1985:
1982:
1981:
1977:
1974:
1972:
1969:
1967:
1966:
1962:
1959:
1957:
1954:
1953:
1949:
1946:
1944:
1941:
1939:
1938:
1934:
1931:
1929:
1926:
1925:
1921:
1918:
1915:
1912:
1909:
1906:
1905:
1899:
1893:
1889:
1884:
1877:
1872:
1863:
1861:
1857:
1856:Stewarts Lane
1853:
1849:
1845:
1841:
1837:
1836:
1830:
1816:
1813:
1809:
1805:
1801:
1798:
1794:
1790:
1786:
1783:
1779:
1776:
1772:
1769:
1766:
1762:
1758:
1755:
1751:
1747:
1743:
1740:
1736:
1732:
1728:
1724:
1721:
1717:
1714:
1710:
1706:
1703:
1699:
1695:
1691:
1688:
1684:
1680:
1676:
1672:
1671:
1665:
1663:
1654:
1650:
1647:
1643:
1635:
1631:
1626:
1617:
1613:
1609:
1607:
1603:
1599:
1595:
1591:
1585:
1583:
1579:
1578:jumper cables
1575:
1571:
1567:
1559:
1554:
1545:
1543:
1538:
1536:
1532:
1527:
1521:
1519:
1511:
1507:
1504:
1503:
1502:
1500:
1496:
1492:
1489:was actually
1488:
1484:
1479:
1475:
1471:
1468:
1464:
1460:
1456:
1452:
1448:
1444:
1440:
1429:
1426:
1418:
1407:
1404:
1400:
1397:
1393:
1390:
1386:
1383:
1379:
1376: โ
1375:
1371:
1370:Find sources:
1364:
1360:
1354:
1353:
1348:This section
1346:
1342:
1337:
1336:
1331:
1326:
1317:
1314:
1310:
1306:
1305:steam heating
1302:
1297:
1295:
1291:
1287:
1283:
1278:
1276:
1272:
1269:'s 1963 film
1268:
1264:
1260:
1255:
1251:
1247:
1242:
1239:
1235:
1231:
1227:
1223:
1217:
1215:
1211:
1210:Three Bridges
1207:
1203:
1199:
1195:
1191:
1187:
1183:
1179:
1175:
1171:
1170:
1165:
1161:
1157:
1153:
1149:
1145:
1135:
1133:Total built:
1131:
1127:
1123:
1119:
1117:
1114:
1111:
1110:
1106:
1104:
1101:
1098:
1097:
1093:
1090:
1087:
1086:
1072:
1058:
1051:
1043:
1032:
1028:
1024:
1019:
1010:
1008:
1004:
986:
985:Restriction 0
982:
981:Hastings Line
978:
974:
965:
956:
954:
950:
949:Restriction 4
946:
931:
928:
924:
922:
911:
909:
908:vacuum brakes
905:
901:
897:
893:
889:
885:
884:diesel engine
881:
878:
874:
870:
866:
862:
861:Sulzer Type 2
852:
850:
846:
841:
837:
833:
827:
824:
820:
816:
810:
808:
804:
800:
794:
792:
788:
782:
780:
779:Hastings line
775:
771:
768:
765:(BRCW), with
764:
760:
755:
753:
749:
745:
741:
736:
732:
731:Sulzer Type 2
726:
724:
720:
716:
712:
708:
704:
699:
694:
692:
688:
684:
680:
676:
672:
668:
658:
655:
653:
649:
645:
641:
636:
634:
630:
626:
621:
619:
615:
612:
608:
604:
590:
586:
582:
579:
575:
571:
566:
561:
558:
554:
550:
546:
542:
540:
536:
533:
528:
524:
520:
516:
512:
507:
503:
499:
495:
492:
488:
483:
479:
471:
467:
463:
459:
455:
450:
