Knowledge

Agra Metro

Source 📝

940:
underground tanks of different capacities will be built in the Agra Metro Depot complex. For zero discharge facility, a joint water treatment plant of 1 lakh litre capacity will be set up at Agra Metro Depot. In this water treatment plant, the grey water coming out from the kitchen, washroom, floor cleaning, will be recycled. For this, a plant with a capacity of 70,000 litres will be installed. Similarly, a 30,000 litres capacity plant will be set up to treat such black water by washing the coach and whatever other chemical-rich water will come out. Both the plants will be built in the same building so that they can be used in a better way.
322: 501: 67: 833: 25: 2529: 379: 848:. However the contract was cancelled and Alstom was chosen to supply the rolling stock for the Yellow line. The rolling stock resembles those that run on the Kanpur Metro. On 6 March 2023, the first set of coaches arrived at the Taj Station of the Yellow line from Alstom's manufacturing facility at Savli in Gujarat. 943:
June 2021: Construction of depot line for Agra Metro has begun with the commencement of piling work on the depot line with 13 piles already constructed so far.} The depot line will connect the mainline with the Metro Depot which is under construction at PAC Ground where metro trains will be stabled
951:
June 2021: Along with the construction of the Agra Metro Project Priority Section (Taj East Gate to Jama Masjid), UP Metro has also started the construction of the Depot Line. For this, along with starting the piling, the construction of 13 piles has also been completed. The covered train stabling
947:
June 2021: The casting of the concourse beam of Taj East Gate, the first metro station of Agra Metro, has also started. The piling work has already been completed with the construction of 69 piles of Taj East Gate Metro Station. Currently, the pillars are being constructed in the side grid of Taj
939:
May 2021: UP Metro has built 400 piles out of a total of 686 in the priority section of the Agra Metro project. With this, 45 pile-caps and 16 pillars are also ready. The work of a zero discharge facility at Agra Metro depot is also at a rapid pace. For the zero discharge facility, several
935:
April 2021: In Agra metro priority section, a total of 688 piles are to be constructed in the 3 km long portion on Fatehabad Road, in which 344 piles are ready, 10 pillars are built, and digging is continued for 3 metro
359:(UPMRC). It is set to consist of two metro lines, with a total length of 29.65 kilometres (18.42 mi) and 27 stations. The Agra Metro is one of four rapid transit system in Uttar Pradesh, the others being the 1685: 1339: 1839: 1736: 1369: 1248: 1276: 926:
rolling stock and signalling contract. Agra Metro project gets conditional clearance from the Supreme Court. The project which was stuck due to the court stay will now progress fast.
1196: 717: 508:
In Phase 1, 14 metro stations will be built on the Yellow Line (Line 1) from Sikandra to Taj East Gate and 15 metro stations will be built on the Blue Line (Line 2) from
461:
About 20 lakh population of the city is expected to be benefited by Agra Metro Rail Project directly and indirectly at the time of commencement of commercial operations.
2664: 447:
The length of Sikandra to Taj East Gate corridor 14.00 km, which is partly elevated and partly underground and comprises 13 stations (6-Elevated and 7-Underground).
1503: 2517: 1529: 1331: 1405: 1145: 1361: 1115: 1762: 1582: 860:
September 2017: The central government rejected the DPR of Agra Metro as it didn't conform with the new Metro Rail Policy 2017 introduced that month.
3243: 1171: 1448: 952:
yard, integrated workshop, and pit wheel length are being constructed in Agra Metro Depot with the new PEB (Pre Engineering Building) technique.
2622: 1909: 1026: 424:
Agra Metro Rail Project will have 2 corridors that will pass through the heart of the city and will connect prominent tourist places including
2495: 1788: 1659: 1420: 2659: 1865: 1475: 1711: 1607: 976:
Aug 2021: Taj East Gate Metro Station takes shape, and it will be the first metro station of Agra Metro to be completed, as of 24 August.
1555: 1633: 3253: 2510: 1813: 3204: 973:
August 2021: European Investment Bank (EIB) approves and is ready to fund 480 mn euros for Agra Metro Rail Project, as of 10 August.
321: 2363: 2312: 932:
December 2020: Prime Minister Narendra Modi inaugurated the construction work at the Agra Metro Project Site on 7 December 2020.
844:
won the contract to supply the rolling stock and the signalling system, and the project received conditional clearance from the
2581: 2568: 985:
December 2021: Work on Agra Metro's third metro station, Fatehabad Metro Station, is expected to be completed by December-end.
472:(IPT), and non-motorized transport (NMT). The project will have non-fare box revenue from rental and advertisement as well as 2368: 2503: 2110: 1686:"Agra Metro Rail Project: आगरा मेट्रो के सभी स्टेशनों के यूनिक कोड को मिली मंजूरी, अब इन नामों से भी जाने जाएंगे ये स्टेशन" 1391: 1006: 929:
October 2020: Contract awarded for construction for three metro stations. Civil engineering work to start in December 2020.
356: 85: 2586: 2479: 2429: 2474: 2469: 2439: 2434: 2358: 2307: 1902: 2715: 2484: 2464: 2419: 2414: 2409: 2322: 2128: 1996: 1763:"आगरा मेट्रो के काम ने पकड़ी रफ्तार: ताज पूर्वी के साथ अब बसई स्टेशन पर कार्य शुरू, दस महीने में 102 पिलर का निर्माण" 912:
and others other departments are pending. Once permissions are in place, land acquisition will take another 3 months.
2454: 2404: 2317: 1814:"आगरा में मेट्रो: तीसरे स्टेशन का काम दिसंबर अंत में होगा पूरा, निर्माण के दौरान ताजमहल की खूबसूरत तस्वीर आई सामने" 1089: 3258: 2459: 2449: 2444: 991:
March 2024: Prime Minister Narendra Modi inaugurated the priority corridor section of Agra Metro on 6 March 2024.
676: 509: 437: 2050: 3080: 2525: 2424: 2378: 909: 898: 481: 2383: 2302: 1895: 469: 433: 2388: 2133: 1123: 477: 944:
and maintained. For the depot line, a total of 500 piles, 39 pile capes, and 34 piers will be constructed.
