By not affecting the existing rail service of the 177 trains per day using the corridor, a risk of loss of ridership was removed that could have occurred in relation to potential delays. Long and short distance travellers were continuously able to get to their destinations as planned, which helped to
108:
A key component in building the tunnel was the readily available supply of precast deck segments nearby. The project required 1.6 kilometres of girders so Soncin, who was contracted by Fairmont Developments to construct the extension of Simcoe Street, built a precast facility on site. A total of 153
116:
corridor has the highest train volume for a single terminus location in North America. It was necessary to maintain the normal operation schedule of the railway corridor during construction. In order to not cause any disruption to the operation of 16 tracks, construction was scheduled during train
166:
waterfront within the City of Toronto. The original rail corridor was a major physical barrier between the downtown and the lakefront where continuous residential, recreational and business developments are occurring. The tunnel reduces the length of vehicular travel time and associated carbon
104:
Construction of the tunnel began in late 2006 and was carried out in stages. Thin soil cover prohibited the use of bored tunnel and hacked tunnel methods. For each stage the substructure was first constructed within the excavated trenches to the underside of the temporary trestles.
174:
was quoted saying “The Simcoe Street underpass will improve downtown traffic flow and help provide important services to future development on the lands south of Union Station. But most importantly, the project will improve access to our waterfront for all Torontonians."
80:
hotel. The tunnel roof structure is designed to carry all 16 pre-existing railway tracks. The ground structure provides one vehicle lane north bound and two lanes south bound, one bicycle lane and one extra wide pedestrian sidewalk on each side of the tunnel.
157:
To help protect the environment during construction of the tunnel a Quality Management Plan was set in place. This plan ensured all waste materials were disposed of according to government regulations. Disposal techniques were also monitored for compliance.
246: 137:
to ensure the services of 177 daily scheduled trains that passed over the tunnel were maintained. Some trains were temporarily rerouted to adjacent tracks.
319: 294: 273: 358: 162:
avoid an increase in the use of personal vehicles. A lasting environmental impact after construction is the improved access to the
213: 187: 121:
the project managers, designers, contract administrators and site engineers, worked with the railway companies including
171: 109:
girders were produced in three months. Fifty-one girders were post tensioned and 102 girders were normally reinforced.
368: 77: 373: 363: 178:
According to the city report published in 2014, the underpass was flooded 5 times between 2010 and 2013.
126: 113: 167:
emissions, and the new ease of access promotes carbon-free travel, i.e., bicycling and walking.
8: 118: 192: 247:"Commuter traffic will gain new corridor as work done daily underfoot and undercover" 96: 84:
The Simcoe Street tunnel was officially opened on September 22, 2009 by Councillor
352: 334: 321: 218: 163: 85: 112:
Design and construction of the tunnel posed significant challenges as the
150: 134: 298: 145: 122: 73: 65: 130: 295:"Flooding on Lower Simcoe underpass 'warning sign,' Tory says" 268: 266: 264: 100:
The Simcoe Street Tunnel while it was under construction.
76:
and in close proximity to Toronto Union Station and the
261: 72:
tunnel is situated in a densely urban site below the
64:
is located between Front Street and Bremner Blvd. in
140: 350: 240: 238: 236: 233: 205: 144: 95: 244: 16:Road tunnel in Toronto, Ontario, Canada 351: 211: 153:train passing over the Simcoe Tunnel. 245:Versace, Vince (February 28, 2008). 188:Lower Simcoe Street underpass murals 359:Buildings and structures in Toronto 13: 274:"Simcoe Street underpass now open" 212:Hanes, Allison (August 19, 2009). 14: 385: 141:Environmental and social impacts 91: 78:InterContinental Toronto Centre 287: 1: 198: 7: 181: 10: 390: 170:Former Mayor of Toronto, 127:Canadian National Railway 50: 45: 37: 29: 24: 68:, Ontario, Canada. This 369:Road tunnels in Ontario 249:. Daily Commercial News 335:43.64361°N 79.384583°W 154: 101: 148: 99: 374:Transport in Toronto 364:Geography of Toronto 340:43.64361; -79.384583 62:Simcoe Street tunnel 20:Simcoe Street Tunnel 331: /  119:Morrison Hershfield 21: 214:"Simcoe Underpass" 193:Toronto Waterfront 155: 102: 19: 58: 57: 381: 346: 345: 343: 342: 341: 336: 332: 329: 328: 327: 324: 311: 310: 308: 306: 291: 285: 284: 282: 281: 270: 259: 258: 256: 254: 242: 231: 230: 228: 226: 209: 71: 22: 18: 389: 388: 384: 383: 382: 380: 379: 378: 349: 348: 339: 337: 333: 330: 325: 322: 320: 318: 317: 315: 314: 304: 302: 301:. July 28, 2016 293: 292: 288: 279: 277: 276:. National Post 272: 271: 262: 252: 250: 243: 234: 224: 222: 210: 206: 201: 184: 143: 94: 69: 17: 12: 11: 5: 387: 377: 376: 371: 366: 361: 313: 312: 286: 260: 232: 203: 202: 200: 197: 196: 195: 190: 183: 180: 142: 139: 93: 90: 70:CA$ 40 million 56: 55: 52: 48: 47: 43: 42: 39: 35: 34: 31: 27: 26: 15: 9: 6: 4: 3: 2: 386: 375: 372: 370: 367: 365: 362: 360: 357: 356: 354: 347: 344: 300: 296: 290: 275: 269: 267: 265: 248: 241: 239: 237: 221: 220: 219:National Post 215: 208: 204: 194: 191: 189: 186: 185: 179: 176: 173: 168: 165: 159: 152: 147: 138: 136: 132: 128: 124: 120: 117:work blocks. 115: 114:Union Station 110: 106: 98: 89: 87: 82: 79: 75: 67: 63: 53: 49: 44: 40: 36: 32: 28: 23: 326:79°23′04.5″W 316: 303:. Retrieved 289: 278:. Retrieved 251:. Retrieved 223:. Retrieved 217: 207: 177: 172:David Miller 169: 164:Lake Ontario 160: 156: 111: 107: 103: 92:Construction 86:Adam Vaughan 83: 61: 59: 338: / 305:February 4, 253:February 4, 225:February 4, 353:Categories 323:43°38′37″N 280:2011-03-10 199:References 151:GO Transit 135:GO Transit 46:Operation 299:CBC News 182:See also 123:Via Rail 30:Location 25:Overview 74:SkyWalk 66:Toronto 131:Amtrak 51:Opened 33:Canada 38:Start 307:2020 255:2020 227:2020 133:and 60:The 54:2009 41:2006 355:: 297:. 263:^ 235:^ 216:. 149:A 129:, 125:, 88:. 309:. 283:. 257:. 229:.

Index

Toronto
SkyWalk
InterContinental Toronto Centre
Adam Vaughan

Union Station
Morrison Hershfield
Via Rail
Canadian National Railway
Amtrak
GO Transit

GO Transit
Lake Ontario
David Miller
Lower Simcoe Street underpass murals
Toronto Waterfront
"Simcoe Underpass"
National Post



"Commuter traffic will gain new corridor as work done daily underfoot and undercover"



"Simcoe Street underpass now open"
"Flooding on Lower Simcoe underpass 'warning sign,' Tory says"
CBC News
43°38′37″N 79°23′04.5″W / 43.64361°N 79.384583°W / 43.64361; -79.384583

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.