446:
442:
439:
437:
433:
429:
424:
420:
416:
413:
409:
405:
403:Maximum speed
401:
396:
392:
384:
380:
376:
373:
371:
367:
364:
361:
359:Train heating
357:
348:
346:
342:
339:
336:
332:
328:
326:
322:
318:
315:
313:
309:
305:
302:
300:
296:
292:
290:Fuel capacity
288:
282:
278:
274:
268:
264:
260:
256:
252:
248:
244:
238:
234:
230:
226:
222:
220:
217: โข
215:
211:
209:
205:
201:
197:
195:
194:Minimum curve
191:
187:
183:
179:
173:1,435 mm
153:
151:
147:
144:
141:
137:
133:
131:
128: โข
126:
122:
117:
112:
108:
100:
94:
90:
86:
82:
80:Serial number
78:
75:
72:
68:
64:
60:
55:
51:
40:
34:
29:
22:
19:
5997:
5816:Departmental
5622:
5481:
5476:
5244:43 (II)
5193:
5188:
4715:
4688:
4661:
4634:
4621:
4594:
4567:
4540:
4513:
4486:
4460:
4441:
4419:
4400:
4381:
4362:
4343:
4334:
4315:
4296:
4277:
4258:
4236:
4217:
4198:
4179:
4152:
4129:
4111:
4102:
4077:
4071:
4059:. Retrieved
4053:
4043:
4031:. Retrieved
4027:
4018:
4006:. Retrieved
4002:
3993:
3981:. Retrieved
3967:
3958:
3952:
3940:. Retrieved
3931:
3919:. Retrieved
3915:
3906:
3894:. Retrieved
3889:
3880:
3868:. Retrieved
3864:the original
3854:
3842:
3834:the original
3827:
3818:
3804:
3792:. Retrieved
3781:
3769:. Retrieved
3755:
3748:Vaughan 2003
3743:
3731:. Retrieved
3727:the original
3716:
3704:. Retrieved
3690:
3678:
3666:
3659:Trevena 1981
3654:
3642:
3630:. Retrieved
3617:
3605:
3593:
3581:
3569:
3557:
3545:. Retrieved
3535:
3526:
3520:
3511:
3505:
3493:. Retrieved
3483:
3477:
3465:
3453:
3441:
3418:
3413:
3401:
3382:
3376:
3364:
3352:
3340:
3323:
3317:
3288:
3276:
3264:
3252:
3240:
3228:
3216:
3204:
3192:
3180:
3153:
3141:
3082:
3055:
3026:
2976:
2947:
2942:, p. 8.
2920:
2915:, p. 7.
2861:. Retrieved
2857:
2848:
2837:
2812:. Retrieved
2808:
2784:
2765:
2755:
2698:
2669:
2651:
2646:
2635:Operational
2625:
2620:
2609:Operational
2596:
2572:
2561:Operational
2549:
2541:
2533:Operational
2520:
2498:
2487:Operational
2477:
2472:
2461:Operational
2451:
2446:
2435:Operational
2423:
2418:
2407:Operational
2395:
2390:
2369:
2364:
2353:Operational
2341:
2336:
2325:Operational
2312:
2304:
2296:Operational
2283:
2260:
2252:
2244:Operational
2228:
2205:
2200:
2189:Operational
2176:
2171:
2144:
2123:
2118:
2095:
2090:
2079:Operational
2069:
2064:
2041:
2036:
2014:
2003:Operational
1991:
1983:
1963:
1955:
1947:Operational
1935:
1927:
1910:TOPS number
1907:1957 number
1897:
1866:Preservation
1834:
1826:
1722:, Hampshire.