2533: 2343: 2286: 2281: 1300: 1298: 1001: 66: 450:
The length of Agra Cantt to Kalindi Vihar corridor is 15.40 km comprising 14 stations all elevated.
3248: 3070: 2638: 2348: 2276: 2271: 1295: 2373: 2353: 1453: 919: 841: 3016: 2643: 2573: 2558: 1737:"Agra Metro Rail Project: जल्द आकार लेने लगेगा आगरा का ये मेट्रो स्टेशन, रखा गया पहला डबल टी गर्डर" 956: 761: 623: 533: 1222: 1064: 1050: 874:
September 2018: Detailed Project Report (DPR) sent by the UP Government to the Central Government.
2617: 2593: 2045: 1306: 473: 275: 2818: 2563: 2541: 2338: 2148: 1991: 905: 668: 556: 979:
September 2021: Construction begins of Agra Metro's second metro station, Basai Metro Station.
3075: 2598: 2138: 2060: 1634:"Narendra Modi: PM Narendra Modi inaugurates construction work | Agra News - Times of India" 3065: 2986: 966:
August 2021: Unique codes of all metro stations in Agra Metro Rail Project get approved by
8: 3101: 2780: 2230: 2143: 2080: 1973: 648: 38:
Please help update this article to reflect recent events or newly available information.
2981: 2173: 1608:"दिसंबर से शुरू होगा आगरा मेट्रो का काम, 273 करोड़ की लागत से बनेंगे तीन प्रमुख स्टेशन" 1583:"Agra Metro Line-1's Construction Works Worth Rs 272 Crores Set for award to Sam India" 464:
The proposed corridors will be having multimodal integration with railway stations and
948:
East Gate Metro Station. Soon the construction of the concourse level will also start.
421:
350 crore per km. The cost will be evaluated based on the June 2015 price index.
3106: 3050: 3021: 2765: 2178: 2075: 2070: 1504:"तेजी सेे बढ़ रही आगरा की मेट्रो, स्टेशनों के लिए जमीन हस्तांतरण की तैयारी Agra News" 1476:"कानपुर से पीएम मोदी ने किया आगरा मेट्रो का शिलान्यास, ताजनगरी में हुआ सीधा प्रसारण" 3001: 2960: 2839: 2834: 2261: 2183: 1968: 1277:"Agra Metro Project: अब आएगी रफ्तार, अगले सप्ताह से शुरू होगा मेट्रो के लिए ये काम" 789: 440:, Collectorate, Sanjay Place, and surrounding densely populated residential areas. 1866:"PM Modi inaugurates priority section of Agra Metro; here's a look at the project" 3096: 3060: 3055: 2996: 2991: 2976: 2944: 2844: 2725: 2700: 1943: 1530:"Work on Agra Metro yet to start; may miss deadline | Agra News - Times of India" 967: 1421:"कानपुर-आगरा को जल्द मिलेगी मेट्रो की सौगात, 350 करोड़ रुपयों से पकड़ेगी रफ्तार" 3151: 3120: 3006: 2900: 2885: 2869: 2859: 2854: 2849: 2235: 2090: 2055: 2040: 2035: 1425: 1197:"PM Modi to flag off Agra Metro priority corridor: Route, price, other details" 888: 284: 267: 500: 3237: 3219: 3206: 3011: 2910: 2750: 2745: 2710: 2678: 2168: 1918: 1011: 891: 845: 406: 360: 348: 340: 119: 109: 1249:"Now, reach Taj Mahal by Metro. PM to launch Agra 'priority corridor' today" 398:
On 28 February 2019, Union Cabinet approved the metro project in Agra worth
3156: 3135: 2915: 2895: 2864: 2803: 2760: 2755: 2735: 2730: 2204: 2199: 2105: 2100: 1021: 1016: 923: 901:
has requested relevant authorities to transfer land for Metro construction.
368: 364: 982:
October 2021: Tenders invited for electrification contract for Agra Metro.
3181: 3176: 3166: 2905: 2890: 2813: 2808: 2770: 2740: 2720: 2705: 2095: 2085: 2065: 1789:"Tender invited for electrification contract for Agra Metro Rail Project" 904:
January 2020: Construction work yet to start as few permissions from the
372: 239: 884:
28 February 2019: Central Government approved the metro project in Agra.
3186: 3171: 3161: 2798: 2775: 2225: 2209: 1887: 1480: 819: 287: 1556:"TYPSA-Italferr JV Wins Kanpur & Agra Metro's General Consultancy" 832: 3035: 2030: 2025: 857:
July 2016: Detailed Project Report submitted to the State Government.
429: 425: 1223:"Agra Metro – Information, Route Maps, Fares, Tenders & Updates" 2929: 1065:"Agra Metro - Information, Route Map, Fares, Tenders & Updates" 1051:"Agra Metro - Information, Route Map, Fares, Tenders & Updates" 863:
January 2018: The UP Government Cabinet decides to build metros in
1712:"EIB agrees to fund 480 million euros for Agra Metro Rail Project" 915:
15 June 2020: TYPSA - Italferr JV wins General Consultant contract
2120: 1960: 1449:"Adityanath thanks Modi for clearing Agra, Kanpur Metro projects" 868: 864: 786: 457:
8,379.62 crore and the project will be completed in five years.
2528: 2245: 960: 392: 378: 352: 2240: 2017: 1983: 1938: 1933: 1362:"Centre rejects metro rail project report - Times of India" 1090:"Agra Metro: Information, Route Maps & Project Updates" 465: 344: 281: 105: 95: 908:, Taj Trapezium Zone Authority (TTZ), Forest department, 173: 1392:"UP to Start Metro Services in Agra, Kanpur and Meerut" 1307:"Decks cleared for Agra Metro project, with conditions" 1271: 1269: 409:
inaugurated the first stretch of Agra Metro Project.
