42: 630:
It will have modern, hydroacoustic equipment, such as echo sounding, sonar, an ocean floor profiler, a current profiler, and a high-precision acoustic positioning system. It will also be outfitted with biology, microbiology, and chemistry labs, and it will have the means for collecting, storing, and
669:
Chilean defense sources said the icebreaker project to replace the 6.500 ton Almirante Viel include an initial budget of 150 million dollars and building the new 8.000 ton ice breaker with foreign technical assistance in local shipyard Asmar. Meanwhile, Marinero Fuentealba, an 1,800-ton offshore
621:
Antártica 1 will have greater capabilities for supporting high-level, onboard scientific activities which will allow it to break from the seasonality of scientific work, accessing data in real time, and analyzing the results obtained while
582:
Speaking to Jane's at Euronaval 2018 in Paris, ASMAR shipyard's chief marketing officer, Jorge Terrazas, confirmed that first steel was officially cut in August, marking the start of construction at its Talcahuano facilities in the Biobio
704:
Chilean president Michelle Bachelet cut the first sheet of steel for the construction of the country's new icebreaker which is expected to be operational for the 2022/23 Antarctic season, replacing the ageing Almirante Oscar
350:
is 111 metres (364 ft 2 in) long and has a beam and draft of 21 metres (68 ft 11 in) and 7.2 metres (23 ft 7 in). She displaces 13,000 tons. Her maximum speed is 15
692: 657: 570: 687: 652: 535: 727: 509: 606: 739:
The new vessel, to be delivered in 2021, will rival Argentina's 15,000 ton displacement Almirante Irizar, presently the largest icebreaker in South America.
682: 601: 647: 462: 556: 330: 521:
The vessel is scheduled to be completed within four years at a cost of USD217 million, according to the Chilean Ministry of Defense.
757: 631:
preserving water samples and samples from the seabed, with the capacity provided by modern and spacious refrigeration chambers,
532: 334:
acquired from Canada in 1994 and decommissioned in 2019. Accounts differ as to when construction of the ship began. The
436: 717: 499: 596: 670:
patrol vessel with reinforced hull for polar operations, is being completed by ASMAR for commissioning in August.
360:
She will be able to sail through one-year ice, one meter thick, at 2 knots (3.7 km/h; 2.3 mph).
561: 341: 17: 373: 126: 8: 722: 400: 364: 172: 238: 235: 683:"Chile cuts steel for its new 13.000 tons icebreaker to be operational in 2022/23" 539: 248: 153: 648:"Chile plans to build a new icebreaker and has earmarked an initial 150 million" 504: 336: 357:
She will have the capacity to house 150 crew and researchers or passengers.
302:
Helipad and hangar for two medium helicopters of the Super Puma or Cougar type
751: 413: 314: 224: 166: 321: 66: 557:"Euronaval 2018: ASMAR ramps up production of new Chilean Navy icebreaker" 463:"Es chileno: Así es el primer buque rompehielos construido en Sudamérica" 351: 270: 317: 149: 122: 80: 369: 276:
3 knots (5.6 km/h; 3.5 mph) in 1 m (3.3 ft) ice
566: 76: 494: 492: 490: 488: 486: 484: 368:
reports that when completed, she will be comparable to
710: 481: 431: 429: 286:
14,000 nautical miles (26,000 km; 16,000 mi)
500:"Chile cuts steel for its new 13.000 tons icebreaker" 340:
reported the first steel was cut in May 2017, while
328:, it will replace the 1969-built second-hand vessel 259:
4,500 kW (6,000 hp) main propulsion motors
675: 426: 594: 399: 455: 749: 588: 437:"Launch of Chile's first self-built icebreaker" 324:. Previously referred to with the project name 640: 548: 344:reported construction began in August 2018. 554: 718:"Chile Moves Forward with New Icebreaker" 273:(30 km/h; 18 mph) in open water 597:"Chile Builds Its First Icebreaker Ship" 394: 392: 14: 750: 533:Design of the Chilean Antarctic Vessel 526: 389: 38: 234:Four 3,400 kW (4,600 hp) 24: 216:10.6 m (34 ft 9 in) 192:111 m (364 ft 2 in) 25: 769: 595:Carolina Contreras (2017-07-20). 208:7.2 m (23 ft 7 in) 200:21 m (68 ft 11 in) 40: 758:Icebreakers of the Chilean Navy 730:from the original on 2016-02-02 695:from the original on 2017-05-11 660:from the original on 2015-06-28 609:from the original on 2018-10-26 573:from the original on 2018-10-25 512:from the original on 2018-10-26 13: 1: 382: 555:Kate Tringham (2018-10-24). 7: 542:. Dan McGeer, VARD Marine. 10: 774: 688:South Atlantic News Agency 653:South Atlantic News Agency 562:Jane's Navy International 544:Retrieved 2018-10-28. 342:Jane's Navy International 140: 33: 29: 141:General characteristics 403:ASMAR Talcahuano 114 331:Almirante Ă“scar Viel 299:Aviation facilities 723:Maritime Executive 538:2018-10-28 at the 443:. 23 December 2022 365:Maritime Executive 354:(28 km/h). 306: 305: 239:diesel generators 16:(Redirected from 765: 742: 741: 736: 735: 714: 708: 707: 701: 700: 679: 673: 672: 666: 665: 644: 638: 637: 634: 629: 626:Retamales said. 625: 620: 615: 614: 602:Dialogo Americas 592: 586: 585: 579: 578: 552: 546: 545: 530: 524: 523: 518: 517: 496: 479: 478: 476: 474: 459: 453: 452: 450: 448: 433: 424: 423: 421: 420: 407: 396: 376:Almirante IrĂ­zar 320:operated by the 258: 254: 236:General Electric 106:22 December 2022 48: 45: 44: 43: 27: 26: 21: 773: 772: 768: 767: 766: 764: 763: 762: 748: 747: 746: 745: 733: 731: 716: 715: 711: 698: 696: 681: 680: 676: 663: 661: 646: 645: 641: 632: 627: 623: 618: 612: 610: 593: 589: 576: 574: 553: 549: 543: 540:Wayback Machine 531: 527: 515: 513: 498: 497: 482: 472: 470: 467:GobiernodeChile 461: 460: 456: 446: 444: 435: 434: 427: 418: 416: 398: 397: 390: 385: 256: 252: 249:Diesel-electric 231:Installed power 154:research vessel 90:US$ 217 million 46: 41: 39: 23: 22: 15: 12: 11: 5: 771: 761: 760: 744: 743: 726:. 2016-02-01. 709: 691:. 2017-05-11. 674: 656:. 2014-12-09. 639: 587: 547: 525: 508:. 2017-05-15. 