1679:Hoo Junction
1675:Paddock Wood
1659:
1639:
1614:
1610:
1586:
1563:
1539:
1522:
1515:
1480:
1476:
1472:
1436:
1421:
1415:January 2024
1412:
1402:
1395:
1388:
1381:
1369:
1357:Please help
1352:verification
1349:
1298:
1279:
1275:Look at Life
1274:
1270:
1243:
1218:
1174:Hither Green
1167:
1163:
1141:
1116:Hither Green
975:, Kent, and
970:
942:
929:
925:
917:
896:turbocharger
892:de Havilland
858:
828:
811:
799:Cliffe, Kent
795:
783:
776:
772:
756:
727:
695:
664:
656:
637:
622:
606:
602:
600:
572:(33/2s only)
569:
567:(33/1s only)
564:
559:
522:
498:British Rail
493:
453:
443:45,000
440:
427:
421:(1,156
414:
411:Power output
370:Train brakes
334:Transmission
18:
5936:locomotives
5879:D0226/D0227
5859:15097โ15099
5780:Multi-modes
5387:10201โ10203
5377:10000โ10001
5239:43 (I)
4438:Webb, Brian
3847:Lilley 2020
3706:17 February
3683:Butlin 2015
3610:Lilley 2020
3598:Bishop 1984
3586:Bishop 1984
3574:Bishop 1984
3562:Lilley 2020
3547:20 November
3495:29 December
3458:Lilley 2020
3446:Lilley 2020
3406:Denton 1981
3369:Lilley 2020
3310:Lilley 2020
3281:Lilley 2020
3269:Lilley 2020
3257:Lilley 2020
3245:Lilley 2020
3233:Lilley 2020
3221:Lilley 2020
3209:Lilley 2020
3197:Lilley 2020
3185:Lilley 2020
3173:Lilley 2020
3158:Lilley 2020
3146:Lilley 2020
3134:Lilley 2020
3119:Lilley 2020
3104:Lilley 2020
3087:Lilley 2020
3075:Lilley 2020
3060:Lilley 2020
3048:Lilley 2020
3031:Lilley 2020
3019:Lilley 2020
2998:Lilley 2020
2981:Lilley 2020
2969:Lilley 2020
2952:Lilley 2020
2940:Lilley 2020
2925:Lilley 2020
2913:Lilley 2020
2896:Glover 2001
2863:25 December
2715:. In 2010
1894:in May 2023
1818:locomotive.
1720:Wallers Ash
1662:train guard
1570:Bournemouth
1495:boat trains
1455:Southampton
1445:powered by
1186:Chislehurst
1169:Night Ferry
1164:Man of Kent
1040:March 1974
1013:Early years
921:boat trains
807:Lanarkshire
607:BRCW Type 3
588:Disposition
454:Continuous:
417:1,550
299:Prime mover
254:Loco weight
46: 1978
24:BRCW Type 3
6046:Categories
5852:Prototypes
5689:(pre-TOPS)
5370:(pre-TOPS)
4717:Model Rail
4451:0715375148
4372:0711015104
4255:Hoole, Ken
4033:1 February
3983:19 January
3870:2 February
3860:"Class 33"
3794:31 October
3671:Hoole 1983
3632:1 February
3470:Moody 1979
2881:Moody 1979
2805:"Class 33"
2777:References
2652:Jim Martin
2163:dark blue
1840:Class 47/9
1775:Mottingham
1694:Burghclere
1582:Oxted Line
1566:third rail
1451:Winchester
1447:third-rail
1385:newspapers
1254:Uddingston
1148:boat train
894:LAG 37-17
845:Winchester
803:Uddingston
675:Portsmouth
661:Background
468:(349
461:Brakeforce
447:(200
352:Blue Star,
345:MU working
281:short tons
267:short tons
88:Build date
62:Power type
5687:Electrics
5551:Electrics
4734:173324502
4726:1369-5118
4699:0953-4563
4672:0262-561X
4645:0262-561X
4613:185031160
4134:Ian Allan
4094:226087101
4086:1753-2469
3959:Trackside
3423:Ian Allan
3332:0264-3642
2814:1 January
2789:Webb 1978
2760:D6565โ85.