16:
Mass rapid transit system in the city of Agra, India
2665:
Delhi–Sonipat–Panipat Regional Rapid Transit System
487:The Agra Metro became operational on 6 March 2024. 1266: 1172:"Centre approves Agra, Kanpur metro rail projects" 1146:"Kanpur & Agra metro projects get cabinet nod" 1118:[Metro project remains pending in Agra]. 877:7 February 2019: The UP Government has allocated 3235: 468:stations and will have a feeder network of bus, 1332:"Uttar Pradesh govt gets DPRs for Meerut, Agra" 391:As of July 2016, DPR has been prepared by 881:175 crore to start preliminary work in budget. 2511: 1903: 1840:"Agra witnesses first Metro train trial run" 1660:"EIB to fund Agra metro rail project: UPMRC" 1418: 1189: 887:8 March 2019: Foundation stone laid down by 2623:Delhi–Meerut Regional Rapid Transit System 2518: 2504: 1910: 1896: 1441: 1247:Rao, Lingamgunta Nirmitha (6 March 2024). 2660:Delhi–Alwar Regional Rapid Transit System 417:The cost of construction is estimated at 355:. The metro is owned and operated by the 1917: 1152:. Press Trust of India. 28 February 2019 831: 499: 377: 3244:Proposed rapid transit in Uttar Pradesh 443:Highlights of these corridors include: 395:and submitted to the state government. 3236: 2569:Hyderabad Multi-Modal Transport System 2344:Cities and towns in Firozabad district 1116:"मेट्रो का सपना कहीं सपना ही न रह जाए" 2499: 2349:Cities and towns in Mainpuri district 1891: 453:The estimated cost of the project is 412: 2354:Cities and towns in Mathura district 1342:from the original on 6 February 2017 1304: 1007:Uttar Pradesh Metro Rail Corporation 357:Uttar Pradesh Metro Rail Corporation 86:Uttar Pradesh Metro Rail Corporation 18: 1580: 1372:from the original on 9 October 2017 1246: 13: 2582:Barabanki–Lucknow Suburban Railway 1122:. 16 February 2016. Archived from 988:July 2023 : Trial run begins. 711: 14: 3270: 2129:Krishna Janmasthan Temple Complex 1997:United Provinces of Agra and Oudh 851: 592: 504:Mankameshwar Temple Metro Station 3254:Standard gauge railways in India 2527: 1419:Anurag Gupta (8 February 2019). 1406:"UP govt sent DPR to Union govt" 827: 490: 432:, and Sikandra as well as ISBT, 320: 234:7.0 km (priority corridor) 65: 23: 2587:Lucknow–Kanpur Suburban Railway 1858: 1832: 1806: 1781: 1755: 1729: 1704: 1678: 1652: 1626: 1600: 1574: 1548: 1522: 1496: 1468: 1412: 1398: 1384: 1354: 1324: 476:(VCF) through the mechanism of 438:Agra Cantonment railway station 3081:Thiruvananthapuram Light Metro 2364:Villages in Firozabad district 1581:Rai, M. K. (23 October 2020). 1240: 1215: 1164: 1138: 1108: 1082: 1057: 1043: 910:Archaeological Survey of India 482:transfer of development rights 297:34.0 km/h (21.1 mph) 1: 1036: 470:intermediate public transport 434:Raja Ki Mandi railway station 405:6 March 2024: Prime Minister 2369:Villages in Mathura district 2134:Vrindavan Chandrodaya Mandir 963:for Agra Metro Rail Project. 770: 478:transit-oriented development 7: 3220:27.18000000°N 78.02000000°E 2534:Urban rail transit in India 2193:Rivers, dams, lakes, canals 2111:Tourist attractions in Agra 1614:(in Hindi). 21 October 2020 1002:Urban rail transit in India 995: 718:List of Agra Metro stations 10: 3275: 3071:Kolkata Light Rail Transit 2639:Ahmedabad Suburban Railway 2618:Bengaluru Suburban Railway 2010:Places of tourist interest 1510:(in Hindi). 22 August 2019 724: 715: 495: 386: 382:Agra Metro & Taj Mahal 305:90 km/h (56 mph) 211:Elevated & Underground 3144: 3128: 3119: 3089: 3043: 3034: 2969: 2953: 2937: 2928: 2878: 2827: 2789: 2688: 2677: 2652: 2631: 2607: 2551: 2540: 2397: 2359:Villages in Agra district 2331: 2295: 2254: 2218: 2192: 2161: 2119: 2051:Tomb of I'timād-ud-Daulah 2016: 2009: 1982: 1959: 1952: 1926: 920:Bombardier Transportation 842:Bombardier Transportation 746: 705: 694: 621: 607: 599: 577: 520: 309: 301: 293: 274: 238: 228: 223: 215: 207: 189: 184: 168: 158: 133: 125: 115: 101: 91: 81: 76: 64: 59: 32:This article needs to be 3225:27.18000000; 78.02000000 3017:Tiruchirappalli Monorail 2644:Nagpur broad-gauge Metro 2574:Kolkata Suburban Railway 2559:Chennai Suburban Railway 2296:Lok Sabha constituencies 1484:(in Hindi). 8 March 2019 1283:(in Hindi). 