505:Santiago Times 480: 454: 425: 414:S&P Global 387: 386: 384: 381: 348:Almirante Viel 337:Santiago Times 310:Almirante Viel 304: 303: 300: 296: 295: 292: 288: 287: 284: 280: 279: 278: 277: 274: 265: 261: 260: 251:; two shafts 2 246: 242: 241: 232: 228: 227: 222: 218: 217: 214: 210: 209: 206: 202: 201: 198: 194: 193: 190: 186: 185: 182: 178: 177: 176: 175: 169: 161: 157: 156: 147: 143: 142: 138: 137: 134: 130: 129: 120: 119:Identification 116: 115: 112: 108: 107: 104: 100: 99: 96: 92: 91: 88: 84: 83: 74: 70: 69: 64: 60: 59: 57:Almirante Viel 54: 50: 49: 36: 35: 31: 30: 9: 6: 4: 3: 2: 770: 759: 756: 755: 753: 740: 729: 725: 724: 719: 713: 706: 694: 690: 689: 684: 678: 671: 659: 655: 654: 649: 643: 636: 608: 604: 603: 598: 591: 584: 572: 568: 564: 563: 558: 551: 541: 537: 534: 529: 522: 511: 507: 506: 501: 495: 493: 491: 489: 487: 485: 469:. 3 July 2024 468: 464: 458: 442: 438: 432: 430: 415: 411: 406: 404: 395: 393: 388: 380: 378: 377: 371: 367: 366: 361: 358: 355: 353: 349: 345: 343: 339: 338: 333: 332: 327: 323: 319: 316: 315:Polar Class 5 312: 311: 301: 298: 297: 293: 290: 289: 285: 282: 281: 275: 272: 268: 267: 266: 263: 262: 250: 247: 244: 243: 240: 237: 233: 230: 229: 226: 225:Polar Class 5 223: 220: 219: 215: 212: 211: 207: 204: 203: 199: 196: 195: 191: 188: 187: 183: 180: 179: 174: 170: 168: 164: 163: 162: 159: 158: 155: 151: 148: 145: 144: 139: 135: 132: 131: 128: 124: 121: 118: 117: 113: 110: 109: 105: 102: 101: 97: 94: 93: 89: 86: 85: 82: 78: 75: 72: 71: 68: 65: 62: 61: 58: 55: 52: 51: 37: 32: 28: 19: 738: 732:. Retrieved 721: 712: 703: 697:. Retrieved 686: 677: 668: 662:. Retrieved 651: 642: 617: 611:. Retrieved 600: 590: 581: 575:. Retrieved 560: 550: 528: 520: 514:. Retrieved 503: 471:. Retrieved 466: 457: 445:. Retrieved 441:PolarJournal 440: 417:. Retrieved 409: 402: 375: 363: 362: 359: 356: 347: 346: 335: 329: 325: 322:Chilean Navy 309: 308: 307: 181:Displacement 165:10,044  111:Commissioned 67:Chilean Navy 56: 447:25 December 326:Antartica 1 184:13,000 tons 171:3,813  114:3 July 2024 95:Yard number 18:Antartica 1 734:2018-10-25 699:2018-10-25 664:2018-10-25 613:2018-10-25 577:2018-10-25 516:2018-10-25 419:2018-10-28 405:(9843948)" 383:References 318:icebreaker 245:Propulsion 150:Icebreaker 136:In service 123:IMO number 81:Talcahuano 635:he added. 622:underway, 374:ARA  370:Argentina 291:Endurance 221:Ice class 752:Category 728:Archived 693:Archived 658:Archived 607:Archived 571:Archived 536:Archived 510:Archived 103:Launched 63:Operator 583:region. 410:Sea-web 294:60 days 205:Draught 160:Tonnage 127:9843948 125::  73:Builder 34:History 473:5 July 257:  253:  189:Length 133:Status 705:Viel. 633:' 628:' 624:' 619:' 567:Paris 352:knots 313:is a 283:Range 271:knots 264:Speed 213:Depth 77:ASMAR 47:Chile 475:2024 449:2022 197:Beam 146:Type 87:Cost 53:Name 372:'s 269:16 173:DWT 98:114 754:: 737:. 720:. 702:. 685:. 667:. 650:. 616:. 605:. 599:. 580:. 569:. 565:. 559:. 519:. 502:. 483:^ 465:. 439:. 428:^ 412:. 408:. 391:^ 379:. 167:GT 152:, 79:, 477:. 451:. 422:. 401:" 255:Ă— 20:)

Index

Antartica 1
Chilean Navy
ASMAR
Talcahuano
IMO number
9843948
Icebreaker
research vessel
GT
DWT
Polar Class 5
General Electric
diesel generators
Diesel-electric
knots
Polar Class 5
icebreaker
Chilean Navy
Almirante Ă“scar Viel
Santiago Times
Jane's Navy International
knots
Maritime Executive
Argentina
ARA Almirante IrĂ­zar


"ASMAR Talcahuano 114 (9843948)"
S&P Global

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.

↑