2657:Carnforth
2425:Swordfish
2275:BR Green
2153:Carnforth
2129:Carnforth
2101:Carnforth
2070:Eastleigh
1965:Eastleigh
1916:Location
1852:Eastleigh
1761:Guildford
1702:Hampshire
1698:Highclere
1683:Tonbridge
1594:push-pull
1574:push-pull
1499:run-round
1328:33118 at
1286:Eastleigh
1190:Faversham
1182:Tonbridge
1146:worked a
1103:Eastleigh
1094:Quantity
869:Smethwick
832:Tonbridge
823:Sheffield
570:Slim Jims
560:Cromptons
556:Nicknames
490:Operators
319:generator
312:Generator
275:(79
273:long tons
261:(75
259:long tons
208:Wheelbase
91:1960โ1962
5838:Southern
5229:41 (III)
4707:49953699
4680:49957965
4653:49957965
4586:17916362
4559:58829151
4532:60054445
4505:24733799
4440:(1978).
4257:(1983).
4171:17226439
4008:13 April
3977:Archived
3921:27 April
3771:21 March
3489:Archived
2729:OO gauge
2721:OO gauge
2713:OO gauge
2705:HO gauge
2638:BR Blue
2588:BR Blue
2564:BR Blue
2536:BR Blue
2490:BR Blue
2464:BR Blue
2410:BR Blue
2382:BR Blue
2299:BR Blue
2178:Spitfire
2124:Glen Loy
2028:BR Blue
1937:Sea King
1848:Waterloo
1804:Somerset
1727:Class 47
1602:Class 74
1598:Class 73
1510:Class 74
1439:Weymouth
1309:Class 24
1248:to work
977:Hastings
648:Class 27
603:Class 33
565:Bagpipes
502:Southern
441:Maximum:
428:At rail:
169: in
123:
5934:Getlink
5833:Eastern
5807:99 (II)
5802:93 (II)
5797:88 (II)
5678:93 (II)
5623:83 (II)
5558:22 (II)
5359:70 (II)
5274:48 (II)
5224:41 (II)
5134:21 (II)
5114:18 (II)
4122:Sources
4061:3 April
3896:30 July
3829:YouTube
3733:26 June
2709:O gauge
2452:Vampire
2370:Sealion
2314:Seagull
2262:Ashford
2043:Griffon
1922:Livery
1890:on the
1535:Cardiff
1491:tramway
1485:at the
1399:scholar
1290:Spondon
1160:Chatham
1025:with a
996:⁄
840:Feltham
836:Reading
707:Margate
703:Chatham
671:Reading
548:Numbers
523:Current
415:Engine:
164:⁄
70:Builder
5998:Lists:
5985:99 (I)
5924:Taurus
5914:HS4000
5673:93 (I)
5648:88 (I)
5618:83 (I)
5563:70 (I)
5269:48 (I)
5219:41 (I)
5139:22 (I)
5129:21 (I)
5109:18 (I)
4732:
4724:
4705:
4697:
4678:
4670:
4651:
4643:
4611:
4601:
4584:
4574:
4557:
4547:
4530:
4520:
4503:
4493:
4467:
4448:
4426:
4407:
4388:
4369:
4350:
4322:
4303:
4284:
4265:
4243:
4224:
4205:
4186:
4169:
4159:
4140:
4092:
4084:
3942:3 July
3429:
3389:
3330:
2725:Heljan
2674:33208
2643:D6592
2617:D6587
2593:D6586
2569:D6536
2546:33116
2517:D6528
2495:D6527
2469:D6525
2443:D6521
2415:D6514
2397:Sophie
2387:D6513
2361:D6585
2333:D6583
2309:33057
2280:D6571
2257:33052
2233:33048
2207:Merlin
2197:D6564
2168:D6553
2141:D6548
2115:D6547
2087:D6543
2061:D6539
2033:D6534
2011:D6530
1988:33012
1960:33008
1932:33002
1833:73205
1782:Hilsea
1765:Surrey
1750:Marden
1646:beacon
1564:While
1518:Type 1
1401:
1394:
1387:
1380:
1372:
1294:Didcot
1250:Cliffe
1031:Fawley
1023:Oxford
855:Design
849:Didcot
689:. The