24 July 2020 957:European Investment Bank 71:Agra metro rolling stock 2594:Mumbai Suburban Railway 2046:Tomb of Akbar the Great 1150:Business Standard India 922:won the Agra Metro and 474:value capture financing 232:29.65 km (Phase-1) 3259:2024 in rail transport 2564:Delhi Suburban Railway 2149:Krishna Balaram Mandir 906:Supreme Court of India 837: 505: 383: 195:; 6 months ago 3076:Kozhikode Light Metro 2599:Pune Suburban Railway 2379:People from Firozabad 2121:In and around Mathura 2061:Tomb of Mariam Zamani 1368:. 16 September 2017. 1305:IANS (24 July 2020). 959:(EIB) to fund 480 mn 835: 503: 381: 164:6 (priority corridor) 3066:Greater Nashik Metro 2987:Bhubaneswar Monorail 2384:People from Mainpuri 2339:Agra district topics 1793:Urban Transport News 1716:Urban Transport News 780:Mankameshwar Mandir 634:Mankameshwar Mandir 3216: /  3102:Visakhapatnam Metro 2799:Bhoj Metro (Bhopal) 2781:Rapid Metro Gurgaon 2389:People from Mathura 2287:National Highway 93 2282:National Highway 11 2144:Banke Bihari Temple 2081:Mankameshwar Temple 1974:Krishna Janmashtami 1408:. 5 September 2018. 643:Under construction 436:, Medical College, 2982:Bengaluru Monorail 2277:National Highway 3 2272:National Highway 2 2018:In and around Agra 1953:Mythology, history 1870:The Indian Express 1638:The Times of India 1560:The Metro Rail Guy 1534:The Times of India 1394:. 18 January 2018. 1366:The Times of India 1336:The Indian Express 1311:www.daijiworld.com 1227:The Metro Rail Guy 1069:The Metro Rail Guy 838: 735:First Operational 512:to Kalindi Vihar. 506: 413:Project highlights 384: 193:March 6, 2024 159:Number of stations 3249:Transport in Agra 3199: 3198: 3195: 3194: 3115: 3114: 3107:Uttarakhand Metro 3051:Chennai Metrolite 3030: 3029: 3022:Warangal Monorail 2924: 2923: 2819:Bhubaneswar Metro 2766:Navi Mumbai Metro 2673: 2672: 2493: 2492: 2219:Languages, people 2157: 2156: 2005: 2004: 1640:. 7 December 2020 1536:. 21 January 2020 1027:Delhi Meerut RRTS 970:, as of 7 August. 836:Agra Metro Inside 825: 824: 709: 708: 590: 589: 333: 332: 329: 328: 53: 52: 3266: 3231: 3230: 3228: 3227: 3226: 3221: 3217: 3214: 3213: 3212: 3209: 3126: 3125: 3041: 3040: 3002:Kolkata Monorail 2961:Chennai Monorail 2935: 2934: 2840:Coimbatore Metro 2835:Chandigarh Metro 2686: 2685: 2549: 2548: 2532: 2531: 2520: 2513: 2506: 2497: 2496: 2374:People from Agra 2262:Grand Trunk Road 2014: 2013: 1957: 1956: 1912: 1905: 1898: 1889: 1888: 1882: 1881: 1879: 1877: 1862: 1856: 1855: 1853: 1851: 1836: 1830: 1829: 1827: 1825: 1810: 1804: 1803: 1801: 1799: 1785: 1779: 1778: 1776: 1774: 1759: 1753: 1752: 1750: 1748: 1733: 1727: 1726: 1724: 1722: 1708: 1702: 1701: 1699: 1697: 1682: 1676: 1675: 1673: 1671: 1656: 1650: 1649: 1647: 1645: 1630: 1624: 1623: 1621: 1619: 1604: 1598: 1597: 1595: 1593: 1578: 1572: 1571: 1569: 1567: 1552: 1546: 1545: 1543: 1541: 1526: 1520: 1519: 1517: 1515: 1500: 1494: 1493: 1491: 1489: 1472: 1466: 1465: 1463: 1461: 1445: 1439: 1438: 1436: 1434: 1416: 1410: 1409: 1402: 1396: 1395: 1388: 1382: 1381: 1379: 1377: 1358: 1352: 1351: 1349: 1347: 1328: 1322: 1321: 1319: 1317: 1302: 1293: 1292: 1290: 1288: 1273: 1264: 1263: 1261: 1259: 1244: 1238: 1237: 1235: 1233: 1219: 1213: 1212: 1210: 1208: 1193: 1187: 1186: 1184: 1182: 1168: 1162: 1161: 1159: 1157: 1142: 1136: 1135: 1133: 1131: 1112: 1106: 1105: 1103: 1101: 1086: 1080: 1079: 1077: 1075: 1061: 1055: 1054: 1047: 880: 814: 812: 811: 807: 804: 796: 764: 756:Electrification 722: 721: 671: 626: 597: 596: 559: 536: 515: 514: 456: 420: 401: 324: 311: 310: 270: 264: 262: 261: 257: 254: 246: 203: 201: 196: 180: 177: 175: 152: 151: 143: 69: 57: 56: 48: 45: 39: 27: 26: 19: 3274: 3273: 3269: 3268: 3267: 3265: 3264: 3263: 3234: 3233: 3224: 3222: 3218: 3215: 3210: 3207: 3205: 3203: 3202: 3200: 3191: 3140: 3111: 3097:Prayagraj Metro 3085: 3061:Gorakhpur Metro 3056:Delhi Metrolite 3026: 2997:Kanpur Monorail 2992:Indore Monorail 2977:Aizawl Monorail 2965: 2949: 2945:Mumbai Monorail 2920: 2874: 2845:Gorakhpur Metro 2823: 2791: 2785: 2726:Hyderabad Metro 2706:Bengaluru Metro 2701:Ahmedabad Metro 2680: 2669: 2648: 2627: 2611: 2609: 2603: 2543: 2536: 2526: 2524: 2494: 2489: 2398:Other divisions 2393: 2327: 2291: 2250: 2214: 2188: 2153: 2115: 2001: 1978: 1961:Mathura related 1948: 1944:Saman Sanctuary 1922: 1916: 1886: 1885: 1875: 1873: 1864: 1863: 1859: 1849: 1847: 1844:Hindustan Times 1838: 1837: 1833: 1823: 1821: 1812: 1811: 1807: 1797: 1795: 1787: 1786: 1782: 1772: 1770: 1761: 1760: 1756: 1746: 1744: 1735: 1734: 1730: 1720: 1718: 1710: 1709: 1705: 1695: 1693: 1684: 1683: 1679: 1669: 1667: 1664:Hindustan Times 1658: 1657: 1653: 1643: 1641: 1632: 1631: 1627: 1617: 1615: 1606: 1605: 1601: 1591: 1589: 1587:Metro Rail News 1579: 1575: 1565: 1563: 1554: 1553: 1549: 1539: 1537: 1528: 1527: 1523: 1513: 1511: 1502: 1501: 1497: 1487: 1485: 1474: 1473: 1469: 1459: 1457: 1447: 1446: 1442: 1432: 1430: 1417: 1413: 1404: 1403: 1399: 1390: 1389: 1385: 1375: 1373: 1360: 1359: 1355: 1345: 1343: 1338:. 1 July 2016. 1330: 1329: 1325: 1315: 1313: 1303: 1296: 1286: 1284: 1275: 1274: 1267: 1257: 1255: 1253:Hindustan Times 1245: 1241: 1231: 1229: 1221: 1220: 1216: 1206: 1204: 1195: 1194: 1190: 1180: 1178: 1170: 1169: 1165: 1155: 1153: 1144: 1143: 1139: 1129: 1127: 1114: 1113: 1109: 1099: 1097: 1096:. 8 August 2023 1094:Metro Rail News 1088: 1087: 1083: 1073: 1071: 1063: 1062: 1058: 1049: 1048: 1044: 1039: 998: 968:Indian Railways 878: 854: 830: 809: 805: 802: 800: 799:4 ft  798: 794: 762: 738:Last Extension 727: 720: 714: 712:Current network 669: 624: 595: 557: 534: 498: 493: 454: 418: 415: 402:8379.62 crore. 399: 389: 276:Electrification 266: 259: 255: 252: 250: 249:4 ft  248: 244: 233: 199: 197: 194: 190:Began operation 172: 163: 147: 146: 139: 126:Number of lines 72: 49: 43: 40: 37: 28: 24: 17: 12: 11: 5: 3272: 3262: 3261: 3256: 3251: 3246: 3208:27°10′48.000″N 3197: 3196: 3193: 3192: 3190: 3189: 3184: 3179: 3174: 3169: 3164: 3159: 3154: 3152:Bhavnagar Tram 3148: 3146: 3142: 3141: 3139: 3138: 3132: 3130: 3123: 3117: 3116: 3113: 3112: 3110: 3109: 3104: 3099: 3093: 3091: 3087: 3086: 3084: 3083: 3078: 3073: 3068: 3063: 3058: 3053: 3047: 3045: 3038: 3032: 3031: 3028: 3027: 3025: 3024: 3019: 3014: 3009: 3007:Patna Monorail 3004: 2999: 2994: 2989: 2984: 2979: 2973: 2971: 2967: 2966: 2964: 2963: 2957: 2955: 2951: 2950: 2948: 2947: 2941: 2939: 2932: 2926: 2925: 2922: 2921: 2919: 2918: 2913: 2908: 2903: 2901:Srinagar Metro 2898: 2893: 2888: 2886:Bareilly Metro 2882: 2880: 2876: 2875: 2873: 2872: 2870:Varanasi Metro 2867: 2862: 2860:Ludhiana Metro 2857: 2855:Jabalpur Metro 2852: 2850:Guwahati Metro 2847: 2842: 2837: 2831: 2829: 2825: 2824: 2822: 2821: 2816: 2811: 2806: 2801: 2795: 2793: 2787: 2786: 2784: 2783: 2778: 2773: 2768: 2763: 2758: 2753: 2748: 2743: 2738: 2733: 2728: 2723: 2718: 2713: 2708: 2703: 2698: 2692: 2690: 2683: 2675: 2674: 2671: 2670: 2668: 2667: 2662: 2656: 2654: 2650: 2649: 2647: 2646: 2641: 2635: 2633: 2629: 2628: 2626: 2625: 2620: 2614: 2612: 2605: 2604: 2602: 2601: 2596: 2591: 2590: 2589: 2584: 2576: 2571: 2566: 2561: 2555: 2553: 2546: 2538: 2537: 2523: 2522: 2515: 2508: 2500: 2491: 2490: 2488: 2487: 2482: 2477: 2472: 2467: 2462: 2457: 2452: 2447: 2442: 2437: 2432: 2427: 2422: 2417: 2412: 2407: 2401: 2399: 2395: 2394: 2392: 2391: 2386: 2381: 2376: 2371: 2366: 2361: 2356: 2351: 2346: 2341: 2335: 2333: 2329: 2328: 2326: 2325: 2320: 2315: 2313:Fatehpur Sikri 2310: 2305: 2299: 2297: 2293: 2292: 2290: 2289: 2284: 2279: 2274: 2269: 2264: 2258: 2256: 2252: 2251: 2249: 2248: 2243: 2238: 2236:Standard Hindi 2233: 2228: 2222: 2220: 2216: 2215: 2213: 2212: 2207: 2202: 2196: 2194: 2190: 2189: 2187: 2186: 2181: 2176: 2171: 2165: 2163: 2159: 2158: 2155: 2154: 2152: 2151: 2146: 2141: 2136: 2131: 2125: 2123: 2117: 2116: 2114: 2113: 2108: 2103: 2098: 2093: 2088: 2083: 2078: 2073: 2068: 2063: 2058: 2056:Chini Ka Rauza 2053: 2048: 2043: 2041:Buland Darwaza 2038: 2036:Fatehpur Sikri 2033: 2028: 2022: 2020: 2011: 2007: 2006: 2003: 2002: 2000: 1999: 1994: 1988: 1986: 1980: 1979: 1977: 1976: 1971: 1965: 1963: 1954: 1950: 1949: 1947: 1946: 1941: 1936: 1930: 1928: 1924: 1923: 1915: 1914: 1907: 1900: 1892: 1884: 1883: 1872:. 6 March 2024 1857: 1846:. 11 July 2023 1831: 1805: 1780: 1754: 1728: 1703: 1677: 1666:. 29 July 2021 1651: 1625: 1599: 1573: 1562:. 15 June 2020 1547: 1521: 1495: 1467: 1440: 1426:Dainik Jagaran 1411: 1397: 1383: 1353: 1323: 1294: 1265: 1239: 1214: 1203:. 