494:Former
485:Career
383:Vacuum
381:&
306:8LDA28
304:Sulzer
246:Height
228:Length
200:chains
134:BoโฒBoโฒ
39:Woking
5978:Ships
5919:Janus
5894:D2999
5889:D0280
5884:D0260
5874:89001
5869:18100
5864:18000
5542:D33/1
5537:D27/1
5532:D25/1
5527:D23/1
5522:D22/2
5517:D22/1
5512:D20/2
5507:D20/1
5502:D17/2
5497:D17/1
5492:D16/2
5487:D16/1
5482:D15/2
5477:D15/1
5472:D14/2
5467:D14/1
5462:D13/1
5457:D12/3
5452:D12/2
5447:D12/1
5442:D11/5
5437:D11/4
5432:D11/3
5427:D11/2
5422:D11/1
5417:D10/3
5412:D10/2
5407:D10/1
5392:10800
5382:10100
5073:D3/14
5068:D3/13
5063:D3/12
5058:D3/11
5053:D3/10
5003:D2/12
4998:D2/11
4993:D2/10
4923:15107
4918:15100
4913:13000
4908:11104
4903:11001
4892:(pre-
4626:(PDF)
3765:(PDF)
3700:(PDF)
3626:(PDF)
2747:Notes
2670:D6593
2647:33207
2621:33202
2597:33201
2573:33117
2542:D6535
2521:33111
2499:33110
2473:33109
2447:33108
2419:33103
2391:33102
2365:33065
2337:33063
2305:D6575
2284:33053
2253:D6570
2229:D6566
2223:blue
2201:33046
2172:33035
2145:33030
2119:33029
2091:33025
2065:33021
2037:33019
2015:33018
1984:D6515
1956:D6508
1928:D6501
1913:Name
1823:83301
1808:47202
1467:Poole
1406:JSTOR
1392:books
1202:20002
1198:E5004
1178:Dover
1150:from
1144:D5012
611:Bo-Bo
539:Class
279:; 87
265:; 83
236:Width
219:Bogie
150:Gauge
143:Bo-Bo
5953:9000
5948:0031
5943:0001
5828:97/6
5402:D8/2
5397:D8/1
5048:D3/9
5043:D3/8
5038:D3/7
5033:D3/6
5028:D3/5
5023:D3/4
5018:D3/3
5013:D3/2
5008:D3/1
4988:D2/9
4983:D2/8
4978:D2/7
4973:D2/6
4968:D2/5
4963:D2/4
4958:D2/3
4953:D2/2
4948:D2/1
4943:D1/4
4938:D1/3
4933:D1/2
4928:D1/1
4894:TOPS
4821:01/5
4730:OCLC
4722:ISSN
4703:OCLC
4695:ISSN
4690:RAIL
4676:OCLC
4668:ISSN
4649:OCLC
4641:ISSN
4609:OCLC
4599:ISBN
4582:OCLC
4572:ISBN
4555:OCLC
4545:ISBN
4528:OCLC
4518:ISBN
4501:OCLC
4491:ISBN
4465:ISBN
4446:ISBN
4424:ISBN
4405:ISBN
4386:ISBN
4367:ISBN
4348:ISBN
4320:ISBN
4301:ISBN
4282:ISBN
4263:ISBN
4241:ISBN
4222:ISBN
4203:ISBN
4184:ISBN
4167:OCLC
4157:ISBN
4138:ISBN
4090:OCLC
4082:ISSN
4063:2021
4035:2020
4010:2021
3985:2022
3944:2021
3923:2024
3898:2022
3872:2008
3796:2020
3773:2017
3735:2018
3708:2015
3634:2010
3549:2012
3497:2020
3427:ISBN
3387:ISBN
3328:ISSN
2865:2020
2816:2023
2707:and
2701:Lima
1858:and
1850:and
1842:and
1838:, a
1793:4CIG
1789:4VEP
1754:Kent
1696:and
1634:quay
1600:and
1526:DEMU
1487:quay
1463:4TCs
1459:4REP
1453:and
1378:news
1263:York
1236:and
1212:and
1200:and
1188:and
1176:and
1166:and
1158:via
1091:Name
1088:Code
945:TOPS
906:and
847:and
834:and
801:and
705:and
696:The
687:ยฃ25m
673:and
504:and
375:Dual
5909:GT3
5904:DP2
5899:DP1
5751:ES1
5746:EM2
5741:EM1
5736:EF1
5731:EE1
5726:EB1
5721:AL6
5716:AL5
5711:AL4
5706:AL3
5701:AL2
5696:AL1
1844:4TC
1748:at
1711:at
1681:to
1558:4TC
1361:by
1230:UIC
1154:to
1136:98
1120:47
1107:49
1029:to
1009:6.