5 March 2024 1188: 1163: 1137: 1126:on 3 July 2017 1120:Agra City News 1107: 1081: 1056: 1041: 1040: 1038: 1035: 1034: 1033: 1032: 1031: 1030: 1029: 1024: 1019: 1014: 997: 994: 993: 992: 989: 986: 983: 980: 977: 974: 971: 964: 953: 949: 945: 941: 937: 933: 930: 927: 916: 913: 902: 895: 889:Prime Minister 885: 882: 875: 872: 861: 858: 853: 852:Status updates 850: 829: 826: 823: 822: 816: 792: 784: 783:Taj East Gate 781: 778: 775: 772: 769: 766: 758: 757: 754: 751: 750:Rolling Stock 748: 745: 742: 739: 736: 733: 729: 728: 725: 716:Main article: 713: 710: 707: 706: 704: 701: 700:29.67 km 698: 692: 691: 688: 685: 684:15.40 km 682: 681:Kalindi Vihar 679: 674: 664: 663: 660: 657: 654: 653:Taj East Gate 651: 645: 644: 641: 638: 635: 632: 629: 619: 618: 615: 612: 609: 606: 602: 601: 594: 593:Current phases 591: 588: 587: 584: 583:29.67 km 581: 575: 574: 571: 570:15.40 km 568: 567:Kalindi Vihar 565: 562: 552: 551: 548: 547:14.27 km 545: 544:Taj East Gate 542: 539: 529: 528: 525: 522: 519: 497: 494: 492: 489: 459: 458: 451: 448: 414: 411: 388: 385: 331: 330: 327: 326: 316: 315: 307: 306: 303: 299: 298: 295: 291: 290: 278: 272: 271: 268:standard gauge 242: 236: 235: 230: 226: 225: 221: 220: 217: 213: 212: 209: 205: 204: 191: 187: 186: 182: 181: 170: 166: 165: 160: 156: 155: 154: 153: 144: 135: 131: 130: 127: 123: 122: 117: 113: 112: 103: 99: 98: 93: 89: 88: 83: 79: 78: 74: 73: 70: 62: 61: 51: 50: 31: 29: 22: 15: 9: 6: 4: 3: 2: 3271: 3260: 3257: 3255: 3252: 3250: 3247: 3245: 3242: 3241: 3239: 3232: 3229: 3211:78°1′12.000″E 3188: 3185: 3183: 3180: 3178: 3175: 3173: 3170: 3168: 3165: 3163: 3160: 3158: 3155: 3153: 3150: 3149: 3147: 3143: 3137: 3134: 3133: 3131: 3127: 3124: 3122: 3118: 3108: 3105: 3103: 3100: 3098: 3095: 3094: 3092: 3088: 3082: 3079: 3077: 3074: 3072: 3069: 3067: 3064: 3062: 3059: 3057: 3054: 3052: 3049: 3048: 3046: 3042: 3039: 3037: 3033: 3023: 3020: 3018: 3015: 3013: 3012:Pune Monorail 3010: 3008: 3005: 3003: 3000: 2998: 2995: 2993: 2990: 2988: 2985: 2983: 2980: 2978: 2975: 2974: 2972: 2968: 2962: 2959: 2958: 2956: 2952: 2946: 2943: 2942: 2940: 2936: 2933: 2931: 2927: 2917: 2914: 2912: 2911:Madurai Metro 2909: 2907: 2904: 2902: 2899: 2897: 2894: 2892: 2889: 2887: 2884: 2883: 2881: 2877: 2871: 2868: 2866: 2863: 2861: 2858: 2856: 2853: 2851: 2848: 2846: 2843: 2841: 2838: 2836: 2833: 2832: 2830: 2826: 2820: 2817: 2815: 2812: 2810: 2807: 2805: 2802: 2800: 2797: 2796: 2794: 2788: 2782: 2779: 2777: 2774: 2772: 2769: 2767: 2764: 2762: 2759: 2757: 2754: 2752: 2751:Lucknow Metro 2749: 2747: 2746:Kolkata Metro 2744: 2742: 2739: 2737: 2734: 2732: 2729: 2727: 2724: 2722: 2719: 2717: 2714: 2712: 2711:Chennai Metro 2709: 2707: 2704: 2702: 2699: 2697: 2694: 2693: 2691: 2687: 2684: 2682: 2676: 2666: 2663: 2661: 2658: 2657: 2655: 2651: 2645: 2642: 2640: 2637: 2636: 2634: 2630: 2624: 2621: 2619: 2616: 2615: 2613: 2606: 2600: 2597: 2595: 2592: 2588: 2585: 2583: 2580: 2579: 2577: 2575: 2572: 2570: 2567: 2565: 2562: 2560: 2557: 2556: 2554: 2550: 2547: 2545: 2539: 2535: 2530: 2521: 2516: 2514: 2509: 2507: 2502: 2501: 2498: 2486: 2483: 2481: 2478: 2476: 2473: 2471: 2468: 2466: 2463: 2461: 2458: 2456: 2453: 2451: 2448: 2446: 2443: 2441: 2438: 2436: 2433: 2431: 2428: 2426: 2423: 2421: 2418: 2416: 2413: 2411: 2408: 2406: 2403: 2402: 2400: 2396: 2390: 2387: 2385: 2382: 2380: 2377: 2375: 2372: 2370: 2367: 2365: 2362: 2360: 2357: 2355: 2352: 2350: 2347: 2345: 2342: 2340: 2337: 2336: 2334: 2330: 2324: 2321: 2319: 2316: 2314: 2311: 2309: 2306: 2304: 2301: 2300: 2298: 2294: 2288: 2285: 2283: 2280: 2278: 2275: 2273: 2270: 2268: 2265: 2263: 2260: 2259: 2257: 2253: 2247: 2244: 2242: 2239: 2237: 2234: 2232: 2229: 2227: 2224: 2223: 2221: 2217: 2211: 2208: 2206: 2203: 2201: 2198: 2197: 2195: 2191: 2185: 2182: 2180: 2177: 2175: 2172: 2170: 2167: 2166: 2164: 2160: 2150: 2147: 2145: 2142: 2140: 2137: 2135: 2132: 2130: 2127: 2126: 2124: 2122: 2118: 2112: 2109: 2107: 2104: 2102: 2099: 2097: 2094: 2092: 2089: 2087: 2084: 2082: 2079: 2077: 2074: 2072: 2069: 2067: 2064: 2062: 2059: 2057: 2054: 2052: 2049: 2047: 2044: 2042: 2039: 2037: 2034: 2032: 2029: 2027: 2024: 2023: 2021: 2019: 2015: 2012: 2008: 1998: 1995: 1993: 1992:Mughal Empire 1990: 1989: 1987: 1985: 1981: 1975: 1972: 1970: 1967: 1966: 1964: 1962: 1958: 1955: 1951: 1945: 1942: 1940: 1937: 1935: 1932: 1931: 1929: 1925: 1920: 1919:Agra division 1913: 1908: 1906: 1901: 1899: 1894: 1893: 1890: 1871: 1867: 1861: 1845: 1841: 1835: 1819: 1815: 1809: 1794: 1790: 1784: 1768: 1764: 1758: 1742: 1741:Dainik Jagran 1738: 1732: 1717: 1713: 1707: 1691: 1690:Dainik Jagran 1687: 1681: 1665: 1661: 1655: 1639: 1635: 1629: 1613: 1609: 1603: 1588: 1584: 1577: 1561: 1557: 1551: 1535: 1531: 1525: 1509: 1508:Dainik Jagran 1505: 1499: 1483: 1482: 1477: 1471: 1456: 1455: 1450: 1444: 1428: 1427: 1422: 1415: 1407: 1401: 1393: 1387: 1371: 1367: 1363: 1357: 1341: 1337: 1333: 1327: 1312: 1308: 1301: 1299: 1282: 1281:Dainik Jagran 1278: 1272: 1270: 1254: 1250: 1243: 1228: 1224: 1218: 1202: 1198: 1192: 1177: 1173: 1167: 1151: 1147: 1141: 1125: 1121: 1117: 1111: 1095: 1091: 1085: 1070: 1066: 1060: 1052: 1046: 1042: 1028: 1025: 1023: 1020: 1018: 1015: 1013: 1012:Lucknow Metro 1010: 1009: 1008: 1005: 1004: 1003: 1000: 999: 990: 987: 984: 981: 978: 975: 972: 969: 965: 962: 958: 954: 950: 946: 942: 938: 934: 931: 928: 925: 921: 917: 914: 911: 907: 903: 900: 897:August 2019: 896: 893: 892:Narendra Modi 890: 886: 883: 876: 873: 870: 866: 862: 859: 856: 855: 849: 847: 846:Supreme Court 843: 834: 828:Rolling stock 821: 817: 795:1,435 mm 793: 791: 788: 785: 782: 779: 776: 773: 768:6 March 2024 767: 765: 760: 759: 755: 752: 749: 743: 740: 737: 734: 731: 730: 723: 719: 702: 699: 697: 693: 689: 686: 683: 680: 678: 675: 673: 672: 666: 665: 662:6 March 2024 661: 658: 655: 652: 650: 647: 646: 642: 639: 637:9.07 km 636: 633: 630: 628: 627: 620: 617:Opening Date 616: 613: 610: 604: 603: 598: 585: 582: 580: 576: 572: 569: 566: 563: 561: 560: 554: 553: 549: 546: 543: 540: 538: 537: 531: 530: 526: 523: 517: 516: 513: 511: 502: 491:Route network 488: 485: 483: 479: 475: 471: 467: 462: 452: 449: 446: 445: 444: 441: 439: 435: 431: 427: 422: 410: 408: 407:Narendra Modi 403: 396: 394: 380: 376: 374: 370: 366: 362: 361:Lucknow Metro 358: 354: 350: 349:Uttar Pradesh 346: 342: 341:rapid transit 338: 325: 323: 318: 317: 313: 312: 308: 304: 300: 296: 294:Average speed 292: 289: 286: 283: 279: 277: 273: 269: 245:1,435 mm 243: 241: 237: 231: 229:System length 227: 222: 218: 214: 210: 206: 192: 188: 183: 179: 171: 167: 161: 157: 150: 145: 142: 138: 137: 136: 132: 128: 124: 121: 120:Rapid transit 118: 114: 111: 110:Uttar Pradesh 107: 104: 100: 97: 94: 90: 87: 84: 80: 75: 68: 63: 58: 55: 47: 35: 30: 21: 20: 3201: 3157:Chennai Tram 3136:Kolkata Tram 2916:Trichy Metro 2896:Ranchi Metro 2865:Meerut Metro 2804:Indore Metro 2792:construction 2761:Nagpur Metro 2756:Mumbai Metro 2736:Kanpur Metro 2731:Jaipur Metro 2716:Chennai MRTS 2695: 2610:construction 2266: 2205:Keetham Lake 2106:Taj Mahotsav 2101:Paliwal Park 1984:Agra related 1874:. Retrieved 1869: 1860: 1848:. Retrieved 1843: 1834: 1822:. Retrieved 1817: 1808: 1796:. Retrieved 1792: 1783: 1773:28 September 1771:. Retrieved 1766: 1757: 1747:28 September 1745:. Retrieved 1740: 1731: 1721:28 September 1719:. Retrieved 1715: 1706: 1696:28 September 1694:. Retrieved 1689: 1680: 1670:28 September 1668:. Retrieved 1663: 1654: 1642:. Retrieved 1637: 1628: 1616:. Retrieved 1611: 1602: 1590:. Retrieved 1586: 1576: 1564:. Retrieved 1559: 1550: 1538:. Retrieved 1533: 1524: 1512:. Retrieved 1507: 1498: 1486:. Retrieved 1479: 1470: 1458:. Retrieved 1452: 1443: 1431:. Retrieved 1424: 1414: 1400: 1386: 1374:. Retrieved 1365: 1356: 1344:. Retrieved 1335: 1326: 1314:. Retrieved 1310: 1285:. Retrieved 1280: 1256:. Retrieved 1252: 1242: 1230:. Retrieved 1226: 1217: 1205:. Retrieved 1200: 1191: 1179:. Retrieved 1175: 1166: 1154:. Retrieved 1149: 1140: 1128:. Retrieved 1124:the original 1119: 1110: 1098:. Retrieved 1093: 1084: 1072:. Retrieved 1068: 1059: 1045: 1022:Meerut Metro 1017:Kanpur Metro 924:Kanpur Metro 839: 777:5.2 km 753:Track Gauge 695: 667: 649:Mankameshwar 622: 578: 555: 532: 507: 486: 463: 460: 442: 423: 416: 404: 397: 390: 369:Kanpur Metro 365:Meerut Metro 336: 334: 319: 216:Train length 162:27 (Phase 1) 148: 140: 116:Transit type 54: 41: 33: 3223: / 3182:Nashik Tram 3177:Mumbai Tram 3167:Kanpur Tram 3129:Operational 2938:Operational 2906:Thane Metro 2891:Jammu Metro 2814:Surat Metro 2809:Patna Metro 2771:Noida Metro 2741:Kochi Metro 2721:Delhi Metro 2689:Operational 2552:Operational 2139:Prem Mandir 2096:Mehtab Bagh 2086:Guru