904:air
877:SKF
464:35
445:lbf
419:bhp
379:Air
130:UIC
6048::
5969:98
5823:97
5792:74
5787:73
5771:JB
5766:JA
5761:HB
5756:HA
5668:92
5663:91
5658:90
5653:89
5643:87
5638:86
5633:85
5628:84
5613:82
5608:81
5603:80
5598:77
5593:76
5588:75
5583:74
5578:73
5573:72
5568:71
5354:69
5349:68
5344:67
5339:66
5334:65
5329:62
5324:60
5319:59
5314:58
5309:57
5304:56
5299:55
5294:53
5289:52
5284:51
5279:50
5264:47
5259:46
5254:45
5249:44
5234:42
5214:40
5209:38
5204:37
5199:35
5194:34
5189:33
5184:31
5179:30
5174:29
5169:28
5164:27
5159:26
5154:25
5149:24
5144:23
5124:20
5119:19
5104:17
5099:16
5094:15
5089:14
4881:13
4876:12
4871:11
4866:10
4861:09
4856:08
4851:07
4846:06
4841:05
4836:04
4831:03
4826:02
4816:01
4728:.
4701:.
4674:.
4647:.
4607:.
4580:.
4553:.
4526:.
4499:.
4165:.
4136:.
4110:.
4088:.
4052:.
4026:.
4001:.
3975:.
3914:.
3888:.
3826:.
3300:^
3165:^
3126:^
3111:^
3094:^
3067:^
3038:^
3005:^
2988:^
2959:^
2932:^
2903:^
2888:^
2873:^
2856:.
2824:^
2807:.
2796:^
2731:.
2677:โ
2601:โ
2577:โ
2525:โ
2503:โ
2288:โ
2236:โ
2149:โ
2019:โ
1763:,
1752:,
1700:,
1537:.
1277:.
1216:.
1128:2
1112:HG
1099:EH
1077:HG
1063:EH
809:.
805:,
681:,
470:kN
449:kN
423:kW
317:DC
198:4
175:)
101:98
43:c.
41:,
4896:)
4796:e
4789:t
4782:v
4736:.
4709:.
4682:.
4655:.
4615:.
4588:.
4561:.
4534:.
4507:.
4473:.
4454:.
4432:.
4413:.
4394:.
4375:.
4356:.
4328:.
4309:.
4290:.
4271:.
4249:.
4230:.
4211:.
4192:.
4173:.
4146:.
4114:.
4096:.
4065:.
4037:.
4012:.
3987:.
3946:.
3925:.
3900:.
3874:.
3812:.
3798:.
3775:.
3737:.
3710:.
3636:.
3551:.
3499:.
3435:.
3395:.
3334:.
2867:.
2818:.
1878:.
1767:.
1756:.
1704:.
1428:)
1422:(
1417:)
1413:(
1403:ยท
1396:ยท
1389:ยท
1382:ยท
1355:.
1252:โ
998:2
994:1
991:+
989:1
583:6
508:)
500:(
472:)
451:)
425:)
385:)
377:(
350:โ
283:)
277:t
269:)
263:t
171:(
166:2
162:1
159:+
157:8
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.