ka Tal 2076:Moti Masjid 2071:Jama Masjid 2066:Gyarah Sidi 1232:19 December 1181:28 February 1156:28 February 955:July 2021: 918:July 2020: 871:, and Agra. 763:Yellow Line 625:Yellow Line 564:Agra Cantt 535:Yellow Line 373:Noida Metro 240:Track gauge 141:Yellow Line 134:Line number 92:Area served 3238:Categories 3187:Patna Tram 3172:Kochi Tram 3162:Delhi Tram 2776:Pune Metro 2696:Agra Metro 2480:Saharanpur 2430:Chitrakoot 2267:Agra Metro 2231:Hindustani 2226:Braj Bhasa 2210:Agra Canal 1824:6 December 1820:(in Hindi) 1818:Amar Ujala 1798:23 October 1769:(in Hindi) 1767:Amar Ujala 1743:(in Hindi) 1692:(in Hindi) 1644:7 December 1618:30 October 1612:Amar Ujala 1592:30 October 1540:29 January 1481:Amar Ujala 1429:(in Hindi) 1176:aninews.in 1037:References 820:third rail 732:Line Name 726:Agra Metro 677:Agra Cantt 656:6 km 608:Terminals 605:Line Name 541:Sikandara 521:Terminals 518:Line Name 510:Agra Cantt 480:(TOD) and 343:system in 337:Agra Metro 314:System map 288:third rail 200:2024-03-06 60:Agra Metro 44:March 2024 3036:Metrolite 2475:Prayagraj 2470:Moradabad 2440:Gorakhpur 2435:Devipatan 2308:Firozabad 2255:Transport 2174:Firozabad 2162:Districts 2031:Agra Fort 2026:Taj Mahal 1514:29 August 1376:9 October 1346:9 October 1316:16 August 1287:16 August 1130:9 October 936:stations. 840:In 2020, 818:750 V DC 747:Terminal 670:Blue Line 631:Sikandra 614:Stations 558:Blue Line 527:Stations 430:Agra Fort 426:Taj Mahal 302:Top speed 224:Technical 219:3 Coaches 208:Character 185:Operation 149:Blue Line 3090:Proposed 2970:Proposed 2930:Monorail 2879:Proposed 2653:Proposed 2578:Lucknow 2542:Suburban 2485:Varanasi 2465:Mirzapur 2420:Bareilly 2415:Azamgarh 2332:See also 2323:Mainpuri 2179:Mainpuri 2091:Ram Bagh 1488:20 March 1460:20 March 1433:20 March 1370:Archived 1340:Archived 996:See also 813: in 741:Station 690:Planned 600:Phase 1 263: in 77:Overview 3145:Defunct 3044:Planned 2954:Planned 2828:Planned 2681:transit 2632:Planned 2455:Lucknow 2410:Ayodhya 2405:Aligarh 2318:Mathura 2184:Mathura 1969:Krishna 1927:General 1876:6 March 1850:12 July 1566:15 June 1454:Outlook 1258:6 March 1207:5 March 1100:6 March 1074:6 March 808:⁄ 744:Length 611:Length 524:Length 496:Phase 1 484:(TDR). 387:History 258:⁄ 198: ( 169:Website 34:updated 2460:Meerut 2450:Kanpur 2445:Jhansi 2200:Yamuna 1921:topics 869:Kanpur 865:Meerut 787:Alstom 371:, and 176:.lmrcl 102:Locale 2790:Under 2679:Rapid 2608:Under 2425:Basti 2246:Jatav 961:euros 790:MOVIA 696:Total 579:Total 393:RITES 353:India 339:is a 82:Owner 3121:Tram 2544:rail 2303:Agra 2241:Urdu 2169:Agra 1939:Braj 1934:Doab 1878:2024 1852:2023 1826:2021 1800:2021 1775:2021 1749:2021 1723:2021 1698:2021 1672:2021 1646:2020 1620:2020 1594:2020 1568:2020 1542:2020 1516:2019 1490:2019 1462:2019 1435:2019 1378:2017 1348:2017 1318:2020 1289:2020 1260:2024 1234:2020 1209:2024 1201:Mint 1183:2019 1158:2019 1132:2017 1102:2024 1076:2024 899:LMRC 771:N/A 466:BRTS 345:Agra 335:The 280:750 178:.com 106:Agra 96:Agra 703:28 687:15 586:28 573:15 550:13 174:www 3240:: 1868:. 1842:. 1816:. 1791:. 1765:. 1739:. 1714:. 1688:. 1662:. 1636:. 1610:. 1585:. 1558:. 1532:. 1506:. 1478:. 1451:. 1423:. 1364:. 1334:. 1309:. 1297:^ 1279:. 1268:^ 1251:. 1225:. 1199:. 1174:. 1148:. 1092:. 1067:. 867:, 815:) 774:6 659:6 640:7 428:, 375:. 367:, 363:, 351:, 347:, 285:DC 265:) 108:, 2519:e 2512:t 2505:v 1911:e 1904:t 1897:v 1880:. 1854:. 1828:. 1802:. 1777:. 1751:. 1725:. 1700:. 1674:. 1648:. 1622:. 1596:. 1570:. 1544:. 1518:. 1492:. 1464:. 1437:. 1380:. 1350:. 1320:. 1291:. 1262:. 1236:. 1211:. 1185:. 1160:. 1134:. 1104:. 1078:. 1053:. 894:. 879:₹ 810:2 806:1 803:+ 801:8 797:( 455:₹ 419:₹ 400:₹ 282:V 260:2 256:1 253:+ 251:8 247:( 202:) 129:2 46:) 42:( 36:.

Index

Agra metro rolling stock
Uttar Pradesh Metro Rail Corporation
Agra
Agra
Uttar Pradesh
Rapid transit
www.lmrcl.com
Track gauge
standard gauge
Electrification
V
DC
third rail
Represents Agra metro route with updated station name.
rapid transit
Agra
Uttar Pradesh
India
Uttar Pradesh Metro Rail Corporation
Lucknow Metro
Meerut Metro
Kanpur Metro
Noida Metro

RITES
Narendra Modi
Taj Mahal
Agra Fort
Raja Ki Mandi railway station
Agra Cantonment railway station

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.